91 The best way to insure quality conformance is to _____.A. distribute the responsibility to subordinates.B. maintain total control.C. train each worker to implement the work.D. inspect quality into the project.E. None of the above

题目

91 The best way to insure quality conformance is to _____.

A. distribute the responsibility to subordinates.

B. maintain total control.

C. train each worker to implement the work.

D. inspect quality into the project.

E. None of the above


相似考题
更多“91 The best way to insure quality conformance is to _____.A. distribute the responsibility to subordinates.B. maintain total control.C. train each worker to implement the work.D. inspect quality into the project.E. None of the above”相关问题
  • 第1题:

    The best way to insure quality conformance is to _____.

    A . distribute the responsibility to subordinates.

    B . maintain total control.

    C . train each worker to implement the work.

    D . inspect quality into the project.

    E . None of the above.


    正确答案:C

  • 第2题:

    A proven effective means to insure quality conformance is to:

    A . delegate accountability to subordinates

    B . revise quality specifications to match quality measurements

    C . train workers in proper quality methods

    D . inspect quality into the product

    E . make quality a higher priority than cost or schedule


    正确答案:C

  • 第3题:

    Which of the following is closet to Deming's definition of Quality:

    A . conformance to requirements.

    B . fitness for use.

    C . continuous improvement of products and services.

    D . customer focus.

    E . All of the above.


    正确答案:C

  • 第4题:

    76 Quality may be defined as:

    A. conformance to requirements.

    B. fitness for use.

    C. continuous improvement of products and services

    D. appeal to the customer

    E. All of the above except B


    正确答案:E

  • 第5题:

    110 Which of the following is closet to Deming's definition of Quality:

    A. conformance to requirements.

    B. fitness for use.

    C. continuous improvement of products and services.

    D. customer focus.

    E. All of the above


    正确答案:C

  • 第6题:

    5 Japanese quality control has improved dramatically in the last 30 years for all of the following reasons except:

    A. the use of quality circles.

    B. small, continuous improvements in quality control.

    C. the use of worker suggestion systems.

    D. the use of quality control charts.

    E. focusing quality control efforts on production outputs


    正确答案:E

  • 第7题:

    132 A proven effective means to insure quality conformance is to:

    A. delegate accountability to subordinates

    B. revise quality specifications to match quality measurements

    C. train workers in proper quality methods

    D. inspect quality into the product

    E. make quality a higher priority than cost or schedule


    正确答案:C

  • 第8题:

    3 In order to achieve long-term quality improvements, management must do the following:

    A. Motivate the employees with seminars, contests, and institute programs such as "Quality Improvement' day.

    B Create a quality control department and give the head of the department ultimate responsibility for quality improvement.

    C. Implement of a formal quality control program with worker and management involvement.

    D. Establish financial incentive packages for worker.

    E. A and D


    正确答案:C

  • 第9题:

    16 Inspection of a complex project according to specifications is accomplished by _____.

    A. inspection by attributes.

    B cyclical inspection

    C. quality conformance inspection

    D. original inspection

    E. None of the above


    正确答案:C

  • 第10题:

    47 Quality control is normally performed by the _____ .

    A. QA personnel

    B. project team

    C. operating personnel

    D. project management

    E. None of the above


    正确答案:C

  • 第11题:

    185 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above


    正确答案:A

  • 第12题:

    “Cost of quality”is a project management concept that includes cost of( 73)

    A.exceedings requirements

    B.Changes to the requirements

    C.Ensuring conformance to requirements

    D.The quality control requirements


    正确答案:C

  • 第13题:

    In order to achieve long-term quality improvements, management must do the following:

    A . Motivate the employees with seminars, contests, and institute programs such as "Quality Improvement' day.

    B . Create a quality control department and give the head of the department ultimate responsibility for quality improvement.

    C . Implement of a formal quality control program with worker and management involvement.

    D . Establish financial incentive packages for worker.

    E . A and D


    正确答案:C

  • 第14题:

    Which of the following is closest to Juran's definition of Quality:

    A . conformance to requirements.

    B . fitness for use.

    C . continuous improvement.

    D . customer focus.

    E . All of the above.


    正确答案:B

  • 第15题:

    Quality may be defined as:

    A . conformance to requirements.

    B . fitness for use.

    C . continuous improvement of products and services

    D . appeal to the customer

    E . All of the above except B


    正确答案:E

  • 第16题:

    100 The auditing function that provides feedback about the quality of output is referred to as:

    A. quality control.

    B. quality planning.

    C. quality assurance.

    D. quality improvement

    E. All of the above


    正确答案:C

  • 第17题:

    117 Which of the following is closest to Juran's definition of Quality:

    A. conformance to requirements.

    B. fitness for use.

    C. continuous improvement.

    D. customer focus.

    E. All of the above


    正确答案:B

  • 第18题:

    99 Scope management is:

    A. a project control function.

    B. employs change control.

    C. a work authorization process.

    D. considers Cost, Quality and Schedule.

    E. All of the above


    正确答案:E

  • 第19题:

    179 In the project environment, the individual ultimately responsible for quality control is:

    A. The line workers who must strive "to do things right the first time" to avoid quality problems.

    B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

    C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

    D. The project manager who has ultimate responsibility for the entire project.

    E. the customer who must ensure that he is receiving a quality product from the vendor


    正确答案:D

  • 第20题:

    9 The best way to insure quality conformance is to _____.

    A. distribute the responsibility to subordinates.

    B maintain total control.

    C. train each worker to implement the work.

    D. inspect quality into the project.

    E. None of the above


    正确答案:C

  • 第21题:

    39 Quality and _____ are directly related.

    A. productivity

    B. cost overruns

    C. scope control

    D. Pareto diagram

    E. None of the above.


    正确答案:A

  • 第22题:

    69 Non-conformance penalties are a form. of _____.

    A. quality incentive

    B. risk sharing

    C. contract negotiations

    D. quality assurance programs

    E. None of the above


    正确答案:C

  • 第23题:

    79 Proper implementation of project management will guarantee that:

    A. Budgets will be met.

    B. Schedules will be adhered to.

    C. Quality/performance will be met.

    D. The project will be a success.

    E. None of the above


    正确答案:E