156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is sti

题目

156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:

A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.

C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.

D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)

E. Is the same since baseline schedules cannot change once the development phase is completed


相似考题
参考答案和解析
正确答案:C
更多“156During project execution, the customer authorizes and funds a scope change which requir ”相关问题
  • 第1题:

    假设需要更改表名“CUSTOMER”为“CUSTOMER_CHANGE”,可以使用()语句。

    A.ALTER TABLE CUSTOMER RENAME CUSTOMER_CHANGE

    B.ALTER TABLE CUSTOMER RENAME TO CUSTOMER_CHANGE

    C.RENAME TABLE CUSTOMER TO CUSTOMER_CHANGE

    D.RENAME TABLE CUSTOMER CUSTOMER_CHANGE


    参考答案:B

  • 第2题:

    Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk
    B.problem
    C.result
    D.data

    答案:A
    解析:
    风险不是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第3题:

    哈默和钱皮认为,有三种力量,使今天的公司陷入惊恐不安的陌生境地。他们称之为3C(Customer, Competition, Change),也就是()。

    A.顾客

    B.竞争

    C.变化

    D.上帝


    顾客?竞争?变革

  • 第4题:

    Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.

    A.risk
    B.problem
    C.result
    D.data

    答案:A
    解析:
    风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A 是风险,选项B 是问题,选项 C 是结果,选项 D 是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择 A

  • 第5题:

    假设需要更改表名“CUSTOMER”为“CUSTOMER_CHANGE”,可以使用()语句。

    A.ALTER TABLE CUSTOMER RENAME CUSTOMER_CHANGE;

    B.ALTER TABLE CUSTOMER RENAME TO CUSTOMER_CHANGE;

    C.RENAME TABLE CUSTOMER TO CUSTOMER_CHANGE;

    D.RENAME TABLE CUSTOMER CUSTOMER_CHANGE;


    ALTER TABLE CUSTOMER RENAME TO CUSTOMER_CHANGE

  • 第6题:

    哈默和钱皮认为,有三种力量,使今天的公司陷入惊恐不安的陌生境地。他们称之为3C(customer,competition,change),也就是()。

    A.顾客

    B.竞争

    C.变化

    D.上帝