Deflection involves the transfer of risk by:A Contracting out to another partyB Developing schedule alternative.C Establishing functions under the project manager to handle risk events.D Disaster planning and responses.E None of the above.

题目

Deflection involves the transfer of risk by:

A Contracting out to another party

B Developing schedule alternative.

C Establishing functions under the project manager to handle risk events.

D Disaster planning and responses.

E None of the above.


相似考题
参考答案和解析
正确答案:A
更多“Deflection involves the transfer of risk by:A Contracting out to another partyB Developing schedule alternative.C Establishing functions under the project manager to handle risk events.D Disaster planning and responses.E None of the above.”相关问题
  • 第1题:

    Risk mitigation includes all but which of the following:

    A Developing system (policies, procedures, responsibilities)

    B Obtaining insurance against loss

    C performing contingent planning

    D developing planning alternatives

    E identification of project risks.


    正确答案:E

  • 第2题:

    Sensitivity analysis can be used in risk analysis to:

    A Substitute for uncertainty analysis in risk quantification

    B estimate the level of risk aversion adopted by management

    C estimate the effect of change of one project variable on the overall project

    D A and B

    E All of the above.


    正确答案:C

  • 第3题:

    Risk mitigation involves all but which of the following:

    A developing system standards (policies, procedure, responsibility standards)

    B obtaining insurance against loss

    C identification of project risks

    D performing contingent planning

    E developing planning alternatives


    正确答案:C

  • 第4题:

    84 Risk management allows the project manager and the project team to:

    A. eliminate most risks during the planning phase of the project

    B. identify project risks

    C. identify impacts of various risks

    D. plan suitable responses

    E. B, C and D only


    正确答案:E

  • 第5题:

    11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

    A. Reduce features and/or functionality

    B Increase risk.

    C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

    D. All of the above.

    E. A and B only


    正确答案:D

  • 第6题:

    166 Risk mitigation includes all but which of the following:

    A. Developing system (policies, procedures, responsibilities)

    B. Obtaining insurance against loss

    C. performing contingent planning

    D. developing planning alternatives

    E. identification of project risks


    正确答案:E

  • 第7题:

    Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses


    正确答案:A
    风险管理并不能使得项目经理及其团队在项目的规划过程中避免大多数的风险。

  • 第8题:

    Risk management allows the project manager and the project team not to (71).

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

  • 第9题:

    Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.

    A.cost management plan

    B.risk management

    C.scope management plan

    D.management schedule


    正确答案:D

  • 第10题:

    Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element


    A.cost management plan
    B.risk management plan
    C.soope management plan
    D.management schedule


    答案:D
    解析:

  • 第11题:

    The most crucial time for project risk assessment is ( ) .

    A.when a problem surfaces
    B.during the planning phase
    C.during the close-out phase
    D.after the project schedule has been published

    答案:B
    解析:
    进行项目风险评估最关键的时候是规划阶段。A.问题出现时 B.规划阶段 C.结束阶段 D.项目进度公布后

  • 第12题:

    ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.

    • A、Quantitative Risk Analysis
    • B、Qualitative Risk Analysis
    • C、Enterprise Environmental Factors
    • D、Risk Management Plan

    正确答案:B

  • 第13题:

    The schedule risk is the _____ .

    A the accumulated "expected' durations which maintain project completion.

    B Critical Path adjusted by "high-risk" activity float.

    C highest risk path that maintains quality.

    D Critical Path when calculated with "most likely" duration.

    E highest risk path that contributes the most risk toward the project completion.


    正确答案:B

  • 第14题:

    In Project Risk Management, Risk Response may include actions to:

    A reduce the probability of risk events

    B change the scope, budget, schedule or quality specifications of the project

    C reduce the consequences or severity of impacts of a potential risk event

    D A and C

    E All of the above.


    正确答案:E

  • 第15题:

    By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

    A Significantly reduce project risks

    B eliminate project risks

    C provide a rational basis for better decision making

    D identify risks, their impact(s), and any appropriate responses

    E None of the above.


    正确答案:B

  • 第16题:

    113 Risk mitigation involves all but which of the following:

    A. developing system standards (policies, procedure, responsibility standards)

    B. obtaining insurance against loss

    C. identification of project risks

    D. performing contingent planning

    E. developing planning alternatives


    正确答案:C

  • 第17题:

    156 Deflection involves the transfer of risk by:

    A. Contracting out to another party

    B. Developing schedule alternative.

    C. Establishing functions under the project manager to handle risk events.

    D. Disaster planning and responses.

    E. None of the above


    正确答案:A

  • 第18题:

    ● Risk management allows the project manager and the project team not to(71).

    (71)

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

    试题(71)分析
      下面不属于风险管理中项目经理和项目团队职责的是  (71)  。
      A.排除大部分项目执行中的风险        B.风险识别
      C.风险分析                          D.妥善处理
    参考答案
    (71)A

  • 第19题:

    The most crucial time for project risk assessment is (75) .A.when a problem surfacesSXB

    The most crucial time for project risk assessment is (75) .

    A.when a problem surfaces

    B.during the planning phase

    C.during the close-out phase

    D.after the project schedule has been published


    正确答案:A
    项目风险评估最重要的时间是:当问题呈现时在规划阶段在收尾阶段在项目进度发布后

  • 第20题:

    The most crucial time for project risk assessment is ( ).

    A.when a problem surfaces

    B.during the planning phase

    C.during the close-out phase

    D.after the project schedule has been published


    正确答案:B

  • 第21题:

    Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.

    A.cost management plan
    B.risk management
    C.scope management plan
    D.management schedule

    答案:D
    解析:
    翻译:建立项目进度管理计划涉及里程碑,活动和可交付成果的开始和完成日期,人力资源日历也属于其中一种元素。A、成本管理计划 B、风险管理计划C、范围管理计划 D、进度管理计划

  • 第22题:

    Risk management allows the project manager and the project team not to()

    A.eliminate most risks during the planning phase of the project
    B.identify project risks
    C.identify impacts of various risks
    D.plan suitable responses

    答案:A
    解析:
    下面不属于风险管理中项目经理和项目团队职责的是(71)。A.排除大部分项目执行中的风险B.风险识别C.风险分析D.妥善处理

  • 第23题:

    The most crucial time for project risk assessment is ( ).

    • A、when a problem surfaces
    • B、during the planning phase
    • C、during the close-out phase
    • D、after the project schedule has been published

    正确答案:B