Project Risk Management is based on which of the following premises:A the future is unknown.B unknowns can result in risks or opportunities.C we cannot control risk events.D project risk impact can be measured and controlledE All of the above.

题目

Project Risk Management is based on which of the following premises:

A the future is unknown.

B unknowns can result in risks or opportunities.

C we cannot control risk events.

D project risk impact can be measured and controlled

E All of the above.


相似考题
参考答案和解析
正确答案:E
更多“Project Risk Management is based on which of the following premises:A the future is unknown.B unknowns can result in risks or opportunities.C we cannot control risk events.D project risk impact can be measured and controlledE All of the above.”相关问题
  • 第1题:

    Sensitivity analysis can be used in risk analysis to:

    A Substitute for uncertainty analysis in risk quantification

    B estimate the level of risk aversion adopted by management

    C estimate the effect of change of one project variable on the overall project

    D A and B

    E All of the above.


    正确答案:C

  • 第2题:

    Risk classified as unknown unknowns (i.e., those which cannot be identified or evaluated):

    A should be deflected to the contracting officer

    B should be handled via contingency allowances

    C should be ignored, since they cannot be identified

    D should be ignored, since they are not covered in the Project Risk Assessment

    E C and D


    正确答案:B

  • 第3题:

    Total project risk can be defined as:

    A the sum of the probabilities of project risks events times the sum of consequences of those risks

    B the sum of the products of each project risk event times its consequences

    C the sum of the consequences of all project risk events

    D the sum of the probabilities of all project risk events

    E 1 - the sum of the probabilities of all project risk events.


    正确答案:B

  • 第4题:

    77 Since risk is associated with most projects, the best course of action is to:

    A. cover all project risks by buying appropriate insurance

    B. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.

    C. avoid projects with clear and present risks

    D. eliminate all known risks prior to the execution phase of the project

    E. identify various risks and implement actions to mitigate their potential impact


    正确答案:E

  • 第5题:

    59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

    A. Significantly reduce project risks

    B. eliminate project risks

    C. provide a rational basis for better decision making

    D. identify risks, their impact(s), and any appropriate responses

    E. None of the above


    正确答案:B

  • 第6题:

    173 The Risk of NOT meeting project quality objectives:

    A. can be minimized through continuous monitoring.

    B. considered a long term risk.

    C. will be reflected in the "in-service" life of the product or service.

    D. B and C

    E. All of the above.


    正确答案:E

  • 第7题:

    The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


    正确答案:A
    风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

  • 第8题:

    Since risk is associated with most projects,the best course of action is to ( )

    A.cover all project risks by buying appropriate insurance

    B.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious manner

    C.avoid project with clear and present risk

    D.identify various risks and implement actions to mitigate their potential impact


    正确答案:D
    识别所有风险,潜在应对措施。

  • 第9题:

    ()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.

    A.identify risks
    B.monitor risks
    C.implement risks responses
    D.plan risk management

    答案:A
    解析:
    翻译:()是识别单个项目风险以及整个项目风险的来源,并记录其特征的过程。
    A.识别风险
    B.监控风险
    C.实施风险应对措施
    D.计划风险管理
    识别风险是识别单个项目风险以及整个项目风险的来源,并记录其特征的过程。

  • 第10题:

    ( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.

    A.Quantitative Risk Analysis
    B.Qualitative Risk Analysis
    C.Enterprise Environmental Factors
    D.Risk Management Plan

    答案:B
    解析:
    翻译:(71)利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。A.定量风险分析 B.定性风险分析 C.企业环境因素 D.风险管理计划

  • 第11题:

    ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.

    • A、Quantitative Risk Analysis
    • B、Qualitative Risk Analysis
    • C、Enterprise Environmental Factors
    • D、Risk Management Plan

    正确答案:B

  • 第12题:

    单选题
    ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.
    A

    Quantitative Risk Analysis

    B

    Qualitative Risk Analysis

    C

    Enterprise Environmental Factors

    D

    Risk Management Plan


    正确答案: B
    解析: 参考答案:B

  • 第13题:

    In Project Risk Management, Risk Response may include actions to:

    A reduce the probability of risk events

    B change the scope, budget, schedule or quality specifications of the project

    C reduce the consequences or severity of impacts of a potential risk event

    D A and C

    E All of the above.


    正确答案:E

  • 第14题:

    By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

    A Significantly reduce project risks

    B eliminate project risks

    C provide a rational basis for better decision making

    D identify risks, their impact(s), and any appropriate responses

    E None of the above.


    正确答案:B

  • 第15题:

    Since risk is associated with most projects, the best course of action is to:

    A cover all project risks by buying appropriate insurance

    B ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.

    C avoid projects with clear and present risks

    D eliminate all known risks prior to the execution phase of the project

    E identify various risks and implement actions to mitigate their potential impact


    正确答案:E

  • 第16题:

    15 Total project risk can be defined as:

    A. the sum of the probabilities of project risks events times the sum of consequences of those risks

    B. the sum of the products of each project risk event times its consequences

    C. the sum of the consequences of all project risk events

    D. the sum of the probabilities of all project risk events

    E. 1 - the sum of the probabilities of all project risk events


    正确答案:B

  • 第17题:

    108 Project Risk Management is based on which of the following premises:

    A. the future is unknown.

    B. unknowns can result in risks or opportunities.

    C. we cannot control risk events.

    D. project risk impact can be measured and controlled

    E. All of the above


    正确答案:E

  • 第18题:

    ______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.

    A.Quantitative Risk Analysis

    B.Qualitative Risk Analysis

    C.Enterprise Environmental Factors

    D.Risk Management Plan


    正确答案:B
    解析:定性风险分析利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。
    选项A是定量风险分析,选项B是定性风险分析,选项C是企业环境因素,选项D是风险管理计划。故B是正确的。

  • 第19题:

    Since risk is associated with most projects,the best course of action is to (71)

    A.cover all project risks by buying appropriate insurance

    B.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious manner

    C.avoid project with clear and present risk

    D.identify various risks and implement actions to mitigate their potential impact


    正确答案:D
    识别所有风险,潜在应对措施。

  • 第20题:

    ()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.

    A.Identity risks

    B.Control risks

    C.Plan risk responses

    D.Plan risk management


    正确答案:B

  • 第21题:

    The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    A.Risk Identification
    B.Quantitative Risk Analysis
    C.Qualitative Risk Analysis
    D.Risk Monitoring anD.Control

    答案:A
    解析:
    项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。
    A.风险识别 B.定量风险分析 C.定性风险分析 D.风险检测与控制

  • 第22题:

    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    • A、Riskldentification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:A

  • 第23题:

    单选题
    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
    A

    Riskldentification

    B

    Quantitative Risk Analysis

    C

    Qualitative Risk Analysis

    D

    Risk Monitoring and Control


    正确答案: C
    解析: 该题的关键词为"ascertains、documenting the risks' characteristics",其语句结构为"The()_process(主语)ascertains(谓语)which risks have the potential of affecting the project and documenting the risks' characteristics",含义为"什么过程确定那些可能影响项目的风险并记录这些风险特征",根据风险管理知识领域,识别并记录风险是风险识别子过程的主要任务,所以选择A