更多“Non-conformance penalties are a form. of _____.A . quality incentiveB . risk sharingC . contract negotiationsD . quality assurance programsE . None of the above.”相关问题
  • 第1题:

    Quality control is normally performed by the _____ .

    A . QA personnel

    B . project team

    C . operating personnel

    D . project management

    E . None of the above.


    正确答案:C

  • 第2题:

    Inspection of a complex project according to specifications is accomplished by _____.

    A . inspection by attributes.

    B . cyclical inspection

    C . quality conformance inspection

    D . original inspection

    E . None of the above.


    正确答案:C

  • 第3题:

    The Risk of NOT meeting project quality objectives:

    A . can be minimized through continuous monitoring.

    B . considered a long term risk.

    C . will be reflected in the "in-service" life of the product or service.

    D . B and C

    E . All of the above.


    正确答案:E

  • 第4题:

    The Quality Risk _____ .

    A is minimized through continuous monitoring.

    B is considered a long term risk.

    C will be reflected in the in-service life of the project result.

    D B and C

    E All of the above.


    正确答案:E

  • 第5题:

    100 The auditing function that provides feedback about the quality of output is referred to as:

    A. quality control.

    B. quality planning.

    C. quality assurance.

    D. quality improvement

    E. All of the above


    正确答案:C

  • 第6题:

    69 Non-conformance penalties are a form. of _____.

    A. quality incentive

    B. risk sharing

    C. contract negotiations

    D. quality assurance programs

    E. None of the above


    正确答案:C

  • 第7题:

    ● Project tradeoffs are usually made by comparing _____ and constraints.

    A Time, cost, and quality

    B Time, risk, and quality

    C Risk, quality, and manpower availability

    D Cost, quality, and technical performance

    E Cost, quality, and risk


    正确答案:D

  • 第8题:

    ● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

    (73)

    A. Quality assurance (QA)

    B. Quality planning

    C. Quality control (QC)

    D. Quality costs


    正确答案:A

  • 第9题:

    Which of the following is not part of the quality assurance process?(73)

    A.Operational definitions

    B.Quality policy

    C.Quality audits

    D.Quality improvement


    正确答案:B
    解析:A、C、D都是质量过程中重要内容,只是B不是。

  • 第10题:

    ● Which of the following is not part of the quality assurance process?(73)

    (73)

    A.Operational definitions

    B.Quality policy

    C.Quality audits

    D.Quality improvement


    正确答案:B

  • 第11题:

    ()is the application of planned,systematic quality activities to ensure thatthe project will employ all processes needed to meet requirements.

    A.Quality assurance(QA)
    B.Quality planning
    C.Quality control(QC)
    D.Quality costs

    答案:A
    解析:
    质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。质量成本是指为满足质量要求所付出的主要成本。质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项 A 是质量保证(QA),选项B 是质量计划,选项 C 是质量控制(QC),选项 D 是质量成本。因此应选择 A。

  • 第12题:

    Quality management has four main components:quality planning .,quality assurance.,quality control and quality( ).

    A.improvement
    B.change
    C.spiral
    D.evolution

    答案:A
    解析:
    包括四个主要环节:质量计划、质量保证、质量控制和过程改进。A. 改进 B.变更 C.升级 D.进化

  • 第13题:

    Quality and _____ are directly related.

    A . productivity

    B . cost overruns

    C . scope control

    D . Pareto diagram

    E . None of the above.


    正确答案:A

  • 第14题:

    The best way to insure quality conformance is to _____.

    A . distribute the responsibility to subordinates.

    B . maintain total control.

    C . train each worker to implement the work.

    D . inspect quality into the project.

    E . None of the above.


    正确答案:C

  • 第15题:

    The auditing function that provides feedback about the quality of output is referred to as:

    A . quality control.

    B . quality planning.

    C . quality assurance.

    D . quality improvement

    E . All of the above.


    正确答案:C

  • 第16题:

    In Project Risk Management, Risk Response may include actions to:

    A reduce the probability of risk events

    B change the scope, budget, schedule or quality specifications of the project

    C reduce the consequences or severity of impacts of a potential risk event

    D A and C

    E All of the above.


    正确答案:E

  • 第17题:

    39 Quality and _____ are directly related.

    A. productivity

    B. cost overruns

    C. scope control

    D. Pareto diagram

    E. None of the above.


    正确答案:A

  • 第18题:

    72 Project trade-offs vary between

    A. risk, cost and schedule.

    B. direct cost, indirect cost, and resource availability

    C. quality, schedule and time

    D. cost, quality and schedule

    E. contract terms, scope and budget


    正确答案:D

  • 第19题:

    ● Proper implementation of project management will guarantee that:

    A Budgets will be met.

    B Schedules will be adhered to.

    C Quality/performance will be met.

    D The project will be a success.

    E None of the above.


    正确答案:E

  • 第20题:

    ● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs


    正确答案:A
    质量保证是一项有计划的、系统的质量活动,以确保项目的所有过程达到并符合要求。

  • 第21题:

    Quality management ensures that an organization , It has foor main components; quality planning,quality assurance. Quality control and quality ( )

    A.improvement

    B.change

    C.spiral

    D.evolution


    正确答案:A

  • 第22题:

    ( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

    A.Quality assurance(QA)
    B.Quality planning
    C.Quality control(QC)
    D.Quality costs

    答案:A
    解析:
    质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。
    质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
    质量成本是指为满足质量要求所付出的主要成本。
    质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。因此应选择A。

  • 第23题:

    Quality?mangement ensures that an organization,product or service is consitent.It has four main components;quality planing,quality assurance( )and quatily improvenment.

    A.quality obiective
    B.quality policy
    C.quality control
    D.quality system

    答案:C
    解析: