更多“Fixed Price contracts place more risk on the:A ownerB buyerC sellerD contractorE C or D”相关问题
  • 第1题:

    Fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on the:

    A Buyer

    B Third party

    C Contractor

    D All of the above

    E None of the above


    正确答案:C

  • 第2题:

    Which of the following types of contracts allows the owner to transfer risk to the contractor:

    A cost plus incentive fee

    B cost sharing

    C firm fixed price

    D cost plus fixed fee

    E performance guarantees


    正确答案:C

  • 第3题:

    Which of the following is equivalent to a lump sum contract:

    A fixed price contract

    B price fixing contract

    C purchase order

    D All of the above.

    E B and C only


    正确答案:A

  • 第4题:

    Which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk?

    A Cost Plus Incentive Fee

    B Cost Plus Percentage of Costs

    C Cost Plus Fixed Fee

    D Firm Fixed Price

    E Firm Fixed Price Plus Incentive


    正确答案:E

  • 第5题:

    73 Fixed Price contracts place more risk on the:

    A. owner

    B. buyer

    C. seller

    D. contractor

    E. C or D


    正确答案:E

  • 第6题:

    103 Which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk?

    A. Cost Plus Incentive Fee

    B. Cost Plus Percentage of Costs

    C. Cost Plus Fixed Fee

    D. Firm Fixed Price

    E. Firm Fixed Price Plus Incentive


    正确答案:E

  • 第7题:

    51 Which of the following types of contracts allows the owner to transfer risk to the contractor:

    A. cost plus incentive fee

    B. cost sharing

    C. firm fixed price

    D. cost plus fixed fee

    E. performance guarantees


    正确答案:C

  • 第8题:

    172 Fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on the:

    A. Buyer

    B. Third party

    C. Contractor

    D. All of the above

    E. None of the above


    正确答案:C

  • 第9题:

    98 In which of the following is the cost of risk hidden by the contractor?

    A. Firm Fixed Price Contract

    B. Fixed Price Plus Incentive

    C. Cost Plus Fixed Price

    D. Cost Plus Percentage of Cost

    E. A and B


    正确答案:D

  • 第10题:

    90 Fixed-price contracts place more risk on the _____ .

    A. owner

    B. contractor

    C. seller

    D. B and C

    E. All of the above


    正确答案:D

  • 第11题:

    If the market price of the financial instrument concerned should be higher on the delivery date than the price agreed in the financial future contract ______ will make a profit.

    A.the seller

    B.the buyer

    C.the broker

    D.the dealer


    正确答案:B
    解析:第一段第二句Under such a contract, if the market price…the buyer can obtain a price or yield which is settled at the time the contract is agreed,意指在交易日,如果金融工具的市场价格高于合同约定价格,或者说市场收益率低于合同收益率,卖方有义务弥补差价,买方则获得在合约中约定好的价格或收益。南此可见,买方受益。或者可以根据后面举的情况相反例子,反过来推断出买方受益。

  • 第12题:

    单选题
    What has happened to the SUV as to the third paragraph?
    A

    It has more advantages when the gas price is rising.

    B

    There is a selling dropping of all sizes of it.

    C

    Its place is replacing by more economical cars.

    D

    Its best-selling time is coming.


    正确答案: A
    解析:
    事实细节题。由题干定位至第三段。首句中rising gas prices finally seem to be driving consumers toward more economical choices—and ringing out the era of the SUV提到,上涨的油价最终可能迫使消费者倾向于更加经济的选择,这意味着the SUV时代的结束,故A错,C正确;由最后两句可知SUVs和轻型货车销量下降,但是末句提到smaller SUVs like the Toyota RAV4 came on strong,排除B;由首句中ringing out the era of the SUV 可知the SUV 的时代将结束,故D错。

  • 第13题:

    Cost Reimbursable contracts are equivalent to:

    A Cost plus contracts

    B Fixed plus contracts

    C Progress payment contracts

    D Back charge contracts

    E None of the above.


    正确答案:A

  • 第14题:

    In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

    A unit price

    B cost plus incentive fee

    C cost plus fixed fee

    D firm fixed price

    E B and D only


    正确答案:D

  • 第15题:

    Which of the following types of contracts is equivalent to a cost plus contract:

    A Fixed firm price

    B Cost reimbursable

    C Fixed price plus incentive fee

    D progress payments

    E All of the above.


    正确答案:B

  • 第16题:

    Cost Plus Percentage of Cost contracts are more desirable for the:

    A owner

    B buyer

    C seller

    D contractor

    E C or D


    正确答案:E

  • 第17题:

    81 Cost Plus Percentage of Cost contracts are more desirable for the:

    A. owner

    B. buyer

    C. seller

    D. contractor

    E. C or D


    正确答案:E

  • 第18题:

    125 Which of the following types of contracts is equivalent to a cost plus contract:

    A. Fixed firm price

    B. Cost reimbursable

    C. Fixed price plus incentive fee

    D. progress payments

    E. All of the above


    正确答案:B

  • 第19题:

    93 The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .

    A. Is accomplished by paying the actual costs to the contractor.

    B. Is accomplished by paying the contractor for his costs plus a fixed fee (profit).

    C. Is an undisclosed contingency in the contractor's bid.

    D. Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.

    E. B and C


    正确答案:C

  • 第20题:

    8 Fixed-price contracts place more risk on the _____ .

    A. owner

    B contractor

    C. seller

    D. B and C

    E. All of the above


    正确答案:D

  • 第21题:

    132 Which of the following contract types has the highest risk to the contractor:

    A. Firm fixed price (FFP)

    B. Time and material (T&M)

    C. Cost plus fixed fee (CPFF)

    D. Cost plus incentive fee (CPIF)

    E. A and B only


    正确答案:A

  • 第22题:

    In fixed price contract which of the following holds true? (72).

    A.More risk is placed on the buyer

    B.If the amount of the contract is exceeded the seller is not obligated to perform. further unless the buyer increases the funds

    C.The seller agrees to perform. a service or furnish supplies at the established contract price

    D.The seller agrees to use his best effort to fulfill the contract within the estimated contract amount


    正确答案:C

  • 第23题:

    何谓市场营销中的4P()

    • A、Product,Price,Place,Promotion
    • B、Product,Public,Place,Promotion
    • C、Please,Price,Place,Promotion
    • D、Product,Price,Place,POP

    正确答案:A