Deflection involves the transfer of risk by:
A Contracting out to another party
B Developing schedule alternative.
C Establishing functions under the project manager to handle risk events.
D Disaster planning and responses.
E None of the above.
第1题:
Risk mitigation includes all but which of the following:
A Developing system (policies, procedures, responsibilities)
B Obtaining insurance against loss
C performing contingent planning
D developing planning alternatives
E identification of project risks.
第2题:
Sensitivity analysis can be used in risk analysis to:
A Substitute for uncertainty analysis in risk quantification
B estimate the level of risk aversion adopted by management
C estimate the effect of change of one project variable on the overall project
D A and B
E All of the above.
第3题:
Risk mitigation involves all but which of the following:
A developing system standards (policies, procedure, responsibility standards)
B obtaining insurance against loss
C identification of project risks
D performing contingent planning
E developing planning alternatives
第4题:
84 Risk management allows the project manager and the project team to:
A. eliminate most risks during the planning phase of the project
B. identify project risks
C. identify impacts of various risks
D. plan suitable responses
E. B, C and D only
第5题:
11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.
A. Reduce features and/or functionality
B Increase risk.
C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)
D. All of the above.
E. A and B only
第6题:
166 Risk mitigation includes all but which of the following:
A. Developing system (policies, procedures, responsibilities)
B. Obtaining insurance against loss
C. performing contingent planning
D. developing planning alternatives
E. identification of project risks
第7题:
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第8题:
Risk management allows the project manager and the project team not to (71).
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第9题:
Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.
A.cost management plan
B.risk management
C.scope management plan
D.management schedule
第10题:
第11题:
第12题:
()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.
第13题:
The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.
第14题:
In Project Risk Management, Risk Response may include actions to:
A reduce the probability of risk events
B change the scope, budget, schedule or quality specifications of the project
C reduce the consequences or severity of impacts of a potential risk event
D A and C
E All of the above.
第15题:
By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:
A Significantly reduce project risks
B eliminate project risks
C provide a rational basis for better decision making
D identify risks, their impact(s), and any appropriate responses
E None of the above.
第16题:
113 Risk mitigation involves all but which of the following:
A. developing system standards (policies, procedure, responsibility standards)
B. obtaining insurance against loss
C. identification of project risks
D. performing contingent planning
E. developing planning alternatives
第17题:
156 Deflection involves the transfer of risk by:
A. Contracting out to another party
B. Developing schedule alternative.
C. Establishing functions under the project manager to handle risk events.
D. Disaster planning and responses.
E. None of the above
第18题:
● Risk management allows the project manager and the project team not to(71).
(71)
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第19题:
The most crucial time for project risk assessment is (75) .
A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
第20题:
The most crucial time for project risk assessment is ( ).
A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
第21题:
第22题:
第23题:
The most crucial time for project risk assessment is ( ).