The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A.Work packages.
B.Subtasks.
C.Tasks.
D.Code of accounts.
E.Integration points.
第1题:
A clear definition of the user's needs serves as the direct basis for the:
A.Work breakdown structure.
B.Functional requirements.
C.Project cost estimate.
D.Selection of personnel.
E.Termination decision.
第2题:
A task-oriented family tree of activities is a:
A.Detailed plan.
B.Linear responsibility chart.
C.Work breakdown structure.
D.Cost account coding system.
E.Work package description.
第3题:
51 Going from Level 2 to Level 4 in the work breakdown structure will result in
A. Less estimating accuracy
B. Better control of the project
C. Lower status reporting costs
D. A greater likelihood that something will fall through the cracks
E. None of the above
第4题:
对一个风险事件的临时应对措施叫做:( )
A.工作项(work item)
B.工作包(work package)
C.权变措施(workaround)
D.工作分解结构(work breakdown structure)
第5题:
● A Work Breakdown Structure:
A assures all work is identified
B subdivides the project into manageable segments
C provides the project sponsor with a time-phase task summary
D both A and B
E All of the above.
第6题:
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A Time, schedule and cost.
B Management coordination and organization structuring.
C Work methods and accountability.
D Quality of work.
E Risk and impact decision-making.
第7题:
● A task-oriented family tree of activities is a:
A Detailed plan.
B Linear responsibility chart.
C Work breakdown structure.
D Cost account coding system.
E Work package description.
第8题:
● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .
(72)
A.identifying individual tasks for a project
B.scheduling the start of tasks
C.scheduling the end of tasks
D.determining potential delays
第9题:
A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements list
A.Essences
B.Elements
C.Purposes
D. Issues
第10题:
The creation of a work breakdown structure (WBS) is the process of______the major project deliverables.
A.subdividing
B.assessing
C.planning
D.integrating
第11题:
第12题:
The SOW (Statement of Work) is another name for the:()
第13题:
The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A.Time, schedule and cost.
B.Management coordination and organization structuring.
C.Work methods and accountability.
D.Quality of work.
E.Risk and impact decision-making.
第14题:
106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A. Work packages.
B. Subtasks.
C. Tasks.
D. Code of accounts.
E. Integration points
第15题:
● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A task
B level of effort
C sub-task
D project
E work package
第16题:
● Going from Level 2 to Level 4 in the work breakdown structure will result in
A Less estimating accuracy
B Better control of the project
C Lower status reporting costs
D A greater likelihood that something will fall through the cracks
E None of the above
第17题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第18题:
● The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A Work packages.
B Subtasks.
C Tasks.
D Code of accounts.
E Integration points.
第19题:
Perform. Quality Control is the process of monitoring and recording resuks of executing the Quality Plan activities to assess performance and recommend necessary changes.( )are the techniques and tools in performing quality control. ①Activity network diagram②Cause and effect diagrams③Inspection④Flow chart⑤Work Breakdown Structure⑥Pareto chart A.①③⑤ B.②④⑤⑥ C.②③④⑤⑥ D.①②③④⑥
第20题:
● The work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the (75) .
(75)
A. planning element
B.work package
C.subtask
D. working interface
第21题:
The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.
A.Schedule and cost
B.Organization structuring
C.Management coordination
D.Quality of work