Risk management requires an understanding that _____ .
A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.
B risk identification must be directly aligned with the Work Breakdown Structure.
C it is merely advanced preparation for possible adverse future events.
D it does not imply complete control of events
E All of the above.
第1题:
Risk mitigation is the process of _____ .
A transferring risk to another party.
B reducing uncertainty on the project
C identifying all possible risk events
D monitoring status and making adjustments
E All of the above.
第2题:
Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?
A concept
B development
C execution
D conclusion
E All of the above.
第3题:
It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
第4题:
92 The highest degrees of project risk and uncertainty are associated with the following phase of the project:
A. conceptual
B. execution
C. cut-over
'D. post project evaluation
E. A and D only
第5题:
70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. concept
B. development
C. execution
D. conclusion
E. All of the above
第6题:
10 The ability to reduce risk is _____ to how far you have progressed through the project life cycle. A. inversely proportional
B. directly proportional
C. not related
D. the responsibility of the risk executive
E. is directly proportional to the amount at stake
第7题:
● Feasibility studies occur in which life cycle phase (s)?
A Conceptual
B Conceptual or Development
C Execution
D Preliminary planning
E any life cycle phase
第8题:
● The critical path in a network is the path that:
A Has the greatest degree of risk.
B Will elongate the project if the activities on this path take longer than anticipated.
C Must be completed before all other paths.
D All of the above.
E A and B only.
第9题:
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control
第10题:
Risk management’s ( ) is to assure uncertainty does not deflect the endeavor from the business.
A.trend
B.detail
C.objective
D.rule
第11题:
第12题:
Team member listing, scheduled tasks, and risk identification are part of the:()
第13题:
The ability to reduce risk is _____ to how far you have progressed through the project life cycle.
A inversely proportional
B directly proportional
C not related
D the responsibility of the risk executive
E is directly proportional to the amount at stake.
第14题:
Giving a part of project work to a contractor is an example of:
A risk mitigation
B risk assignment
C risk delegation
D risk deflection
E risk assumption
第15题:
The highest degrees of project risk and uncertainty are associated with the following phase of the project:
A conceptual
B execution
C cut-over
D post project evaluation
E A and D only
第16题:
111 It is useful to conduct project risk assessment according to the project's
A. charter
B. statement of work
C. Work Breakdown structure
D. network
E. budget
第17题:
186 Risk management requires an understanding that _____ .
A. the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.
B. risk identification must be directly aligned with the Work Breakdown Structure.
C. it is merely advanced preparation for possible adverse future events.
D. it does not imply complete control of events
E. All of the above
第18题:
174 The highest degrees of project risk and uncertainty are associated with the following phase of the project:
A. conceptual
B. execution
C. cut-over
D. post project evaluation
E. A and D only
第19题:
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A Time, schedule and cost.
B Management coordination and organization structuring.
C Work methods and accountability.
D Quality of work.
E Risk and impact decision-making.
第20题:
The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control
第21题:
Workarounds are determined during which risk management process? (75).
A. Risk identification
B. Quantitative risk analysis
C. Plan risk responses
D. Risk monitoring and control
第22题:
第23题:
Which of following best describes customer benefits in delivering network readiness assessment services in plan phase?()