For the p5 590 and p5 595 servers, the HMC must be directly attached. Why is the use of a private service network between HMC and the p5 590 required?()
第1题:
Companycom is installing a p5 590 with a HMC to manage LPARs. The customer is very concerned about security and wants to restrict network traffic that is not necessary. What is necessary for communication between the LPARs and the HMC?()
第2题:
Companycom is considering a partitioned solution which will require cumulative rPerf total of 150. The original sizing came back recommending a 32-way p5 590. However, they have a requirement for future scalability and availability is important. Which of the following would be the best reason to recommend a p5 595?()
第3题:
A system administrator is installing a p5 590 server with an HMC. After pulling the websm client down, it is not possible to connect to the HMC. The HMC can be pinged from the client. Which of the following settings should be verified next?()
第4题:
A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()
第5题:
Companycom purchased a p5 570 with no plans to partition. The customer plans to use the ASMI interface to power on and off the machine. How can ASMI be accessed without a HMC?()
第6题:
A customer currently has five partitioned POWER4 systems and is adding new systems. When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()
第7题:
A client tried to upgrade the system firmware on a p5 590, but it failed. What is the minimum requirement to update the system firmware from the HMC if inventory scout is already installed?()
第8题:
A new p5 customer has just installed a partitioned p5-550 alongside some older POWER4 servers. The pSeries technical specialist has received a call to say that the existing HMC (7315) cannot connect to the new server. How can the specialist help the customer?()
第9题:
An 8-port adapter to the HMC
A hub for the private network
An additional Ethernet card to the HMC
An additional Ethernet card for each partition
第10题:
The resources must be unallocated in an LPAR
The microcode on the pSeries must be current
All network adapters on the LPAR must be defined
Network connectivity and name resolution capability between HMC and LPARs
第11题:
A public internet connection
All of the Logical Partitions need to be active
One partition must be configured with Service Authority
A local Repository must be configured prior to the update
第12题:
An additional switch for the new HMc
Asynchronous adapters on the new HMc
The two 570 servers are directly connected to the new HMc
One 570 is directly connected to the new HMC and the other is directly connected to the existing HMc
第13题:
Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()
第14题:
Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()
第15题:
Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()
第16题:
A client has an existing Logical Partition (LPAR) on a p650 running AIX 5.2 and will be porting this LPAR to a p5 590. A mksysb has been run to tape, and a compatible tape drive is available and allocated to the target LPAR on the p5 590. What additional resource needs to be available on the p5 590?()
第17题:
A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()
第18题:
Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()
第19题:
Companycom is trying to communicate with the service processor of the a new p5 590. However, the customer can not access the service processor. What needs to be done to fix this problem?()
第20题:
Which server houses the database partitions in the AIX BCU V2.1? ()
第21题:
The Bulk Power Controllers are dependent upon the HMC to provide them with DHCP addresses.
A firewall is required to isolate the private network from any of the open networks to which the HMC is attached.
Network communications can be implemented through an open network. No private network is required but it is recommended.
All p5 590 and 595 servers are shipped with one service processor card. A private network is required to manage DHCP addresses.
第22题:
An administrative VLAN with port 1808
Port 657 which must remain open to TCP/IP and UDP traffic
Network addresses are provided by DHCP services on the network
DHCP on the HMC is required to be on to communicate between LPAR and HMC
第23题:
The routes on the HMC
The firewall setting of the LAN adapter
The name resolution protocol on the p5 590 server
The subnet mask settings on the Ethernet adapters