更多“149 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. ConceptualB. Development.C. ExecutionD. FinishE. All of the above”相关问题
  • 第1题:

    Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?

    A concept

    B development

    C execution

    D conclusion

    E All of the above.


    正确答案:A

  • 第2题:

    92 The highest degrees of project risk and uncertainty are associated with the following phase of the project:

    A. conceptual

    B. execution

    C. cut-over

    'D. post project evaluation

    E. A and D only


    正确答案:A

  • 第3题:

    62 Make or buy decisions are usually made during the _____ phase of a project.

    A. Conceptual

    B. Development.

    C. Implementation

    D. Execution

    E. Close-out


    正确答案:B

  • 第4题:

    70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. concept

    B. development

    C. execution

    D. conclusion

    E. All of the above


    正确答案:A

  • 第5题:

    154 A Work Breakdown Structure:

    A. assures all work is identified

    B. subdivides the project into manageable segments

    C. provides the project sponsor with a time-phase task summary

    D. both A and B

    E. All of the above


    正确答案:D

  • 第6题:

    6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第7题:

    88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B. Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第8题:

    86 A work breakdown structure:

    A. assures all work is identified.

    B. subdivides the project into manageable segments.

    C. provides the project sponsor with a time-phase task summary.

    D. both A and B.

    E. All of the above


    正确答案:D

  • 第9题:

    174 The highest degrees of project risk and uncertainty are associated with the following phase of the project:

    A. conceptual

    B. execution

    C. cut-over

    D. post project evaluation

    E. A and D only


    正确答案:A

  • 第10题:

    ● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.

    A Conceptual

    B Development.

    C Execution

    D Finish

    E All of the above.


    正确答案:E

  • 第11题:

    () are individuals and organizations that are actively involved in the project, orwhose interests may be affected as a result of project execution or project completion; they mayalso exert influence over the project and its results.

    A.Controls
    B.Baselines
    C.Project stakeholders
    D.Project managers

    答案:C
    解析:
    项目干系人是积极参与到项目中,或其利益可能会受到项目执行或完成结果影响的个人或组织,他们可能会对项目及其结果施加影响。

  • 第12题:

    单选题
    () are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
    A

    Project managers

    B

    Project team members

    C

    Sponsors

    D

    Project stakeholders


    正确答案: D
    解析: 暂无解析

  • 第13题:

    79 Time management is the allocation of time in a project's life cycle through the process of:

    A. Planning

    B. Estimating.

    C. Scheduling.

    D. Controlling

    E. All of the above.


    正确答案:E

  • 第14题:

    101 The lowest dollar amount 'at stake' is associated with the following phase of the project: A. conceptual

    B. execution

    C. cut-over

    D. post project evaluation

    E. A and D only


    正确答案:A

  • 第15题:

    67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. Conceptual

    B. Development.

    C. Execution

    D. Finish

    E. All of the above


    正确答案:E

  • 第16题:

    141 Feasibility studies occur in which life cycle phase (s)?

    A. Conceptual

    B. Conceptual or Development

    C. Execution

    D. Preliminary planning

    E. any life cycle phase


    正确答案:A

  • 第17题:

    194 During which phase of the project life cycle is the amount at stake lowest?

    A. concept

    B. development

    C. execution

    D. conclusion

    E. C and D


    正确答案:A

  • 第18题:

    185 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above


    正确答案:A

  • 第19题:

    83 Budgetary estimates are the output of the _____ phase(s) of the project.

    A. conceptual

    B. development

    C. implementation

    D. finish

    E. All of the above


    正确答案:B

  • 第20题:

    161 Time management is the allocation of time in a project's life cycle through the process of: A. Planning

    B. Estimating.

    C. Scheduling.

    D. Controlling

    E. All of the above


    正确答案:E

  • 第21题:

    ● A Work Breakdown Structure:

    A assures all work is identified

    B subdivides the project into manageable segments

    C provides the project sponsor with a time-phase task summary

    D both A and B

    E All of the above.


    正确答案:D

  • 第22题:

    are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.

    A.Project manager

    B.Project team member

    C.Sponsor

    D.Proiect stakeholders


    正确答案:D
    解析:项目干系人是指那些积极参与项目或是其利益会受到项目执行或完成的结果影响的个人和组织。

  • 第23题:

    () are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

    • A、Project managers
    • B、Project team members
    • C、Sponsors
    • D、Project stakeholders

    正确答案:B