156 Deflection involves the transfer of risk by:A. Contracting out to another partyB. Developing schedule alternative.C. Establishing functions under the project manager to handle risk events.D. Disaster planning and responses.E. None of the above

题目

156 Deflection involves the transfer of risk by:

A. Contracting out to another party

B. Developing schedule alternative.

C. Establishing functions under the project manager to handle risk events.

D. Disaster planning and responses.

E. None of the above


相似考题
更多“156 Deflection involves the transfer of risk by:A. Contracting out to another partyB. Developing schedule alternative.C. Establishing functions under the project manager to handle risk events.D. Disaster planning and responses.E. None of the above”相关问题
  • 第1题:

    In Project Risk Management, Risk Response may include actions to:

    A reduce the probability of risk events

    B change the scope, budget, schedule or quality specifications of the project

    C reduce the consequences or severity of impacts of a potential risk event

    D A and C

    E All of the above.


    正确答案:E

  • 第2题:

    84 Risk management allows the project manager and the project team to:

    A. eliminate most risks during the planning phase of the project

    B. identify project risks

    C. identify impacts of various risks

    D. plan suitable responses

    E. B, C and D only


    正确答案:E

  • 第3题:

    113 Risk mitigation involves all but which of the following:

    A. developing system standards (policies, procedure, responsibility standards)

    B. obtaining insurance against loss

    C. identification of project risks

    D. performing contingent planning

    E. developing planning alternatives


    正确答案:C

  • 第4题:

    11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

    A. Reduce features and/or functionality

    B Increase risk.

    C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

    D. All of the above.

    E. A and B only


    正确答案:D

  • 第5题:

    166 Risk mitigation includes all but which of the following:

    A. Developing system (policies, procedures, responsibilities)

    B. Obtaining insurance against loss

    C. performing contingent planning

    D. developing planning alternatives

    E. identification of project risks


    正确答案:E

  • 第6题:

    In Project Risk Management, Risk Response may include actions to:

    A. reduce the probability of risk events

    B. change the scope, budget, schedule or quality specifications of the project

    C. reduce the consequences or severity of impacts of a potential risk event

    D. A and C

    E. All of the above


    正确答案:E

  • 第7题:

    ● Risk management allows the project manager and the project team not to(71).

    (71)

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

    试题(71)分析
      下面不属于风险管理中项目经理和项目团队职责的是  (71)  。
      A.排除大部分项目执行中的风险        B.风险识别
      C.风险分析                          D.妥善处理
    参考答案
    (71)A

  • 第8题:

    The most crucial time for project risk assessment is (75) .A.when a problem surfacesSXB

    The most crucial time for project risk assessment is (75) .

    A.when a problem surfaces

    B.during the planning phase

    C.during the close-out phase

    D.after the project schedule has been published


    正确答案:A
    项目风险评估最重要的时间是:当问题呈现时在规划阶段在收尾阶段在项目进度发布后

  • 第9题:

    The most crucial time for project risk assessment is ( ).

    A.when a problem surfaces

    B.during the planning phase

    C.during the close-out phase

    D.after the project schedule has been published


    正确答案:B

  • 第10题:

    Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.

    A.cost management plan
    B.risk management
    C.scope management plan
    D.management schedule

    答案:D
    解析:
    翻译:建立项目进度管理计划涉及里程碑,活动和可交付成果的开始和完成日期,人力资源日历也属于其中一种元素。A、成本管理计划 B、风险管理计划C、范围管理计划 D、进度管理计划

  • 第11题:

    Risk management allows the project manager and the project team not to()

    A.eliminate most risks during the planning phase of the project
    B.identify project risks
    C.identify impacts of various risks
    D.plan suitable responses

    答案:A
    解析:
    下面不属于风险管理中项目经理和项目团队职责的是(71)。A.排除大部分项目执行中的风险B.风险识别C.风险分析D.妥善处理

  • 第12题:

    The most crucial time for project risk assessment is ( ).

    • A、when a problem surfaces
    • B、during the planning phase
    • C、during the close-out phase
    • D、after the project schedule has been published

    正确答案:B

  • 第13题:

    Risk mitigation involves all but which of the following:

    A developing system standards (policies, procedure, responsibility standards)

    B obtaining insurance against loss

    C identification of project risks

    D performing contingent planning

    E developing planning alternatives


    正确答案:C

  • 第14题:

    108 Project Risk Management is based on which of the following premises:

    A. the future is unknown.

    B. unknowns can result in risks or opportunities.

    C. we cannot control risk events.

    D. project risk impact can be measured and controlled

    E. All of the above


    正确答案:E

  • 第15题:

    125 In Project Risk Management, Risk Response may include actions to:

    A. reduce the probability of risk events

    B. change the scope, budget, schedule or quality specifications of the project

    C. reduce the consequences or severity of impacts of a potential risk event

    D. A and C

    E. All of the above


    正确答案:E

  • 第16题:

    112 The schedule risk is the _____ .

    A. the accumulated "expected' durations which maintain project completion.

    B. Critical Path adjusted by "high-risk" activity float.

    C. highest risk path that maintains quality.

    D. Critical Path when calculated with "most likely" duration.

    E. highest risk path that contributes the most risk toward the project completion


    正确答案:B

  • 第17题:

    178 "Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .

    A. be completed in reduced overall time than other projects.

    B. be in a higher risk category than other projects.

    C. not be compatible with project risk and assessment

    D. A and B

    E. All of the above


    正确答案:D

  • 第18题:

    38 Deflection involves the transfer of risk by:

    A. Contracting out to another party

    B. Developing schedule alternative.

    C. Establishing functions under the project manager to handle risk events.

    D. Disaster planning and responses.

    E. None of the above


    正确答案:A

  • 第19题:

    Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses


    正确答案:A
    风险管理并不能使得项目经理及其团队在项目的规划过程中避免大多数的风险。

  • 第20题:

    Risk management allows the project manager and the project team not to (71).

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

  • 第21题:

    Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.

    A.cost management plan

    B.risk management

    C.scope management plan

    D.management schedule


    正确答案:D

  • 第22题:

    Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element


    A.cost management plan
    B.risk management plan
    C.soope management plan
    D.management schedule


    答案:D
    解析:

  • 第23题:

    The most crucial time for project risk assessment is ( ) .

    A.when a problem surfaces
    B.during the planning phase
    C.during the close-out phase
    D.after the project schedule has been published

    答案:B
    解析:
    进行项目风险评估最关键的时候是规划阶段。A.问题出现时 B.规划阶段 C.结束阶段 D.项目进度公布后