Sources for data on activity durations and resource requirements can be gathered from which of the following:A.Past project records (historical data)B.Commercial techniques (standard practices, rules of thumb)C.Past project team members knowledge (experie

题目

Sources for data on activity durations and resource requirements can be gathered from which of the following:

A.Past project records (historical data)

B.Commercial techniques (standard practices, rules of thumb)

C.Past project team members knowledge (experience, oldtimers)

D.All of the above

E.A and C only


相似考题
参考答案和解析
正确答案:D
D
更多“Sources for data on activity durations and resource requirements can be gathered from which of the following:A.Past project records (historical data)B.Commercial techniques (standard practices, rules of thumb)C.Past project team members knowledge (experie”相关问题
  • 第1题:

    By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

    A Significantly reduce project risks

    B eliminate project risks

    C provide a rational basis for better decision making

    D identify risks, their impact(s), and any appropriate responses

    E None of the above.


    正确答案:B

  • 第2题:

    4 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A. Matrix

    B Pure project

    C. Project coordinator

    D. Project expediter

    E. Classical/traditional


    正确答案:B

  • 第3题:

    86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A. Matrix

    B. Pure project

    C. Project coordinator

    D. Project expediter

    E. Classical/traditional


    正确答案:B

  • 第4题:

    151 Sources for data on activity durations and resource requirements can be gathered from which of the following:

    A. Past project records (historical data)

    B. Commercial techniques (standard practices, rules of thumb)

    C. Past project team members knowledge (experience, oldtimers)

    D. All of the above

    E. A and C only


    正确答案:D

  • 第5题:

    ● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.

    (74)

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    试题(74)分析
        项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。
    参考答案
        (74)A

  • 第6题:

    ●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).

    (71)

    A.periodic project reports, periodic visits to the customer, and telephonic exchanges

    B.subordinates, project team members, and the project sponsor

    C.one-time reports, weekly reports, and monthly reports

    D.the telephone, facsimile, and data transmission


    正确答案:A

  • 第7题:

    ( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

    A.Parametric

    B.Analogous

    C.Three-point

    D.Expert judgment


    正确答案:B

  • 第8题:

    ()is a technique for estimating the duration or cost of activity or a projecy using historical data orm a similar activity or project.

    A.Analogous estimating
    B.Parametric estimating
    C.Three-Point estmating
    D.Bottom-Up estimating

    答案:A
    解析:
    本题翻译:
    ()是一种使用来自类似活动或项目的历史数据来估计活动或项目的持续时间或成本的技术。
    A.类比估计
    B.参数估计
    C.三点估算
    D.底部估计
    成本估算的方法中没有D选项,D选项属于迷惑选项。
    参数估算是利用历史数据中的统计关系和其他变量来估算成本。
    三点估算是利用三种估算值来界定活动成本。

  • 第9题:

    Which of the following is the main feature of an OLTP application?()

    • A、Summarized queries
    • B、Granular transactions
    • C、Voluminous historical data
    • D、Heterogeneous data sources

    正确答案:B

  • 第10题:

    The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()

    • A、Data flow model
    • B、The project critical path
    • C、Resource loading chart
    • D、WBS (Work Breakdown Structure)

    正确答案:B

  • 第11题:

    A WebLogic team is developing an enterprise application from their desktop WebLogic environment. All development systems are connected to the same eight data sources for testing. As a WebLogic Administrator supporting this team, which two actions should you perform to free the developers from creating and configuring all the data sources on their desktop WebLogic environment?()

    • A、Provide the team with a WebLogic domain template with the testing data sources configured.
    • B、Provide the development team with a preconfigured domain archive file.
    • C、Provide the development team with the [datasource] -jdbc.xml file to overwrite their local copy.
    • D、Create the data sources on behalf each of the developer.
    • E、Provide the development team with WLST scripts to create and configure the testing data  sources.

    正确答案:E

  • 第12题:

    单选题
    You are designing a Windows Azure application that will use Windows Azure Table storage. The application will allow teams of users to collaborate on projects.  Each user is a member of only one team. You have the following requirements:   - Ensure that each user can efficiently query records related to his or her team’s projects.  - Minimize data access latency.   You need to recommend an approach for partitioning table storage entities. What should you recommend? ()
    A

     Partition by user.

    B

     Partition by team.

    C

     Partition by project.

    D

     Partition by the current date.


    正确答案: B
    解析: 暂无解析

  • 第13题:

    156 Expectancy theory as applied to project management implies that:

    A. The team will work the hardest on those goals that are clearly explained by the project manager

    B. The more rewards that the project manager provides, the better the performance of the team

    C. Team members will work hardest for those project goals that also bring satisfaction to personal goals

    D. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members E. None of the above


    正确答案:C

  • 第14题:

    118 Which of the following would most likely not be an essential objective of a project team kick-off meeting

    A. Create a project technology master plan

    B. Get team members to know one another

    C. Identify project problem areas

    D. Obtain individual and group commitments

    E. Identify the project coordinator


    正确答案:A

  • 第15题:

    78 Which of the following can the project manager use as a means of measuring project team effectiveness?

    A. Absenteeism

    B. Sponsor-approved salary increases

    C. Efficiency of the team

    D. Turnover of personnel

    E. Grievances


    正确答案:C

  • 第16题:

    ● Sources for data on activity durations and resource requirements can be gathered from which of the following:

    A Past project records (historical data)

    B Commercial techniques (standard practices, rules of thumb)

    C Past project team members knowledge (experience, oldtimers)

    D All of the above

    E A and C only


    正确答案:D

  • 第17题:

    Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

  • 第18题:

    Which of the following is the main feature of an OLTP application?()

    A.Summarized queries

    B.Granular transactions

    C.Voluminous historical data

    D.Heterogeneous data sources


    参考答案:B

  • 第19题:

    The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project.The project manager maintains this link through( ).

    A.periodic project reports,periodic visits to the customer,and telephonic exchanges
    B.subordinates,project team members,and the project sponsor
    C.one-time reports,weekly reports,and monthly reports
    D.the telephone,facsimile,and data transmission

    答案:A
    解析:
    项目经理必须保持一个有效的沟通,项目经理保持这个环节,通过与客户的项目定期报告,定期走访客户和电话交流。

  • 第20题:

    ( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

    A.Parametric
    B.Analogous
    C.Three-point
    D.Expert judgment

    答案:B
    解析:
    类比估计是一项使用类似的活动或项目的历史数据,来估计活动的时间或成本的技术。 (73) A.参数 B.类比 C.三点 D.专家判断

  • 第21题:

    Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

    • A、crashing the schedule
    • B、performing resource leveling
    • C、conducting reverse resource allocation scheduling
    • D、utilizing the critical chain resources

    正确答案:A

  • 第22题:

    Which factor has the greatest impact on the estimated per unit labor cost for a project?()

    • A、Historical information
    • B、Use of outside vendors
    • C、Change control processes
    • D、Human resource skill level requirements

    正确答案:D

  • 第23题:

    You are designing a Windows Azure application that will use Windows Azure Table storage. The application will allow teams of users to collaborate on projects.  Each user is a member of only one team. You have the following requirements:   - Ensure that each user can efficiently query records related to his or her team’s projects.  - Minimize data access latency.   You need to recommend an approach for partitioning table storage entities. What should you recommend? ()

    • A、 Partition by user.
    • B、 Partition by team.
    • C、 Partition by project.
    • D、 Partition by the current date.

    正确答案:B