● Which of the following are included as part of a scope statement?
A Project justification
B Project deliverables
C Project objectives
D All of the above
E B and C
第1题:
118 A common way by which executives provide the project manager with written authority is through:
A. A common job description for all project managers
B. An appointment letter
C. A project charter
D. All of the above
E. B and C only
第2题:
146 Which of the following are included as part of a scope statement?
A. Project justification
B. Project deliverables
C. Project objectives
D. All of the above
E. B and C
第3题:
● The use of the project reports:
A are not necessary on small projects
B provides a means whereby various levels of authority can judge project performance
C provides insight into project areas and the effectiveness of the control systems
D All of the above
E B and C
第4题:
● (74) is primarily concerned with defining and controlling what is and is not included in the project.
(74)
A. Project Time Management
B. Project Cost Management
C. Project Scope management
D. Project Communications Management
第5题:
( ) describes, in detail, the project’ s deliverables and the work required to create those deliverables.
A.Product scope description B.Project objectives C.Product specification D.The project scope statement
第6题:
The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter
第7题:
● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)
(74)
A. Scope Planning
B. Scope Verification
C. Scope Change Control
D. Scope Definition
第8题:
The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.
A.project charter
B.project scope goal
C.project budget
D.project scope statement
第9题:
第10题:
第11题:
第12题:
()describes, in detail, the project’s deliverables and the work required to create those deliverables.
第13题:
88 The scope statement provides
A. A basis for future decisions about a project.
B. A baseline to accomplish verification measures.
C. A baseline to evaluate potential scope changes.
D. All of the above
E. B and C only
第14题:
151 Sources for data on activity durations and resource requirements can be gathered from which of the following:
A. Past project records (historical data)
B. Commercial techniques (standard practices, rules of thumb)
C. Past project team members knowledge (experience, oldtimers)
D. All of the above
E. A and C only
第15题:
● Sources for data on activity durations and resource requirements can be gathered from which of the following:
A Past project records (historical data)
B Commercial techniques (standard practices, rules of thumb)
C Past project team members knowledge (experience, oldtimers)
D All of the above
E A and C only
第16题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement
第17题:
______describes,in detail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement
第18题:
● ()is primarily concerned with defining and concerning what is and is not included in the project.()A. Project Time ManagementB. Project Cost ManagementC. Project Scope ManagementD. Project Communications Management
第19题:
The (75) describes,in detail,the project's deliverables and the work required to create those deliverables.
A.product specification
B.project requirement
C.project charter
D.project scope statement
第20题: