subdividing
assessing
planning
integrating
第1题:
106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A. Work packages.
B. Subtasks.
C. Tasks.
D. Code of accounts.
E. Integration points
第2题:
23 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation
B. Scope planning
C. Scope change control
D. Scope
Definition
E. Scope verification
第3题:
● A work breakdown structure is most useful for:
A identifying individual tasks for a project
B scheduling the start of tasks
C developing a cost estimate
D determining potential delays
E A and C
第4题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第5题:
● The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A Work packages.
B Subtasks.
C Tasks.
D Code of accounts.
E Integration points.
第6题:
● The work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the (75) .
(75)
A. planning element
B.work package
C.subtask
D. working interface
第7题:
The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.
A.Schedule and cost
B.Organization structuring
C.Management coordination
D.Quality of work
第8题:
第9题:
第10题:
组织分解结构(OBS Organizational Breakdown Structure)是一种特殊的WBS。
第11题:
Team member listing, scheduled tasks, and risk identification are part of the:()
第12题:
subdividing
assessing
planning
integrating
第13题:
141 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation
B. Scope planning
C. Scope change control
D. Scope Definition
E. Scope verification
第14题:
● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A task
B level of effort
C sub-task
D project
E work package
第15题:
● A Work Breakdown Structure:
A assures all work is identified
B subdivides the project into manageable segments
C provides the project sponsor with a time-phase task summary
D both A and B
E All of the above.
第16题:
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A Time, schedule and cost.
B Management coordination and organization structuring.
C Work methods and accountability.
D Quality of work.
E Risk and impact decision-making.
第17题:
● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .
(72)
A.identifying individual tasks for a project
B.scheduling the start of tasks
C.scheduling the end of tasks
D.determining potential delays
第18题:
A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements list
A.Essences
B.Elements
C.Purposes
D. Issues
第19题:
The creation of a work breakdown structure (WBS) is the process of______the major project deliverables.
A.subdividing
B.assessing
C.planning
D.integrating
第20题:
第21题:
为了把一个大的项目分解成多个较小的,更易于管理的项目,黑带此时应该选择以下哪个工具:()。
第22题:
The SOW (Statement of Work) is another name for the:()
第23题:
WBS (Work Breakdown Structure).
cost benefit analysis.
requirements specifications.
narrative description of the work to be accomplished.
第24题:
对
错