更多“Quality and _____ are directly related.A.productivityB.cost overrunsC.scope controlD.Paret ”相关问题
  • 第1题:

    ● Project tradeoffs are usually made by comparing _____ and constraints.

    A Time, cost, and quality

    B Time, risk, and quality

    C Risk, quality, and manpower availability

    D Cost, quality, and technical performance

    E Cost, quality, and risk


    正确答案:D

  • 第2题:

    While teaching, we should keep our clas running smoothly and

    A.thoroughly
    B.efficiently
    C.speedily
    D.directly

    答案:B
    解析:
    考查副词辨析。句意为“教学过程中,我们应该保持课堂活动流畅而又__________地进行”。thoroughly意为“彻底地”,efficiently意为“高效地”,speedily意为“迅速地”,directly意为“直接地”。根据句意,故选B。

  • 第3题:

    汉译英:“数量;质量”,正确的翻译为( )。
    A. quality ; quarantine B. quantity ; quarantine
    C. quality ; quantity D. quantity ; quality


    答案:D
    解析:

  • 第4题:

    It is___________to?stare?directly?at?the?sun

    A.harmful

    B.harmless

    C.comfortable

    D.safe


    正确答案:A

  • 第5题:

    While teaching, we should keep our class running smoothly and ________.

    A.thoroughly
    B.efficiently
    C.speedily
    D.directly

    答案:B
    解析:
    本题考查副词辨析
    B选项,句意为“教学过程中,我们应该保持课堂活动流畅而又_______地进行”。efficiently “高效地”, 综上,B选项正确。
    A选项,thoroughly “彻底地”,故排除。
    C选项,speedily“迅速地”,故排除。
    D选项,directly“直接地”,故排除。
    故正确答案为B 项。

  • 第6题:

    ()are?those?costs?that?cannot?be?directly?traced?to?a specific?project?and?therefore?will?be?accumulated?and allocated?equitably?over?multiple?projects?by?some?approved and?documented?accounting?procedure.

    A.Direct costs
    B.Operation costs
    C.Indirect costs
    D.Implement costs

    答案:C
    解析:
    本题翻译:
    ()是指不能直接追溯到特定项目的成本,因此将通过一些批准和记录的会计程序在多个项目上平均累计和分配。
    A.直接成本B.运营成本C.间接成本D.实施成本
    本题考查成本的分类,不能直接的就可以理解为间接,间接成本:来自一般管理费用科目或几个项目共同负担的项目成本所分摊给本项目的费用。
    而成本管理中不是涉及运营成本、实施成本。排除BD选项。所以此题选择C选项。