  • 第1题:

    By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

    A Significantly reduce project risks

    B eliminate project risks

    C provide a rational basis for better decision making

    D identify risks, their impact(s), and any appropriate responses

    E None of the above.


    正确答案:B

  • 第2题:

    84 In which of the following cost estimating techniques are statistics models used:

    A. nonparametric cost estimating

    B. parametric cost estimating

    C. life cycle cost estimating

    D. bottom-up estimating

    E. All of the above.


    正确答案:B

  • 第3题:

    166 In which of the following cost estimating techniques are statistics models used:

    A. nonparametric cost estimating

    B. parametric cost estimating

    C. life cycle cost estimating

    D. bottom-up estimating

    E. All of the above


    正确答案:B

  • 第4题:

    ● Sources for data on activity durations and resource requirements can be gathered from which of the following:

    A Past project records (historical data)

    B Commercial techniques (standard practices, rules of thumb)

    C Past project team members knowledge (experience, oldtimers)

    D All of the above

    E A and C only


    正确答案:D

  • 第5题:

    All the following tools and techniques are helpful to accurately confirming customers’needs,except( 72 )。

    A.questionnaires

    B.prototyping approaches

    C.fishbone diagrams

    D.interviews


    正确答案:C

  • 第6题:

    () is one of the tools and techniques.

    A.Decomposition

    B.Fishbone Diagram

    C.Precedence Diagramming Method of Sequence Activities

    D.Expert Judgment


    正确答案:C

  • 第7题:

    You should be ______ with your movements because of all the security.

    A.useful
    B.skillful
    C.careful
    D.helpful

    答案:C
    解析:
    本题考察词义辨析,题目意为“出于安全考虑,你应该对自己的一举一动十分小心。”A选项意为“有用的,有益的”,B选项意为“熟练的,巧妙的”,C选项意为“仔细的,小心的”,D选项意为“有帮助的,有益的”。只有C选项意思符合题意。
      

  • 第8题:

    all the following tools and techniques are helpful to accurately confirming customers needs,except ( )

    A.questionnaires
    B.prototyping approaches
    C.fishbone diagrams
    D.interviews

    答案:C
    解析:
    翻译:以下所有的工具和技术有助于准确地确定客户的需求,除了A.调查问卷 B.原型法C.鱼刺图 D.访谈问卷、原型法、访谈都是确定用户需求的方法;鱼刺图不是。

  • 第9题:

    执行()菜单命令,可以弹出执行自动布线对话框。

    • A、Tools/All…
    • B、Design/All…
    • C、Auto Route/All…
    • D、Place/All…

    正确答案:B

  • 第10题:

    A technician is tasked with clearing all dust covering the fan vents of servers in a small office.Which of the following tools would be the BEST option?()

    • A、Small vacuum
    • B、Air compressor
    • C、Compressed air can
    • D、Paint brush

    正确答案:A

  • 第11题:

    单选题
    all of the following tools and techniques are helpful to acurately confirming customers needs except ()
    A

    questionnaires

    B

    prototyping approaches

    C

    fishbone diagrams

    D

    interviews


    正确答案: C
    解析: 暂无解析

  • 第12题:

    单选题
    According to the passage, which of the following statements is true?
    A

    The imaging techniques not only measure nerve-cell activity but also the extra flow of blood that surges to the most active brain areas.

    B

    The imaging techniques do not measure nerve-cell activity directly, but measure the flow of blood that surges to the most active brain areas.

    C

    The imaging techniques measure the extra flow of blood that surges to the most active brain areas.

    D

    The imaging techniques measure all the activities of the living brain.


    正确答案: D
    解析:
    是非题。文章第二段主要讲述imaging techniques,该段最后一句指出“they measure the extra flow of blood that surges to the most active brain areas.”(这两种成像技术测量的是涌到大脑最活跃部分的血液的额外流量),对应选项C。

  • 第13题:

    59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

    A. Significantly reduce project risks

    B. eliminate project risks

    C. provide a rational basis for better decision making

    D. identify risks, their impact(s), and any appropriate responses

    E. None of the above


    正确答案:B

  • 第14题:

    167 All the techniques described below can be used to keep a meeting focused except:

    A. Recall agenda items/purpose of meeting

    B. Summarize discussion periodically

    C. Encourage pursuit of interesting new ideas

    D. Rephrase unclear ideas presented by group members

    E. All are acceptable techniques


    正确答案:C

  • 第15题:

    98 Which of the following tools and techniques can be used to collect information for the project closure reports?

    A. Customer Surveys

    B. Brainstorming

    C. Document and Performance Analysis

    D. Lessons Learned

    E. All of the above


    正确答案:E

  • 第16题:

    All the following are root-cause analysis techniques used in quality management except( 74 ).

    A.fishbone diagrams

    B.Ishikawa diagrams

    C.system or process flowcharts

    D.checklists


    正确答案:D

  • 第17题:

    all of the following tools and techniques are helpful to acurately confirming customers needsexcept ()

    A.questionnaires

    B.prototyping approaches

    C.fishbone diagrams

    D.interviews


    正确答案:C
    以下所有的工具和技术有助于准确地确定客户的需求,除了()A、问卷B、原型方法C、鱼骨图D、访谈

  • 第18题:

    When a teacher makes a lesson plan, he should do all of the following EXCEPT_____________

    A.design techniques that have easy and difficult aspects of items
    B.try to design techniques that involve all students
    C.take into consideration the different demands and needs of all students
    D.cater only to the top range students to make sure the progress of teaching

    答案:D
    解析:
    考查教学设计。教师在进行教学设计时,应考虑到大多数学生的水平,并根据不同类型学生的特点设计出难易结合的教案.故选D。

  • 第19题:

    ( )is one of the tools and techniques.

    A.Decomposition
    B.Fish bone Diagram
    C.Precedence Diagramming MethoD.of Sequence Activities
    D.Expert Judgment

    答案:C
    解析:
    翻译:前导图法是活动排序的工具和技术之一。
    A.分解 B.鱼骨图
    C.PDM图 D.专家判断

  • 第20题:

    Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.

    • A、PERT
    • B、Resourceleveling
    • C、Schedulecompression
    • D、Critical chain method

    正确答案:D

  • 第21题:

    A workstation no longer has network connectivity. Upon visual inspection, all connectors andsettings seem to be properly configured. Which of the following tools should the technician use to troubleshoot this issue? ()

    • A、PSU tester
    • B、Loopback plug
    • C、Cable tester
    • D、Multimeter

    正确答案:C

  • 第22题:

    Cindy wants to set up third-party tools so she can access them via the designer. Which one of  the following should cindy do?()

    • A、 file-> inport 
    • B、 tools->import 
    • C、 tools->add tools 
    • D、 shared resources->third party tools

    正确答案:B

  • 第23题:

    单选题
    Which of the following items don’t belong to dock repair works?()
    A

    making the repair list, booking spare parts and special tools for the dock repair

    B

    shutting off all of the SW valves to outboard

    C

    the sketches or diagrams used for the dock repair

    D

    cleaning up the oil tank and boiler before enter the dock


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    When dealing with customers on the phone that are not very comfortable with technology, which of the following techniques would be MOST helpful to ensure that effective communication is taking place?()
    A

    Frequently paraphrase what the caller is saying.

    B

    Repeat what is being said multiple times so that the customer can understand exactly what to do.

    C

    Speak very slowly when replying to the customer.

    D

    Tell the customer to send an email stating exactly what the problem is so that the communication between the two parties is clear.


    正确答案: D
    解析: 暂无解析