The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:A . Multiplying the actual hours worked on the project by the budgeted labor rate.B . Multiplying the budgeted hours to complete the task by the bu

题目

The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:

A . Multiplying the actual hours worked on the project by the budgeted labor rate.

B . Multiplying the budgeted hours to complete the task by the budgeted labor rate.

C . Dividing the actual hours required to complete the task by the budgeted labor rate.

D . Cannot be determined.

E . None of the above


相似考题
参考答案和解析
正确答案:B
更多“The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:A . Multiplying the actual hours worked on the project by the budgeted labor rate.B . Multiplying the budgeted hours to complete the task by the bu”相关问题
  • 第1题:

    The planned cost for the total project at its inception is called the _____.

    A . Cost of goods sold.

    B . Depreciable value.

    C . Budgeted cost.

    D . All of the above.

    E . B and C only.


    正确答案:C

  • 第2题:

    An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:

    A . Higher salaried employees were assigned.

    B . Overtime was required.

    C . The overhead rate increased.

    D . Employee salaries had increased.

    E . Any of the above


    正确答案:E

  • 第3题:

    The cost of a quality program should be budgeted at _____ of the total project.

    A . 10-12%

    B . 2-3 %

    C . 6-8%

    D . 3-5%

    E . more than 15 %


    正确答案:D

  • 第4题:

    89 An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:

    A. Higher salaried employees were assigned.

    B. Overtime was required.

    C. The overhead rate increased.

    D. Employee salaries had increased.

    E. Any of the above


    正确答案:E

  • 第5题:

    146 The planned cost for the total project at its inception is called the _____.

    A. Cost of goods sold.

    B. Depreciable value.

    C. Budgeted cost.

    D. All of the above.

    E. B and C only


    正确答案:C

  • 第6题:

    23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

    A. Baseline costs

    B Budgeted costs.

    C. Estimates upon completion costs

    D. Scheduled costs

    E. None of the above


    正确答案:A

  • 第7题:

    105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

    A. Baseline costs

    B. Budgeted costs.

    C. Estimates upon completion costs

    D. Scheduled costs

    E. None of the above


    正确答案:A

  • 第8题:

    135 Using the cumulative cost curve in the special window, height B represents

    A. actual cost to date

    B. total budgeted costs for the project

    C. planned cost for month 6

    D. cost variance

    E. earned value


    正确答案:B

  • 第9题:

    ● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

    (74)

    A.Ahead of schedule

    B.Behind schedule

    C.On schedule

    D.Having not enough information provided


    正确答案:B

  • 第10题:

    ()is the Budgeted amount for the work actually completed on the schedule activity or WBS component during a given period。

    A.Planned value
    B.Actual cost
    C.Earned value
    D.Cost variance

    答案:C
    解析:
    翻译:
    ()是在一个既定的时间段内实际完所工作分解结构中的计划活动所对应的预算。
    A.计划值B.实际成本C.挣值D.成本变化

  • 第11题:

    ()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.

    • A、Plannedvalue
    • B、Earned value
    • C、Actualcost
    • D、Costvariance

    正确答案:B

  • 第12题:

    单选题
    ()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
    A

    Planned value

    B

    Earned value

    C

    Actual cost

    D

    Cost variance


    正确答案: A
    解析: 暂无解析

  • 第13题:

    The most common method for pricing out non-burdened labor hours for a three year project would be to:

    A . Price out the hours at the actual salary of the people to be assigned.

    B . Price out the work using a company-wide average labor rate.

    C . Price out the work using a functional group average labor rate.

    D . All of the above.

    E . A and B only.


    正确答案:C

  • 第14题:

    A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.

    A . Trend line.

    B . Trend analysis.

    C . S curve.

    D . Percent completion report.

    E . Earned value report.


    正确答案:C

  • 第15题:

    58 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.

    A. Trend line.

    B. Trend analysis.

    C. S curve.

    D. Percent completion report.

    E. Earned value report


    正确答案:C

  • 第16题:

    100 The most common method for pricing out non-burdened labor hours for a three year project would be to:

    A. Price out the hours at the actual salary of the people to be assigned.

    B. Price out the work using a company-wide average labor rate.

    C. Price out the work using a functional group average labor rate.

    D. All of the above.

    E. A and B only


    正确答案:C

  • 第17题:

    159 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:

    A. Multiplying the actual hours worked on the project by the budgeted labor rate.

    B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.

    C. Dividing the actual hours required to complete the task by the budgeted labor rate.

    D. Cannot be determined.

    E. None of the above


    正确答案:B

  • 第18题:

    110 The cost of a quality program should be budgeted at _____ of the total project.

    A. 10-12%

    B. 2-3 %

    C. 6-8%

    D. 3-5%

    E. more than 15 %


    正确答案:D

  • 第19题:

    ()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.

    A.Plannedvalue

    B.Earned value

    C.Actualcost

    D.Costvariance


    参考答案:B

    该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。

  • 第20题:

    is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

    A.Planned value

    B.Earned value

    C.Actual cost

    D.Cost variance


    正确答案:B
    解析:挣值是在给定时期内按进度活动或WBS部件所完成工作的预算值。

  • 第21题:

    The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).

    A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index


    正确答案:A

  • 第22题:

    The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ).

    A.Cost Variance
    B.Schedule Variance
    C.EarneD.Value
    D.Cost PerformeD.Index

    答案:A
    解析:
    BCWP与ACWP之间的差值是 。

    A.成本偏差 B.进度偏差 C.挣值 D. 成本绩效

  • 第23题:

    ()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

    • A、Planned value
    • B、Earned value
    • C、Actual cost
    • D、Cost variance

    正确答案:C