Risk management requires an understanding that _____ .A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.B risk identification must be directly aligned with the Work Breakdown Structure.C it is merely advanced preparatio

题目

Risk management requires an understanding that _____ .

A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.

B risk identification must be directly aligned with the Work Breakdown Structure.

C it is merely advanced preparation for possible adverse future events.

D it does not imply complete control of events

E All of the above.


相似考题
更多“Risk management requires an understanding that _____ .A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.B risk identification must be directly aligned with the Work Breakdown Structure.C it is merely advanced preparatio”相关问题
  • 第1题:

    Risk mitigation is the process of _____ .

    A transferring risk to another party.

    B reducing uncertainty on the project

    C identifying all possible risk events

    D monitoring status and making adjustments

    E All of the above.


    正确答案:B

  • 第2题:

    Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?

    A concept

    B development

    C execution

    D conclusion

    E All of the above.


    正确答案:A

  • 第3题:

    It is useful to conduct project risk assessment according to the project's

    A charter

    B statement of work

    C Work Breakdown structure

    D network

    E budget


    正确答案:C

  • 第4题:

    92 The highest degrees of project risk and uncertainty are associated with the following phase of the project:

    A. conceptual

    B. execution

    C. cut-over

    'D. post project evaluation

    E. A and D only


    正确答案:A

  • 第5题:

    70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. concept

    B. development

    C. execution

    D. conclusion

    E. All of the above


    正确答案:A

  • 第6题:

    10 The ability to reduce risk is _____ to how far you have progressed through the project life cycle. A. inversely proportional

    B. directly proportional

    C. not related

    D. the responsibility of the risk executive

    E. is directly proportional to the amount at stake


    正确答案:A

  • 第7题:

    ● Feasibility studies occur in which life cycle phase (s)?

    A Conceptual

    B Conceptual or Development

    C Execution

    D Preliminary planning

    E any life cycle phase


    正确答案:A

  • 第8题:

    ● The critical path in a network is the path that:

    A Has the greatest degree of risk.

    B Will elongate the project if the activities on this path take longer than anticipated.

    C Must be completed before all other paths.

    D All of the above.

    E A and B only.


    正确答案:B

  • 第9题:

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control


    正确答案:B
    定量风险分析过程分析风险事件的影响并对这些影响赋予一个数值化的评价。

  • 第10题:

    Risk management’s ( ) is to assure uncertainty does not deflect the endeavor from the business.

    A.trend

    B.detail

    C.objective

    D.rule


    正确答案:C

  • 第11题:

    The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    A.Risk Identification
    B.Quantitative Risk Analysis
    C.Qualitative Risk Analysis
    D.Risk Monitoring anD.Control

    答案:A
    解析:
    项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。
    A.风险识别 B.定量风险分析 C.定性风险分析 D.风险检测与控制

  • 第12题:

    Team member listing, scheduled tasks, and risk identification are part of the:()

    • A、project plan.
    • B、project charter.
    • C、communication plan.
    • D、WBS (Work Breakdown Structure).

    正确答案:A

  • 第13题:

    The ability to reduce risk is _____ to how far you have progressed through the project life cycle.

    A inversely proportional

    B directly proportional

    C not related

    D the responsibility of the risk executive

    E is directly proportional to the amount at stake.


    正确答案:A

  • 第14题:

    Giving a part of project work to a contractor is an example of:

    A risk mitigation

    B risk assignment

    C risk delegation

    D risk deflection

    E risk assumption


    正确答案:D

  • 第15题:

    The highest degrees of project risk and uncertainty are associated with the following phase of the project:

    A conceptual

    B execution

    C cut-over

    D post project evaluation

    E A and D only


    正确答案:A

  • 第16题:

    111 It is useful to conduct project risk assessment according to the project's

    A. charter

    B. statement of work

    C. Work Breakdown structure

    D. network

    E. budget


    正确答案:C

  • 第17题:

    186 Risk management requires an understanding that _____ .

    A. the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.

    B. risk identification must be directly aligned with the Work Breakdown Structure.

    C. it is merely advanced preparation for possible adverse future events.

    D. it does not imply complete control of events

    E. All of the above


    正确答案:E

  • 第18题:

    174 The highest degrees of project risk and uncertainty are associated with the following phase of the project:

    A. conceptual

    B. execution

    C. cut-over

    D. post project evaluation

    E. A and D only


    正确答案:A

  • 第19题:

    ● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

    A Time, schedule and cost.

    B Management coordination and organization structuring.

    C Work methods and accountability.

    D Quality of work.

    E Risk and impact decision-making.


    正确答案:D

  • 第20题:

    The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


    正确答案:A
    风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

  • 第21题:

    Workarounds are determined during which risk management process? (75).

    A. Risk identification

    B. Quantitative risk analysis

    C. Plan risk responses

    D. Risk monitoring and control


    正确答案:D
    权变措施是在风险管理过程中的(75)过程确定的?。A.风险识别B.风险定量分析C.规划风险应对D.风险监测和控制

  • 第22题:

    Risk management’s ( ) is to assure uncertainty does not deflect the endeavor from the business goals

    A.trend
    B.detail
    C.objective
    D.rule

    答案:C
    解析:

  • 第23题:

    Which of following best describes customer benefits in delivering network readiness assessment services in plan phase?()

    • A、improve its ability to achieve business goals by identifying and aligning advanced technologies with business requirements
    • B、improve its return on investment and speed migration by improve its ability to identify,understand, and plan for necessary changes in infrastructure or resource
    • C、ensure that key employees understand all of the implementation steps
    • D、reduce the amount of risk it is exposed to by using proven project management methodologies and risk mitigation strategies

    正确答案:B