Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.
A.cost management planB.risk management planC.scope management planD.management schedule
第1题:
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.
A.analyze
B.track
C.level
D.extend
第2题:
●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
(75)
A. analyze
B. track
C. level
D. extend
第3题:
______describes,in detail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement
第4题:
Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an element
A.relationships
B.resources
C.stakeholders
D.deliverables
第5题:
In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.
A.schedule
B.activity
C.plan
D.contractor@@@SXB@@@A.finding
B.balance
C.allocation
D.distribution
第6题:
第7题:
第8题:
第9题:
第10题:
()describes, in detail, the project’s deliverables and the work required to create those deliverables.
第11题:
schedule
activity
plan
contractor
第12题:
Product scope description
Project objectives
Stakeholder Analysis
The project scope statement
第13题:
● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).
(71)
A. project elements
B. work drafts
C. work package
D. project deliverables
第14题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement
第15题:
● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)
(74)
A. Scope Planning
B. Scope Verification
C. Scope Change Control
D. Scope Definition
第16题:
In project time management processes,( )involves identifying and documenting the relationships between project activities.
A.activity definition
B.activity sequencing
C.schedule control
D.Schedule development
第17题:
Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.
A.cost management plan
B.risk management
C.scope management plan
D.management schedule
第18题:
第19题:
第20题:
第21题:
In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
第22题:
The () describes, in detail, the project's deliverables and the work required to create those deliverables.
第23题:
analyze
track
level
extend