Going from Level to Level in the work breakdown structure will result in
A.Less estimating accuracy
B.Better control of the project
C.Lower status reporting costs
D.A greater likelihood that something will fall through the cracks
E.None of the above
第1题:
Guidelines for estimating time durations include:
A.Assuming a normal level of labor and equipment.
B.Assuming a normal work week.
C.Using consistent time units
D.Using past actual durations as guides.
E.All or part of each of the above.
第2题:
Which of the following would most likely increase the accuracy of estimating the project cost?
A . Pricing out the work at lower levels in the work breakdown structure.
B . Using historical data.
C . Talking to people who have worked on similar projects.
D . All of the above.
E . A and C only.
第3题:
Risk management requires an understanding that _____ .
A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.
B risk identification must be directly aligned with the Work Breakdown Structure.
C it is merely advanced preparation for possible adverse future events.
D it does not imply complete control of events
E All of the above.
第4题:
106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A. Work packages.
B. Subtasks.
C. Tasks.
D. Code of accounts.
E. Integration points
第5题:
51 Going from Level 2 to Level 4 in the work breakdown structure will result in
A. Less estimating accuracy
B. Better control of the project
C. Lower status reporting costs
D. A greater likelihood that something will fall through the cracks
E. None of the above
第6题:
13 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:
A. Code of accounts.
B. Overhead rates.
C. Budgeting system.
D. Capital budgeting process.
E. All of the above.
第7题:
● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A task
B level of effort
C sub-task
D project
E work package
第8题:
● Going from Level 2 to Level 4 in the work breakdown structure will result in
A Less estimating accuracy
B Better control of the project
C Lower status reporting costs
D A greater likelihood that something will fall through the cracks
E None of the above
第9题:
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A Time, schedule and cost.
B Management coordination and organization structuring.
C Work methods and accountability.
D Quality of work.
E Risk and impact decision-making.
第10题:
● The work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the (75) .
(75)
A. planning element
B.work package
C.subtask
D. working interface
第11题:
第12题:
All messages at the emerg priority level and below from all facilities and messages at the crit priority level and below from the mail and daemon facilities are sent to the TTY of the user sysadmin.
All messages at the emerg priority level and above from all facilities, all messages at any priority level from the mail facility, and all messages at the crit priority level and above from the daemon facilities are sent to the remote host sysadmin.
All messages at the emerg priority level and above from all facilities and messages at the crit priority level and above from the mail and daemon facilities are sent to the remote host sysadmin.
All messages at the emerg priority level and above from all facilities except for the mail facility and messages at the crit priority level and above from the daemon facility are sent to the TTY of the user sysadmin.
第13题:
The work breakdown structure, the work packages, and the company's accounting system are tied together through the:
A . Code of accounts.
B . Overhead rates.
C . Budgeting system.
D . Capital budgeting process.
E . All of the above.
第14题:
The primary source document for establishing the content of the Project Status Report is:
A The project charter
B The Project Plan
C The ASTM Project Document Guide
D The summary work breakdown structure
第15题:
87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.
B. Using historical data.
C. Talking to people who have worked on similar projects.
D. All of the above.
E. A and C only.
第16题:
131 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:
A. Code of accounts.
B. Overhead rates.
C. Budgeting system.
D. Capital budgeting process.
E. All of the above
第17题:
86 The contractual statement of work (CSOW)
A. Must be the same as the proposal statement of work
B. Does not identify reporting requirements
C. Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D. Identifies the contractor's organizational structure for the project
E. All of the above
第18题:
63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A. task
B. level of effort
C. sub-task
D. project
E. work package
第19题:
● The contractual statement of work (CSOW)
A Must be the same as the proposal statement of work
B Does not identify reporting requirements
C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D Identifies the contractor's organizational structure for the project
E All of the above
第20题:
● A Work Breakdown Structure:
A assures all work is identified
B subdivides the project into manageable segments
C provides the project sponsor with a time-phase task summary
D both A and B
E All of the above.
第21题:
● The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A Work packages.
B Subtasks.
C Tasks.
D Code of accounts.
E Integration points.
第22题:
第23题:
The following entry has been added to the syslog.conf file: *.emerg;mail,daemon.crit @ sysadmin Which of the following will result from this entry?()