参考答案和解析
正确答案:C
更多“● Which of the following are types of status reports?A document, variance, trend and exceptionB cost, trend, schedule and acquisitionC cost, schedule, technical performanceD analysis, cost, performance and scheduleE All of the above.”相关问题
  • 第1题:

    What is the relative priority of project Cost, Schedule and Quality?

    A . 1)Cost - 2)Schedule - 3)Quality

    B . 1)Quality - 2)Schedule - 3)Cost

    C . 1)Quality - 2)Cost - 3)Schedule

    D . 1)Schedule - 2)Quality - 3)Cost

    E . All are of equal priority


    正确答案:E

  • 第2题:

    A Project Status Report would include all of the following except:

    A Cost and schedule reports

    B Changes to scope. cost or schedule

    C Narrative explanation of variances

    D Personnel problems on the project

    E Upcoming activities


    正确答案:D

  • 第3题:

    Which of the following types of contracts allows the owner to transfer risk to the contractor:

    A cost plus incentive fee

    B cost sharing

    C firm fixed price

    D cost plus fixed fee

    E performance guarantees


    正确答案:C

  • 第4题:

    The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:

    A post project evaluation

    B post contract evaluation

    C post mortem

    D procurement performance evaluation

    E contractor's performance evaluation


    正确答案:E

  • 第5题:

    181 The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:

    A. post project evaluation

    B. post contract evaluation

    C. post mortem

    D. procurement performance evaluation

    E. contractor's performance evaluation


    正确答案:E

  • 第6题:

    51 Which of the following types of contracts allows the owner to transfer risk to the contractor:

    A. cost plus incentive fee

    B. cost sharing

    C. firm fixed price

    D. cost plus fixed fee

    E. performance guarantees


    正确答案:C

  • 第7题:

    18 The difference between the BCWS and the BCWP is referred to as the:

    A. Schedule variance

    B Cost variance.

    C. Estimate of completion

    D. Actual cost of the work performed

    E. None of the above


    正确答案:A

  • 第8题:

    100 The difference between the BCWS and the BCWP is referred to as the:

    A. Schedule variance

    B. Cost variance.

    C. Estimate of completion

    D. Actual cost of the work performed

    E. None of the above


    正确答案:A

  • 第9题:

    72 Project trade-offs vary between

    A. risk, cost and schedule.

    B. direct cost, indirect cost, and resource availability

    C. quality, schedule and time

    D. cost, quality and schedule

    E. contract terms, scope and budget


    正确答案:D

  • 第10题:

    96 A negative cost variance and positive schedule variance means:

    A. The project is under budget and ahead of schedule

    B. The project is over budget and behind schedule

    C. The project is over budget and ahead of schedule

    D. The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第11题:

    The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned


    正确答案:C
    挣值管理(EVM)是一种常用的绩效测量方法。它综合考虑项目范围、进度与成本指标,帮助项目管理团队评估项目绩效。如果某个项目的成本绩效指数(CPI=EV/AC)值小于1.0,则说明已完成的工作的成本超支(the cost overrun for work completed)。

  • 第12题:

    The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ).

    A.Cost Variance
    B.Schedule Variance
    C.EarneD.Value
    D.Cost PerformeD.Index

    答案:A
    解析:
    BCWP与ACWP之间的差值是 。

    A.成本偏差 B.进度偏差 C.挣值 D. 成本绩效

  • 第13题:

    A negative cost variance and positive schedule variance means:

    A The project is under budget and ahead of schedule

    B The project is over budget and behind schedule

    C The project is over budget and ahead of schedule

    D The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第14题:

    In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:

    A Work breakdown structure

    B milestone review and schedule technique

    C cost/schedule control system

    D planning programming budget system

    E program and evaluation review technique


    正确答案:A

  • 第15题:

    In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

    A unit price

    B cost plus incentive fee

    C cost plus fixed fee

    D firm fixed price

    E B and D only


    正确答案:D

  • 第16题:

    Which of the following types of contracts is equivalent to a cost plus contract:

    A Fixed firm price

    B Cost reimbursable

    C Fixed price plus incentive fee

    D progress payments

    E All of the above.


    正确答案:B

  • 第17题:

    42 In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

    A. unit price

    B. cost plus incentive fee

    C. cost plus fixed fee

    D. firm fixed price

    E.B and D only


    正确答案:D

  • 第18题:

    130 What is the relative priority of project Cost, Schedule and Quality?

    A. 1)Cost - 2)Schedule - 3)Quality

    B. 1)Quality - 2)Schedule - 3)Cost

    C. 1)Quality - 2)Cost - 3)Schedule

    D. 1)Schedule - 2)Quality - 3)Cost

    E. All are of equal priority


    正确答案:E

  • 第19题:

    84 In which of the following cost estimating techniques are statistics models used:

    A. nonparametric cost estimating

    B. parametric cost estimating

    C. life cycle cost estimating

    D. bottom-up estimating

    E. All of the above.


    正确答案:B

  • 第20题:

    57 Which of the following are types of status reports?

    A. document, variance, trend and exception

    B. cost, trend, schedule and acquisition

    C. cost, schedule, technical performance

    D. analysis, cost, performance and schedule

    E. All of the above.


    正确答案:C

  • 第21题:

    95 A Project Status Report would include all of the following except:

    A. Cost and schedule reports

    B. Changes to scope. cost or schedule

    C. Narrative explanation of variances

    D. Personnel problems on the project

    E. Upcoming activities


    正确答案:D

  • 第22题:

    139 Which of the following are types of status reports?

    A. document, variance, trend and exception

    B. cost, trend, schedule and acquisition

    C. cost, schedule, technical performance

    D. analysis, cost, performance and schedule

    E. All of the above


    正确答案:C

  • 第23题:

    The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).

    A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index


    正确答案:A