Expectancy theory as applied to project management implies that:
A The team will work the hardest on those goals that are clearly explained by the project manager
B The more rewards that the project manager provides, the better the performance of the team
C Team members will work hardest for those project goals that also bring satisfaction to personal goals
D Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members
E None of the above
第1题:
In a matrix organizational form, MBO may be difficult to implement:
A . If the functional employees are supervised closely by the line manager rather than the project manager
B . Unless the project manager has an input into the employee's performance review
C . Unless the project and line managers agree on the ultimate objective
D . Unless the project and line managers agree to the duration of the task
E . None of the above are correct answers
第2题:
189 Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .
A. Project managers; team members
B. Company management philosophy in treating employees; the average worker
C. Project sponsors; project managers
D. The functional team; project sponsors
E. Recruitment policy; wage and salary administration
第3题:
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第4题:
●To ensure the project team provides the functionality the customerexpects in a new piece of software, the project manager ask the customer forsign-off on the design criteria. These documents are(75).
(75) A. technical specifications
B. performance specifications
C. product descriptions
D. quality assurance
第5题:
The(70)provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.project charter
第6题:
The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders
第7题:
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
第8题:
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performancIf a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第9题:
第10题:
第11题:
The()provides the project manager with the authority to apply organizational resources to project activities.
第12题:
project management plan
contract
project human resource plan
project charter
第13题:
156 Expectancy theory as applied to project management implies that:
A. The team will work the hardest on those goals that are clearly explained by the project manager
B. The more rewards that the project manager provides, the better the performance of the team
C. Team members will work hardest for those project goals that also bring satisfaction to personal goals
D. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members E. None of the above
第14题:
123 The scope baseline/project charter is prepared by the:
A. Project manager
B. Project manager and project office
C. Project manager, project office and functional team
D. Project manager, project office, functional team and project sponsor
E. Project manager, project sponsor and customer/user
第15题:
● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:
A The project manager and project office personnel.
B The project team and functional managers.
C The project sponsor.
D All of the above.
E A and B only.
第16题:
are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.
A.Project manager
B.Project team member
C.Sponsor
D.Proiect stakeholders
第17题:
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第18题:
The( )provides the project manager with the authority to apply organizational resources to project activities。
A.project management plan
B.project charter
C.project human resource plan
D.project stakeholders
第19题:
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第20题:
The (73) provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.project charter
C.project human resource plan
D.project stakeholders
第21题:
第22题:
The()provides the project manager with the authority to apply organizational resources to project activities.
第23题:
project management plan
contract
project human resource plan
projectcharter