参考答案和解析
正确答案:D
更多“Establishing a project ( ) involves listing milestones, activities, and deliverables with ”相关问题
  • 第1题:

    Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.

    A.analyze

    B.track

    C.level

    D.extend


    正确答案:B
    解析:通常,制订项目进度计划是一个反复迭代的过程,该过程确定每个活动和每个里程碑的开工日期和完成日期。制订进度过程要求对历时估算和资源估算进行评审和修订,从而产生一个经过认可的项目进度表,作为对项目进展进行追踪的基准。

  • 第2题:

    ●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.

    (75)

    A. analyze

    B. track

    C. level

    D. extend


    正确答案:B

  • 第3题:

    ______describes,in detail,the project's deliverables and the work required to create those deliverables.

    A.Product scope description

    B.Project objectives

    C.Stakeholder Analysis

    D.The project scope statement


    正确答案:D
    解析:项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。
    选项A是产品范围说明书,选项B是项目目标,选项C是干系人分析,选项D是项目范围说明书。故D是正确的。

  • 第4题:

    Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an element

    A.relationships

    B.resources

    C.stakeholders

    D.deliverables


    正确答案:D
    解析:建立项目管理的时间表需要里程碑列表、各活动、以及含有估计开始和结束时间的(),其中员工的调度被看作为元素。A,关系B,资源C,干系人D,可交付物

  • 第5题:

    In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.

    A.schedule

    B.activity

    C.plan

    D.contractor@@@SXB@@@A.finding

    B.balance

    C.allocation

    D.distribution


    正确答案:A,C

  • 第6题:

    Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.

    A.cost management plan
    B.risk management
    C.scope management plan
    D.management schedule

    答案:D
    解析:
    翻译:建立项目进度管理计划涉及里程碑,活动和可交付成果的开始和完成日期,人力资源日历也属于其中一种元素。A、成本管理计划 B、风险管理计划C、范围管理计划 D、进度管理计划

  • 第7题:

    Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element


    A.cost management plan
    B.risk management plan
    C.soope management plan
    D.management schedule


    答案:D
    解析:

  • 第8题:

    In project management, a ( ) is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。

    A.schedule
    B.activity
    C.Plan
    D.contractor

    答案:A
    解析:
    在项目管理中,( )是项目的里程碑、活动和交付物的列表,通常包括开始和完成日期。

  • 第9题:

    Establishing a project management timetable involves listing milestones,activities,and( )with intended start and finish dates,of which the scheduling of employees may be an element.

    A.relationships
    B.resources
    C.stakeholders
    D.deliverables

    答案:D
    解析:
    翻译:建立一个项目管理时间表包括列出里程碑,活动,以及开始和结束日期的目标交付物,其中员工是计划中的一个要考虑的要素。A.关系 B.资源 C.干系人 D.交付物

  • 第10题:

    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    • A、Product scope description
    • B、Project objectives
    • C、Stakeholder Analysis
    • D、The project scope statement

    正确答案:D

  • 第11题:

    单选题
    In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.
    A

    schedule

    B

    activity

    C

    plan

    D

    contractor


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.
    A

    Product scope description

    B

    Project objectives

    C

    Stakeholder Analysis

    D

    The project scope statement


    正确答案: A
    解析: 参考答案:D

  • 第13题:

    ● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).

    (71)

    A. project elements

    B. work drafts

    C. work package

    D. project deliverables


    正确答案:D

  • 第14题:

    ●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.

    (74) A. Product scope description

    B. Project objectives

    C. Product specification

    D. The project scope statement


    正确答案:D

  • 第15题:

    ● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)

    (74)

    A. Scope Planning

    B. Scope Verification

    C. Scope Change Control

    D. Scope Definition


    正确答案:D

  • 第16题:

    In project time management processes,( )involves identifying and documenting the relationships between project activities.

    A.activity definition

    B.activity sequencing

    C.schedule control

    D.Schedule development


    正确答案:B

  • 第17题:

    Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.

    A.cost management plan

    B.risk management

    C.scope management plan

    D.management schedule


    正确答案:D

  • 第18题:

    The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    A.project scope statement
    B.project requirement
    C.project charter
    D.product specification

    答案:A
    解析:
    项目范围说明书详细描述了项目的可交付物以及为创建这些可交付物所需的工作。
    A.项目范围说明书B.项目需求C.项目章程 D.产品规范

  • 第19题:

    ()describees,indetail,the project's deliverables and the work required to create those deliverables.


    A.Product scope description
    B.Project objectives
    C.Produce specification
    D.The project scope statement


    答案:D
    解析:
    项目范围说明书详细描述了项目的可交付物和提供这些可交付物必须要做的工作。

  • 第20题:

    ( ) describes,in detail,the project’s deliverables and the work required to create those deliverables.

    A.Product scope description
    B.Project objectives
    C.Stakeholder Analysis
    D.The project scope statement

    答案:D
    解析:
    项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。(72) A.产品范围说明书 B.项目目标 C.干系人分析 D.项目范围说明说

  • 第21题:

    In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.

    • A、schedule
    • B、WBS
    • C、SOW
    • D、charter

    正确答案:A

  • 第22题:

    The () describes, in detail, the project's deliverables and the work required to create those deliverables.

    • A、project scope statement
    • B、project requirement
    • C、project charter
    • D、product specification

    正确答案:A

  • 第23题:

    单选题
    Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.
    A

    analyze

    B

    track

    C

    level

    D

    extend


    正确答案: B
    解析: 该题的关键词为"project schedule、 baseline",其主要的语句结构为一个定语从句结构"project schedule that (主语)can serve as (谓语)a baseline to_progress",含义为"项目进度可以作为怎么样项目进展的基线",根据题意,容易判断对项目进度进行跟踪,所以选择选项B。