One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()A、Two p5 570 16 way 1.9 MHz machinesB、One p5 590 32 way 1.65 MHz machinesC、One p5 595 3

题目

One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()

  • A、Two p5 570 16 way 1.9 MHz machines
  • B、One p5 590 32 way 1.65 MHz machines
  • C、One p5 595 32 way 1.65 MHz machines
  • D、Two p5 570 16 way 1.65 MHz machines

相似考题

4. Companycom has a 16 way 1.65 GHz p5 590 and wants to install a i5/OS partition on their server. The customer wants to keep installation costs to a minimum by sharing devices between all LPARs. Before the operating system can be installed in this partition, the customer was told that there are certain limitations that must be observed. What are these limitations?()A、When the i5/OS partition is housed in the p5 590, the HMC allows seamless installation in a partition as long as the minimum one processor, 256 MB of memory, one Ethernet and one boot adapter/disk is available from internal hardware. B、V5R3 and later releases of i5/OS can be installed on a POWER5 server partition. Only one processor can be assigned to the i5/OS. A special expansion tower must be ordered. This expansion tower and its devices can be shared with other OS partitions. C、When the i5/OS partition is housed in the p5 590, the 5250 Twinaxial console must be used to set up the partition. Only one processor can be assigned to the i5/OS partition. A special expansion tower must be ordered to house the IOPs. Devices in the special expansion tower can be shared with other Linux partitions.  D、V5R3 and later releases of i5/OS can be installed on IBM eServer p5 servers. i5/OS can run on two processors in the p5 590. A special expansion tower must be ordered. This expansion tower and its devices cannot be shared with other OS partitions. The iSeries expansion towers are seen by the IBM eServer p5 server as an I/O subsystem.

更多“One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()A、Two p5 570 16 way 1.9 MHz machinesB、One p5 590 32 way 1.65 MHz machinesC、One p5 595 32”相关问题
  • 第1题:

    Companycom is considering a partitioned solution which will require cumulative rPerf total of 150. The original sizing came back recommending a 32-way p5 590. However, they have a requirement for future scalability and availability is important. Which of the following would be the best reason to recommend a p5 595?()

    • A、The p5 595 would allow for COD
    • B、The p5 595 includes the Advanced Power Virtualization hardware and software
    • C、The p5 595 is priced the same as the p5 590 given the same number/type of CPUs
    • D、The p5 595 performance would be equivalent to the p5 590 given the same number/type of CPUs

    正确答案:A

  • 第2题:

    Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()

    • A、Free up one HMC and update the software for use with the p5 570
    • B、Connect the new p5 570 server to an existing HMC and manage the p690s and p5 570 from that HMC
    • C、Order a new HMC to support the new p5 570 server since the CR3 HMC is not supported for a p5 570
    • D、Backup the HMC to DVD-RAM and select HMC migrate to move all the profile data to the new HMC software

    正确答案:A

  • 第3题:

    Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()

    • A、Upgrade the p690 to a p5 590 server running AIX 5.3
    • B、Upgrade the p690 server to AIX 5.3 and implement Advanced Power Virtualization
    • C、Purchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adapters
    • D、Purchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization

    正确答案:D

  • 第4题:

    Companycom is purchasing a 64-way p5 595. They have determined the location for the server is in a datacenter which does not have a raised floor. Which of the following would best meet the server requirements?()

    • A、The server must be installed into a location with a raised floor for optimum system cooling  and cable management.
    • B、The server should be purchased as a p5 590 and then upgraded to a p5 595. This will eliminate the need for a raised floor environment.
    • C、The server should be purchased as 32-way p5 595 and then upgraded to a 64-way. This will eliminate the need for a raised floor environment.
    • D、The server can be installed into a location without a raised floor if an RPQ is obtained. It is a strong IBM recommendation for a raised floor, not a requirement.

    正确答案:A

  • 第5题:

    Companycom is planning for a 64-way p5 595. The plan is to use Virtual IO Servers and micropartitioning. What is the maximum number of partitions they can allocate?()

    • A、128
    • B、254
    • C、320
    • D、640

    正确答案:B

  • 第6题:

    The storage specialist sized a DS8800 proposal with eight host adapters in the four-port version. 240 drives of the 146GB-15k rpm type will be installed. The proposal needs to meet a very competitive price. The customer will have only minor capacity growth in the future.  Which of the following solutions best meets these requirements()

    • A、offer a DS8800 one-frame system in four-way processor version and standard cabling
    • B、offer a DS8800 one-frame system in two-way processor version and business class cabling
    • C、offer a DS8800 one-frame system in two-way processor version and standard cabling
    • D、offer a DS8800 one-frame system in four-way processor version and business class cabling

    正确答案:A

  • 第7题:

    During the Solution Assurance for a p5 590, Companycom states there is a plan to install OEM Emulex cards in the p5 590. The customer assumes there will be no problem with the plan since IBM resells the Emulex cards. What is the correct response for the customer?()

    • A、The IBM CE will install the card
    • B、The card will not be supported by IBM
    • C、The AIX device driver should work fine
    • D、The customer is correct, there should be no problem

    正确答案:B

  • 第8题:

    单选题
    A client has an existing Logical Partition (LPAR) on a p650 running AIX 5.2 and will be porting this LPAR to a p5 590. A mksysb has been run to tape, and a compatible tape drive is available and allocated to the target LPAR on the p5 590. What additional resource needs to be available on the p5 590?()
    A

    A CD or DVD with installation media

    B

    An internal SCSI adapter in the target LPAR

    C

    An Ethernet adapter for access to an FTP server

    D

    Advanced Power Virtualization feature of the p5 590


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    For the p5 590 and p5 595 servers, the HMC must be directly attached. Why is the use of a private service network between HMC and the p5 590 required?()
    A

    The Bulk Power Controllers are dependent upon the HMC to provide them with DHCP  addresses.

    B

    A firewall is required to isolate the private network from any of the open networks to which the HMC is attached.

    C

    Network communications can be implemented through an open network. No private network  is required but it is recommended.

    D

    All p5 590 and 595 servers are shipped with one service processor card. A private network is  required to manage DHCP addresses.


    正确答案: A
    解析: 暂无解析

  • 第10题:

    单选题
    One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()
    A

    Two p5 570 16 way 1.9 MHz machines

    B

    One p5 590 32 way 1.65 MHz machines

    C

    One p5 595 32 way 1.65 MHz machines

    D

    Two p5 570 16 way 1.65 MHz machines


    正确答案: D
    解析: 暂无解析

  • 第11题:

    单选题
    Companycom is buying an application solution that bases its software licensing on the number of CPUs per machine. They will be running two instances of this application and will require 8 CPUs each. A second application is priced based on CPUs per LPAR as well as the class of machine. That application will require 8 CPUs. What is the best hardware to propose to keep the software cost low?()
    A

    A 24 way p5 595 with 3 LPARs

    B

    A 24 way p5 595 with 2 LPARs

    C

    One p5 570s 16 way and one p5 570 8 way

    D

    One p5 595 12 way active and 12 way inactive, and one p5 570 8 way


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    During the Solution Assurance for a p5 590, Companycom states there is a plan to install OEM Emulex cards in the p5 590. The customer assumes there will be no problem with the plan since IBM resells the Emulex cards. What is the correct response for the customer?()
    A

    The IBM CE will install the card

    B

    The card will not be supported by IBM

    C

    The AIX device driver should work fine

    D

    The customer is correct, there should be no problem


    正确答案: C
    解析: 暂无解析

  • 第13题:

    Companycom has just added some new disk drives to a p5 590. The customer needs to know the largest Logical Track Group that these drives will support. What is the best way to locate this information?()

    • A、Use lquerypv to read the drive
    • B、Use lspv and look at PP Size value
    • C、Look on the outside of the drive itself
    • D、Use bootinfo to find the LTG on the drive

    正确答案:A

  • 第14题:

    Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()

    • A、Include a new HMC in the order to connect to the p5 595
    • B、Include a pair of new HMCs in the order to connect to the p5 595
    • C、Include a media set for POWER5 HMC in the order to upgrade one of the existing HMC’s to POWER5 capabilities
    • D、Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC to  POWER5 capabilities Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC? To POWER5 capabilities

    正确答案:B

  • 第15题:

    A client has an existing Logical Partition (LPAR) on a p650 running AIX 5.2 and will be porting this LPAR to a p5 590. A mksysb has been run to tape, and a compatible tape drive is available and allocated to the target LPAR on the p5 590. What additional resource needs to be available on the p5 590?()

    • A、A CD or DVD with installation media
    • B、An internal SCSI adapter in the target LPAR
    • C、An Ethernet adapter for access to an FTP server
    • D、Advanced Power Virtualization feature of the p5 590

    正确答案:A

  • 第16题:

    A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()

    • A、Implement a proxy server to provide multiple sources to one destination 
    • B、Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two 
    • C、Purchase a network hub or switch so both p5 570s can connect to the single HMC 
    • D、Purchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used

    正确答案:C

  • 第17题:

    A customer plans to purchase a p5-570 that will run in SMP mode to host a large financial database on AIX 5.2.  The application is sized for an 8-way 1.65-GHz machine.  They do not currently have an existing HMC that supports p5 machines. This organization experiences unpredictable short-term spikes in processor utilization.  To mitigate the risk to their business, they are interested in IBM’s CoD offering.  In addition to the 8-way system, what else should the pSeries technical specialist recommend to the customer?()

    • A、Another p5-570 building block
    • B、Capacity Backup p5-570 building block
    • C、Another p5-570 building block and at least one HMC
    • D、Capacity Backup p5-570 building block and at least one HMC

    正确答案:C

  • 第18题:

    Companycom has a p5 595 running 12 LPARs. They are interested in high bandwidth, secure communication between two of the LPARs within the p5 595 server. They do not have any unused Ethernet adapters. Which of the following recommendations will best meet this requirement?()

    • A、Utilize the integrated 10/100/1000 network interface
    • B、Implement Virtual Ethernet to enable inter-partition communication
    • C、Implement shared Ethernet with the Ethernet adapters utilized in the other LPARs
    • D、Implement a Point to Point protocol serial communication between the p5 595 serial ports

    正确答案:B

  • 第19题:

    Which server houses the database partitions in the AIX BCU V2.1? ()

    • A、 IBM System p5 570  
    • B、 IBM System p5 575  
    • C、 IBM System p5 590  
    • D、 IBM System p5 595

    正确答案:B

  • 第20题:

    单选题
    One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()
    A

    Two p5 570 16 way 1.9 MHz machines

    B

    One p5 590 32 way 1.65 MHz machines

    C

    One p5 595 32 way 1.65 MHz machines

    D

    Two p5 570 16 way 1.65 MHz machines


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    Which server houses the database partitions in the AIX BCU V2.1? ()
    A

     IBM System p5 570  

    B

     IBM System p5 575  

    C

     IBM System p5 590  

    D

     IBM System p5 595


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate with the outside world. What is the minimum number of Ethernet adapters that should be provided to ensure redundancy and no single point of failure?()
    A

    One single port Ethernet adapter

    B

    Four dual port Ethernet adapters

    C

    Two single port Ethernet adapters

    D

    Eight single port Ethernet adapters


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    Companycom is planning for a 64-way p5 595. The plan is to use Virtual IO Servers and micropartitioning. What is the maximum number of partitions they can allocate?()
    A

    128

    B

    254

    C

    320

    D

    640


    正确答案: B
    解析: 暂无解析