Human resource management is the management of human resources.It is function in organizations designed to maximize employee ( ) in service of an employer's strategic objectives.A.workB.jobC.scopeD.performance

题目

Human resource management is the management of human resources.It is function in organizations designed to maximize employee ( ) in service of an employer's strategic objectives.

A.work

B.job

C.scope

D.performance


相似考题
参考答案和解析
正确答案:D
更多“Human resource management is the management of human resources.It is function in organizat ”相关问题
  • 第1题:

    ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

    (71)

    A.activity duration estimating, schedule developing, activity resource estimating

    B . activity resource estimating, activity duration estimating, schedule development

    C.schedule developing, activity resource estimating, activity duration estimating

    D.activity resource estimating, schedule developing, activity duration estimating


    正确答案:B
    试题(71)分析
     项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
     项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
     以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule                 development,所以选B。
    参考答案
    (71)B

  • 第2题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第3题:

    is nonprogram text embedded in a program to explain its form. and function to human readers.

    A.Command

    B.Compile

    C.Comment

    D.Statement


    正确答案:C
    解析:注释是嵌入到程序中的非程序文本,用来向阅读程序的人解释程序的结构和功能。

  • 第4题:

    Human resource management is the management of human resources. It is a function in organization designed to maximize employee ( )in service of an employer’s strategic objectives.

    A.work
    B. joB.
    C.scope
    D.performance

    答案:D
    解析:
    翻译:人力资源管理就是对人力资源进行管理,目的是最大限度地发挥员工的表现力来为雇主实现战略目标。A.工作 B.职位 C.范围 D.表现力

  • 第5题:

    A management information system__( )__the business managers the information that they need to make decisions.Early business computers were used for simple operations such__(请作答此空)__tracking inventory,billing,sales,or payroll data,with little detail or structure.Over time,these computer applications became more complex,hardware storage capacities grew,and technologies improved for connecting previously__( )__applications.As more data was stored and linked,managers sought greater abstraction as well as greater detail with the aim of creating significant management reports from the stored__( )__.Originally,the term"MIS”described applications providing managers with information about sales,inventories,and other data that would help in__( )__the enterprise.Over time,the term broadened to include:decision support systems,resource management and human resource management,enterprise resource planning(ERP),enterprise performance management(EPM),supply chain management(SCM),customer relationship management(CRM),project management and database retrieval applications.

    A.as
    B.to
    C.as to
    D.that

    答案:A
    解析:
    管理信息系统给企业管理者做各种决策所需要的信息。早期的商用电脑用于简单的操作如跟踪、结算、销售或小型的工资数据。随着时间的推移,这些计算机的应用程序变得更加复杂,硬件存储容量的增长,需要改善连接这些先前孤立应用程序之间的技术。随着越来越多的数据存储和连接,管理者寻求更抽象以及更详细的目标,从原材料和存储的数据中创造更显著的管理报告。起初,“MIS”描述为管理者提供信息,这将有助于管理企业销售、存货和其他数据的应用程序。随着时间的推移,这个词逐步扩大到包括决策支持系统、资源管理和人力资源管理、企业资源规划(ERP)、企业绩效管理(EPM)、供应链管理(SCM)、客户关系管理(CRM)、项目管理库存储和检索应用程序。

  • 第6题:

    ( ) is responsible for the attraction,selection,training,assessment,and rewarding of employees,while also overseeing organizational leadership and culture,and ensuring compliance with employment and labor laws.

    A.Human resource management
    B.StrategiC.analysis
    C.Team management
    D.RACI

    答案:A
    解析:
    人力资源管理的责任是吸引,选择,培养,评估,奖励员工,同时也监督领导的文化才能,并确保遵从就业和劳动法。

  • 第7题:


    Cyberspace is described by William Gibson as( )

    A.a function only legitimate computer operators have
    B.a representation of data from the human system
    C.an important element stored in the human system
    D.an illusion held by the common computer users

    答案:D
    解析:

  • 第8题:

    A characteristic of operating system is()。

    • A、 resource  management 
    • B、 memory management 
    • C、 error recovery 
    • D、 all the above

    正确答案:A

  • 第9题:

    Enterprise Asset Management packages offer a wide range of capabilities. Which three areas of capability are covered by IBM Maximo Asset Management solutions?()

    • A、work orders
    • B、human resources
    • C、inventory control
    • D、preventive maintenance
    • E、facilities schedule management
    • F、customer relationship management

    正确答案:A,C,D

  • 第10题:

    With which three other business initiatives does Enterprise Asset Management-a business paradigm-integrate strategic planning?()

    • A、sales
    • B、operations
    • C、maintenance
    • D、balance sheet
    • E、human resources
    • F、capital investment decision-making

    正确答案:B,C,F

  • 第11题:

    单选题
    The()provides the project manager with the authority to apply organizational resources to project activities.
    A

    project management plan

    B

    contract

    C

    project human resource plan

    D

    project charter


    正确答案: A
    解析: 项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第12题:

    单选题
    The()provides the project manager with the authority to apply organizational resources to project activities.
    A

    project management plan

    B

    contract

    C

    project human resource plan

    D

    projectcharter


    正确答案: D
    解析: 该题的关键词为"authority to apply organizational resources",其语句结构为"The____(主语)provides(谓语)the project manager with the authority to apply organizationalresources",含义为"什么为项目经理提供了使用组织资源的权力",根据项目管理知识,为项目经理授权的文件为项目章程,所以应该选择选项D,其他选项容易排除。

  • 第13题:

    The(70)provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.contract

    C.project human resource plan

    D.project charter


    正确答案:D
    解析:项目章程为项目经理使用组织资源进行项目活动提供了授权。

  • 第14题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第15题:

    The (73) provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B

  • 第16题:

    () risks cannot be management proactively and therefore may be assigned a management reserve.( )不能主动管理风险,因此可以分配管理准备金。

    A.Known已知
    B.Natural自然
    C.Unknown未知
    D.Human人为

    答案:C
    解析:

  • 第17题:

    A management information system__( )__the business managers the information that they need to make decisions.Early business computers were used for simple operations such__( )__tracking inventory,billing,sales,or payroll data,with little detail or structure.Over time,these computer applications became more complex,hardware storage capacities grew,and technologies improved for connecting previously__( )__applications.As more data was stored and linked,managers sought greater abstraction as well as greater detail with the aim of creating significant management reports from the stored__( )__.Originally,the term"MIS”described applications providing managers with information about sales,inventories,and other data that would help in__(请作答此空)__the enterprise.Over time,the term broadened to include:decision support systems,resource management and human resource management,enterprise resource planning(ERP),enterprise performance management(EPM),supply chain management(SCM),customer relationship management(CRM),project management and database retrieval applications.

    A.setting up
    B.founding
    C.improving
    D.Managing

    答案:D
    解析:
    管理信息系统给企业管理者做各种决策所需要的信息。早期的商用电脑用于简单的操作如跟踪、结算、销售或小型的工资数据。随着时间的推移,这些计算机的应用程序变得更加复杂,硬件存储容量的增长,需要改善连接这些先前孤立应用程序之间的技术。随着越来越多的数据存储和连接,管理者寻求更抽象以及更详细的目标,从原材料和存储的数据中创造更显著的管理报告。起初,“MIS”描述为管理者提供信息,这将有助于管理企业销售、存货和其他数据的应用程序。随着时间的推移,这个词逐步扩大到包括决策支持系统、资源管理和人力资源管理、企业资源规划(ERP)、企业绩效管理(EPM)、供应链管理(SCM)、客户关系管理(CRM)、项目管理库存储和检索应用程序。

  • 第18题:

    ()risks cannot be management proactively and therefore may be assigned a management reserve.

    A.Knowm
    B.Natural
    C.Unknown
    D.Human

    答案:C
    解析:
    本题翻译:
    ()风险不能主动管理,因此可能需要分配管理准备金。
    A.已知B.自然C.未知D.人为
    只要能翻译出题干,就很容易能得到答案,管理准备金是为了“未知-未知”的风险。也就是不能预料
    还要注意,经常容易混淆的点就是应急储备管理是为了“已知-未知”的风险。既然能够已知会发生风险,就可以进行主动管理。
    所以此题选择C选项。

  • 第19题:

    An ERP management information system integrates several areas such as planning, purchasing()etc.

    • A、inventory
    • B、sales
    • C、marketing
    • D、human resources

    正确答案:A,B,C,D

  • 第20题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

    • A、activity duration estimating, schedule developing, activity resource estimating
    • B、activity resource estimating, activity duration estimating, schedule development
    • C、schedule developing, activity resource estimating, activity duration estimating
    • D、activity resource estimating, schedule developing, activity duration estimating

    正确答案:B

  • 第21题:

    You need to recommend a document management solution that supports the company's planned changes.   What should you include in the recommendation?()

    • A、Active Directory Rights Management Services(AD RMS)and File Server Resource Manager (FSRM)
    • B、Active Directory Rights Management Services(AD RMS)and Microsoft SharePoint Foundation 2010
    • C、Authorization Manager and Microsoft SharePoint Foundation 2010
    • D、File Server Resource Manager (FSRM) and Share and Storage Management

    正确答案:B

  • 第22题:

    单选题
    PRM的全名为()
    A

    Professional Risk Manager

    B

    Partner Relationship Management

    C

    Partner Resource Management

    D

    Potential Resource Management


    正确答案: A
    解析: 暂无解析

  • 第23题:

    多选题
    Which two statements are true regarding ownership of shared entities? ()(Choose two.)
    A

    Customers is owned by Oracle Human Resources whereas Locations is owned by Oracle Receivables.

    B

    Items is owned by Oracle Purchasing whereas Locations is owned by Oracle Receivables.

    C

    Sales Force is owned by Oracle Order Management whereas Employees is owned by Oracle Human Resources.

    D

    Set of books is owned by Oracle General Ledger whereas Locations is owned by Oracle Human Resources.

    E

    Suppliers is owned by Oracle Purchasing whereas Units of Measure is owned by Oracle Inventory.


    正确答案: B,C
    解析: 暂无解析