Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource esti

题目
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

A.activity duration estimating, schedule developing, activity resource estimating

B.activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


相似考题
更多“Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. ”相关问题
  • 第1题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第2题:

    ● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .

    (73)

    A. measure, delay, record, distribute, analyze, and direct

    B. plan, schedule, monitor, control, report, and forecast

    C. promote, highlight, monitor, control, forecast, and report

    D. emphasize, visualize, analyze, conceptualize, report, and record


    正确答案:B

  • 第3题:

    Refer to Topic TestKing.com in iPAD document.What happens to the network when TestKingX is reconnected and a trunk exists between the two switches?()

    A. All VLANs except the default VLAN will be removed from all switches.

    B. All existing switches will have the students, admin, faculty, Servers, Management,Production, and no-where VLANs.

    C. The VLANs Servers, Management, Production, and no-where will replace the VLANs on SwX.

    D. The VLANs Servers, Management, Production, and no-where will be removed from existing switches.


    参考答案:D

  • 第4题:

    You are the desktop administrator for Ezonexam, Inc. The company's network contains an intranet Web farm, which consists of three Web servers. The Web servers are named Ezonexam1, Ezonexam2, and Ezonexam3. Users access the Web farm by using the URL http://team.Ezonexam.com. The relevant portion of the network is configured as shown in the exhibit.

    Jack is a user in the company operations department. Jack uses Internet Explorer on this Windows 2000 Professional computer to access files that are located on the Web farm. Jack reports that when he attempts to access a file named Schedule.xls by using the URL http://team.Ezonexam.com/ops/schedule.xls, Internet Explorer displays the following error message: "DNS error or server not found".

    The network administrator informs you that the company DNS server is unavailable. However, Jack needs to access the Schedule.xls file immediately. You need to ensure that King can access the file by using Internet Explorer on his computer.

    Which URL should you instruct King to use?

    A.http://Ezonexam1/ops/schedule.xls

    B.file://Ezonexam1/ops/schedule.xls

    C.http://team.Ezonexam.com/ops$/schedule.xls

    D.file://team.Ezonexam.com/ops/schedule.xls


    正确答案:B
    解析:Explanation: We explicitly refer to the file on one of the servers in the web farm.

    Incorrect Answers
    A: To use the http protocol we would have to use FQDN name.

    C, D: Since the DNS server is not available we should not use the FQDN team.Ezonexam.com.

  • 第5题:

    Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.

    A.Integration

    B.Configuration

    C.Scope

    D.Requirement


    正确答案:C

  • 第6题:

    The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()

    A.Measure, delay, record, distribute, analyze, and direct
    B.Plan, schedule, monitor, control, report, and forecast
    C.Promote, highlight, monitor, control, forecast, and report
    D.Emphasize, visualize, analyze, conceptualize, report and record

    答案:B
    解析:
    项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来(73)。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录