The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
A . Multiplying the actual hours worked on the project by the budgeted labor rate.
B . Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C . Dividing the actual hours required to complete the task by the budgeted labor rate.
D . Cannot be determined.
E . None of the above
第1题:
The planned cost for the total project at its inception is called the _____.
A . Cost of goods sold.
B . Depreciable value.
C . Budgeted cost.
D . All of the above.
E . B and C only.
第2题:
An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:
A . Higher salaried employees were assigned.
B . Overtime was required.
C . The overhead rate increased.
D . Employee salaries had increased.
E . Any of the above
第3题:
The cost of a quality program should be budgeted at _____ of the total project.
A . 10-12%
B . 2-3 %
C . 6-8%
D . 3-5%
E . more than 15 %
第4题:
89 An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:
A. Higher salaried employees were assigned.
B. Overtime was required.
C. The overhead rate increased.
D. Employee salaries had increased.
E. Any of the above
第5题:
146 The planned cost for the total project at its inception is called the _____.
A. Cost of goods sold.
B. Depreciable value.
C. Budgeted cost.
D. All of the above.
E. B and C only
第6题:
23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A. Baseline costs
B Budgeted costs.
C. Estimates upon completion costs
D. Scheduled costs
E. None of the above
第7题:
105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A. Baseline costs
B. Budgeted costs.
C. Estimates upon completion costs
D. Scheduled costs
E. None of the above
第8题:
135 Using the cumulative cost curve in the special window, height B represents
A. actual cost to date
B. total budgeted costs for the project
C. planned cost for month 6
D. cost variance
E. earned value
第9题:
● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .
(74)
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
第10题:
第11题:
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
第12题:
Planned value
Earned value
Actual cost
Cost variance
第13题:
The most common method for pricing out non-burdened labor hours for a three year project would be to:
A . Price out the hours at the actual salary of the people to be assigned.
B . Price out the work using a company-wide average labor rate.
C . Price out the work using a functional group average labor rate.
D . All of the above.
E . A and B only.
第14题:
A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.
A . Trend line.
B . Trend analysis.
C . S curve.
D . Percent completion report.
E . Earned value report.
第15题:
58 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.
A. Trend line.
B. Trend analysis.
C. S curve.
D. Percent completion report.
E. Earned value report
第16题:
100 The most common method for pricing out non-burdened labor hours for a three year project would be to:
A. Price out the hours at the actual salary of the people to be assigned.
B. Price out the work using a company-wide average labor rate.
C. Price out the work using a functional group average labor rate.
D. All of the above.
E. A and B only
第17题:
159 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
A. Multiplying the actual hours worked on the project by the budgeted labor rate.
B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C. Dividing the actual hours required to complete the task by the budgeted labor rate.
D. Cannot be determined.
E. None of the above
第18题:
110 The cost of a quality program should be budgeted at _____ of the total project.
A. 10-12%
B. 2-3 %
C. 6-8%
D. 3-5%
E. more than 15 %
第19题:
A.Plannedvalue
B.Earned value
C.Actualcost
D.Costvariance
该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。
第20题:
is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
第21题:
The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).
A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index
第22题:
第23题:
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.