当前分类: IBM(000-106)
问题:单选题A customer is installing an HMC-managed Power 720 with two partitions, one for Production the other for Testing. They plan to use the Testing partition only occasionally and want to minimize hardware. Which of the following meets these requirements?()A...
查看答案
问题:单选题On a POWER7 processor based server what is the minimum number of cores used by the Hypervisor to run four threads?()A 1B 2C 4D 8...
问题:单选题A customer would like to create a shared processor partition with 16 virtual processors. What is the minimum number of processing units required in the partition profile?()A 0.80B 0.16C 1.60D 0.10...
问题:单选题What is a design consideration when using existing PCIe I/O drawers in a maximum bandwidth/throughput configuration on a new Power 750 system?()A The new system requires 1 installed processor card for the GX++ bus adapterB The new system requires a min...
问题:单选题Which of the following provide for higher system availability on a single CEC Power 770 or Power 780?()A Redundant system clockB Redundant service processorC POWER7 cores include redundant L3 cachesD Main memory DIMMs contain an extra DRAM chip for imp...
问题:单选题What describes the difference between NPIV and vSCSI in the way fibre-channel attached disk and tape are presented when VIO Server is used?()A NPIV presents Virtual HBA addresses and vendor specific information for disk and tape devices.vSCSI presents ...
问题:单选题A customer wants to migrate their existing compute-intensive POWER6 570 to a Power 770. Which of their existing I/O adapters can be migrated to Power 770 enclosures?()A PCIe adaptersB PCI-X adaptersC PCI-X andPCIe adaptersD PCI, PCI-X andPCIe adapters...
问题:单选题A customer has a 4-core POWER6 570 with 4 partitions and a 2-port 1Gbps Integrated Virtual Ethernet (IVE) Adapter. They are having problems with throughput on the Ethernet adapter and want to improve performance. Which of the following solutions will h...
问题:单选题A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()A PowerVM Standard E...
问题:单选题A customer has a 4-core POWER6 570 with 4 partitions and a 2-port 1Gbps Integrated Virtual Ethernet (IVE) Adapter. They are having problems with throughput on the Ethernet adapter and want to improve performance. Which of the following solutions will ...
问题:单选题A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing lim...
问题:单选题When considering migrating a POWER6 server with PCI-X and PCIe adapters to a Power 720, which statement is true?()A PCIe adapters are supported only in I/O drawersB PCI-X adapters are supported in both the CEC and in I/O drawersC PCI-X adapters are sup...
问题:单选题A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server. Which action will reduce the potentia...
问题:单选题A customer is evaluating PowerVM capabilities for dynamically allocating resources without rebooting LPARs. Which features of PowerVM support the customer requirement?()A CoD and PCI hot-plugB DLPAR and Active Memory SharingC Hot node add and hot node ...
问题:单选题A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools. What is the minimum PowerVM E...
问题:单选题What are key benefits of IBM Systems Director Standard Edition?()A Backup data Manage problems Monitor network systemB Report problems Manage servers and virtual environment Monitor the network C Monitor system health and network Install and manage AIX...
问题:单选题A customer is planning on having a single Virtual I/O Server (VIOS) configuration in a Power 750. They haveselected a 4-port 1Gb Integrated Virtual Ethernet (IVE). There will be no other network cards installed in the system. One IVE logical port will ...