A Project Status Report would include all of the following except:
A Cost and schedule reports
B Changes to scope. cost or schedule
C Narrative explanation of variances
D Personnel problems on the project
E Upcoming activities
第1题:
What is the relative priority of project Cost, Schedule and Quality?
A . 1)Cost - 2)Schedule - 3)Quality
B . 1)Quality - 2)Schedule - 3)Cost
C . 1)Quality - 2)Cost - 3)Schedule
D . 1)Schedule - 2)Quality - 3)Cost
E . All are of equal priority
第2题:
In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.
A unit price
B cost plus incentive fee
C cost plus fixed fee
D firm fixed price
E B and D only
第3题:
130 What is the relative priority of project Cost, Schedule and Quality?
A. 1)Cost - 2)Schedule - 3)Quality
B. 1)Quality - 2)Schedule - 3)Cost
C. 1)Quality - 2)Cost - 3)Schedule
D. 1)Schedule - 2)Quality - 3)Cost
E. All are of equal priority
第4题:
57 Which of the following are types of status reports?
A. document, variance, trend and exception
B. cost, trend, schedule and acquisition
C. cost, schedule, technical performance
D. analysis, cost, performance and schedule
E. All of the above.
第5题:
95 A Project Status Report would include all of the following except:
A. Cost and schedule reports
B. Changes to scope. cost or schedule
C. Narrative explanation of variances
D. Personnel problems on the project
E. Upcoming activities
第6题:
96 A negative cost variance and positive schedule variance means:
A. The project is under budget and ahead of schedule
B. The project is over budget and behind schedule
C. The project is over budget and ahead of schedule
D. The project will be overrun but ahead of schedule at completion
第7题:
● Which of the following are types of status reports?
A document, variance, trend and exception
B cost, trend, schedule and acquisition
C cost, schedule, technical performance
D analysis, cost, performance and schedule
E All of the above.
第8题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第9题:
Schedule control is concerned with all the following except (74)
A.influencing the factors that create schedule changes to ensure that the changes are beneficial
B.determing that the schedule has changed
C.managing the actual changes when and as they occur
D.changing the shedule based on customer demands
第10题:
In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on (74)
A.the quality of the schedule and cost control analysis
B.customer satisfaction
C.customer compromise in defining its needs
D.exceeding customer requirements through gold-plating
第11题:
An example of scope verification is ().
第12题:
This process assigns cost estimates to project activities including risks and contingency plans.
The cost baseline will be used to measure variances and future project performance.
This process assigns cost estimates for expected future period operating costs.
The cost baseline is the expected cost for the project.
第13题:
A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
第14题:
42 In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.
A. unit price
B. cost plus incentive fee
C. cost plus fixed fee
D. firm fixed price
E.B and D only
第15题:
41 The scope of a project can be expected to change if:
A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs
C. The project manager is assigned after the project is defined, and the cost and schedule are approved
D. A clear objective is not provided
E. All of the above are possible based upon the situation
第16题:
72 Project trade-offs vary between
A. risk, cost and schedule.
B. direct cost, indirect cost, and resource availability
C. quality, schedule and time
D. cost, quality and schedule
E. contract terms, scope and budget
第17题:
A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.
第18题:
139 Which of the following are types of status reports?
A. document, variance, trend and exception
B. cost, trend, schedule and acquisition
C. cost, schedule, technical performance
D. analysis, cost, performance and schedule
E. All of the above
第19题:
● The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
第20题:
An example of scope verification is __(73)__ .
A.review the performance of an installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project
第21题:
Schedule control is concerned with all the following except ( )
A.influencing the factors that create schedule changes to ensure that the changes are beneficial
B.determing that the schedule has changed
C.managing the actual changes when and as they occur
D.changing the shedule based on customer demands
第22题:
第23题:
You are working on the cost budget for one project. Which of the following is true()