161 Time management is the allocation of time in a project's life cycle through the process of: A. PlanningB. Estimating.C. Scheduling.D. ControllingE. All of the above

题目

161 Time management is the allocation of time in a project's life cycle through the process of: A. Planning

B. Estimating.

C. Scheduling.

D. Controlling

E. All of the above


相似考题
更多“161Time management is the allocation of time in a project's life cycle through the process ”相关问题
  • 第1题:

    A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to(请作答此空)project(s).

    A.a single
    B.a particular
    C.some
    D.all

    答案:D
    解析:
    表示过程管理涉及应用于所有项目的活动。附(参考翻译):一个项目是一个独特的、复杂的、相互关联的活动的[临时]序列,有一个目标或目的,必须在特定的时间、预算内和根据规范完成。项目管理是一个范围界定、计划、人员配置、组织、指导和控制可接受系统开发的过程,在规定的时间内以最低的成本进行。对于任何系统开发项目,有效的项目管理都是必要的,以确保项目在截止日期前完成,在可接受的预算内开发,并满足客户的期望和规范,项目管理是从项目开始时开始的过程,延伸到一个项目中,直到项目完成才达到顶点。良好的项目管理的先决条件是定义良好的系统开发过程。过程管理是一项持续的活动,它记录、管理和改进组织为系统开发所选择的方法(“过程”),过程管理涉及应用于所有项目的活动、可交付成果和质量标准。

  • 第2题:

    A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)(请作答此空)system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).

    A.perfect
    B.acceptable
    C.controlled
    D.completed

    答案:B
    解析:
    表示可接受的、认可的、令人满意的意思。
    附(参考翻译):一个项目是一个独特的、复杂的、相互关联的活动的[临时]序列,有一个目标或目的,必须在特定的时间、预算内和根据规范完成。项目管理是一个范围界定、计划、人员配置、组织、指导和控制可接受系统开发的过程,在规定的时间内以最低的成本进行。对于任何系统开发项目,有效的项目管理都是必要的,以确保项目在截止日期前完成,在可接受的预算内开发,并满足客户的期望和规范,项目管理是从项目开始时开始的过程,延伸到一个项目中,直到项目完成才达到顶点。良好的项目管理的先决条件是定义良好的系统开发过程。过程管理是一项持续的活动,它记录、管理和改进组织为系统开发所选择的方法(“过程”),过程管理涉及应用于所有项目的活动、可交付成果和质量标准。

  • 第3题:

    ()is a document?generated by the?creating?WBS?process?that?support the WBS,which provides?more?detailed?descriptions?of the components in the?WBS.

    A.The project?charter
    B.The?project?scope statement
    C.The?WBS dictionary
    D.The?activity list

    答案:C
    解析:
    本题翻译:()是由支持WBS的创建WBS过程生成的文档,它提供了WBS中组件的更详细描述。
    A.项目章程B.项目范围说明书C.WBS词典D.活动列表
    本题考查的是范围管理中的WBS词典,正确选项为C:WBS词典。
    在制作WBS的过程中,要给WBS的每个部分赋予一个账户编码标志符,它们是成本、进度和资源使用信息汇总的层次结构。需要生成一些配套的文件,这些文件需要和WBS配套使用,称为WBS词典。所以说WBS词典是创建WBS过程生成的支持WBS的文档,它提供了WBS中组件的更详细描述。

  • 第4题:

    A project is a [temporary] ( ) of unique, complex, and connected activities having one goal or purpose and that must be completed by a specific time, within budget, and according to ( )Project management is the process of scoping, planning, staffing, organizing, directing, and controlling the development of a(n) (请作答此空) system at a minimum cost within a specified time frame.
    For any systems development project, effective project management is necessary to ensure that the project meets the ( ), is eveloped within an acceptable budget, and fulfills customer expectations and specifications, Project management is a process that starts at the beginning of a project, extends through a project, and doesn't culminate until the project is completed.
    The prerequisite for good project management is a well-defined system development process. Process management is an ongoing activity that documents, manages the use of, and improves an organization s chosen methodology (the"process")for system development, Process management is concemed with the activities, deliverables, and quallty standards to be applled to ( ) project(s).

    A.perfect
    B.acceptable
    C.controlle
    D.compl

    答案:B
    解析:

  • 第5题:

    A project is a [temporary] (请作答此空) of unique, complex, and connected activities having one goal or purpose and that must be completed by a specific time, within budget, and according to (
    Project management is the process of scoping, planning, staffing, organizing, directing, and controlling the development of a(n) ( ) system at a minimum cost within a specified time frame.
    For any systems development project, effective project management is necessary to ensure that the project meets the ( ), is eveloped within an acceptable budget, and fulfills customer expectations and specifications, Project management is a process that starts at the beginning of a project, extends through a project, and doesn't culminate until the project is completed.
    The prerequisite for good project management is a well-defined system development process. Process management is an ongoing activity that documents, manages the use of, and improves an organization s chosen methodology (the"process")for system development, Process management is concemed with the activities, deliverables, and quallty standards to be applled to ( ) project(s).

    A.task
    B.work
    C.sequence
    D.activity

    答案:C
    解析:

  • 第6题:

    在实际的工作计划制定过程中,主要采用三种方法:“基于项目(Project-based)”,“基于流程(Process-based)”和基于时间(Time-based)。


    以上都是