70 Risk Event Status is defined as _____ .A. Risk Probability x Amount At Stake.B. the severity of the consequences.C. how likely the event is to occur with risk.D. (Cost + Benefit + Business Risk) / Insurable Risk.E. B and C

题目

70 Risk Event Status is defined as _____ .

A. Risk Probability x Amount At Stake.

B. the severity of the consequences.

C. how likely the event is to occur with risk.

D. (Cost + Benefit + Business Risk) / Insurable Risk.

E. B and C


相似考题
参考答案和解析
正确答案:A
更多“70 Risk Event Status is defined as _____ .A. Risk Probability x Amount At Stake.B. the severity of the consequences.C. how likely the event is to occur with risk.D. (Cost + Benefit + Business Risk) / Insurable Risk.E. B and C”相关问题
  • 第1题:

    Risk event probability is defined as:

    A the total number of possible events divided into the expectations or frequency of the risk event

    B the number of times the risk event may occur

    C the fraction of the total project tasks which may be affected by the risk event

    D the total number of possible events divided into the consequences of the risk event.

    E A and B


    正确答案:A

  • 第2题:

    Total Project Risk:

    A should not be calculated for small projects

    B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

    C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

    D A and B

    E A and C


    正确答案:C

  • 第3题:

    Monte Carlo simulation:

    A Was originally developed by Dr. Carlo

    B Is a European technique for assessing project risks

    C assumes the future risk events will occur at random according to predetermined probability distributions

    D is a technique to stimulate create risk event resolution

    E A, B and C only


    正确答案:C

  • 第4题:

    15 Total project risk can be defined as:

    A. the sum of the probabilities of project risks events times the sum of consequences of those risks

    B. the sum of the products of each project risk event times its consequences

    C. the sum of the consequences of all project risk events

    D. the sum of the probabilities of all project risk events

    E. 1 - the sum of the probabilities of all project risk events


    正确答案:B

  • 第5题:

    84 Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?

    A. liability loss

    B. direct property loss

    C. profit loss

    D. personnel-related loss

    E. B and C


    正确答案:C

  • 第6题:

    125 In Project Risk Management, Risk Response may include actions to:

    A. reduce the probability of risk events

    B. change the scope, budget, schedule or quality specifications of the project

    C. reduce the consequences or severity of impacts of a potential risk event

    D. A and C

    E. All of the above


    正确答案:E

  • 第7题:

    81 Amount at Stake is the _____ .

    A. function of planned time/real time project costs.

    B. risk identified in successful project completions.

    C. (Standard Project Deviation + Expected Costs)/6

    D. cost of investment loss + least cost to restore status quo.

    E. inherent risk at conception altered by standard project deviations


    正确答案:D

  • 第8题:

    170 Project Risk _____ .

    A. should not be calculated for small projects.

    B. is the probability of each risk event minus the sum of the consequences of potential risk events.

    C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.

    D. cannot be quantified for first time projects.

    E. B or D


    正确答案:C

  • 第9题:

    152 Risk Event Status is defined as _____ .

    A. Risk Probability x Amount At Stake.

    B. the severity of the consequences.

    C. how likely the event is to occur with risk.

    D. (Cost + Benefit + Business Risk) / Insurable Risk.

    E. B and C


    正确答案:A

  • 第10题:

    ______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.

    A.Quantitative Risk Analysis

    B.Qualitative Risk Analysis

    C.Enterprise Environmental Factors

    D.Risk Management Plan


    正确答案:B
    解析:定性风险分析利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。
    选项A是定量风险分析,选项B是定性风险分析,选项C是企业环境因素,选项D是风险管理计划。故B是正确的。

  • 第11题:

    ( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.

    A.Quantitative Risk Analysis
    B.Qualitative Risk Analysis
    C.Enterprise Environmental Factors
    D.Risk Management Plan

    答案:B
    解析:
    翻译:(71)利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。A.定量风险分析 B.定性风险分析 C.企业环境因素 D.风险管理计划

  • 第12题:

    单选题
    ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.
    A

    Quantitative Risk Analysis

    B

    Qualitative Risk Analysis

    C

    Enterprise Environmental Factors

    D

    Risk Management Plan


    正确答案: B
    解析: 参考答案:B

  • 第13题:

    In Project Risk Management, Risk Response may include actions to:

    A reduce the probability of risk events

    B change the scope, budget, schedule or quality specifications of the project

    C reduce the consequences or severity of impacts of a potential risk event

    D A and C

    E All of the above.


    正确答案:E

  • 第14题:

    Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?

    A liability loss

    B direct property loss

    C profit loss

    D personnel-related loss

    E B and C


    正确答案:C

  • 第15题:

    Total project risk can be defined as:

    A the sum of the probabilities of project risks events times the sum of consequences of those risks

    B the sum of the products of each project risk event times its consequences

    C the sum of the consequences of all project risk events

    D the sum of the probabilities of all project risk events

    E 1 - the sum of the probabilities of all project risk events.


    正确答案:B

  • 第16题:

    27 Monte Carlo simulation:

    A. Was originally developed by Dr. Carlo

    B. Is a European technique for assessing project risks

    C. assumes the future risk events will occur at random according to predetermined probability distributions

    D. is a technique to stimulate create risk event resolution

    E. A, B and C only


    正确答案:C

  • 第17题:

    122 Total Project Risk:

    A. should not be calculated for small projects

    B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

    C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

    D. A and B

    E. A and C


    正确答案:C

  • 第18题:

    144 Risk event probability is defined as:

    A. the total number of possible events divided into the expectations or frequency of the risk event

    B. the number of times the risk event may occur

    C. the fraction of the total project tasks which may be affected by the risk event

    D. the total number of possible events divided into the consequences of the risk event.

    E. A and B


    正确答案:A

  • 第19题:

    137 Range estimating in determining cost risk probabilities requires _____ .

    A. an amount of financial exposure.

    B. risks and opportunities ranked in order of bottom line importance

    C. contingency requirements for expected level of confidence

    D. probability of cost overrun occurrences

    E. All of the above


    正确答案:E

  • 第20题:

    In Project Risk Management, Risk Response may include actions to:

    A. reduce the probability of risk events

    B. change the scope, budget, schedule or quality specifications of the project

    C. reduce the consequences or severity of impacts of a potential risk event

    D. A and C

    E. All of the above


    正确答案:E

  • 第21题:

    ●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.

    (71)

    A. Quantitative Risk Analysis

    B. Qualitative Risk Analysis

    C. Enterprise Environmental Factors

    D. Risk Management Plan


    正确答案:B

  • 第22题:

    ● Project()is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality()A. risk B. problem C. result D. data


    正确答案:A
    项目风险是一种不确定的事件或条年,一旦发生,至少会对一个项目目标,比如时间、成本、范围或质量造成正面或负面的影响。

  • 第23题:

    ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.

    • A、Quantitative Risk Analysis
    • B、Qualitative Risk Analysis
    • C、Enterprise Environmental Factors
    • D、Risk Management Plan

    正确答案:B