  • 第1题:

    Project team building is most difficult in which type of environment?

    A . weak matrix organization

    B . strong matrix organization

    C . projectized organization

    D . functional organization

    E . expediter organization


    正确答案:A

  • 第2题:

    Which of the following organizational forms would be likely to have an individual with the title of Vice President for Project Management?

    A . Classical / traditional

    B . Pure project

    C . Matrix

    D . Project coordinator

    E . None of the above


    正确答案:C

  • 第3题:

    In a matrix organizational form, MBO may be difficult to implement:

    A . If the functional employees are supervised closely by the line manager rather than the project manager

    B . Unless the project manager has an input into the employee's performance review

    C . Unless the project and line managers agree on the ultimate objective

    D . Unless the project and line managers agree to the duration of the task

    E . None of the above are correct answers


    正确答案:E

  • 第4题:

    43 Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?

    A. Project.

    B. Strong matrix.

    C. Weak matrix.

    D. Project coordinator.

    E. Project expeditor.


    正确答案:C

  • 第5题:

    174 In a matrix organizational form, MBO may be difficult to implement:

    A. If the functional employees are supervised closely by the line manager rather than the project manager

    B. Unless the project manager has an input into the employee's performance review C. Unless the project and line managers agree on the ultimate objective

    D. Unless the project and line managers agree to the duration of the task

    E. None of the above are correct answers


    正确答案:E

  • 第6题:

    80 What tool have project managers come to use to identify all of the costs associated with a project.

    A. A bill of materials

    B. A Gantt chart

    C. An arrow diagram network.

    D. A work breakdown structure.

    E. B and C only


    正确答案:D

  • 第7题:

    55 Project team building is most difficult in which type of environment?

    A. weak matrix organization

    B. strong matrix organization

    C. projectized organization

    D. functional organization

    E. expediter organization


    正确答案:A

  • 第8题:

    ● The project charter:

    A Expresses upper management commitment to the project.

    B Provides that authority by which the project will be run.

    C Establishes that organizational structure with the project.

    D Specifies overall objectives and timeframe. of the project.

    E All of the above.


    正确答案:E

  • 第9题:

    ● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

    A The project manager and project office personnel.

    B The project team and functional managers.

    C The project sponsor.

    D All of the above.

    E A and B only.


    正确答案:E

  • 第10题:

    A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

    A.Structure Chart

    B.Organizational Structure

    C.Work Breakdown Structure

    D.Functional decomposition diagram


    正确答案:C

  • 第11题:

    A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

    A.Functional decomposition diagram
    B.Work Breakdown Structure
    C.Structure Chart
    D.Organizational Structure

    答案:B
    解析:

  • 第12题:

    () are individuals and organizations that are actively involved in the project, orwhose interests may be affected as a result of project execution or project completion; they mayalso exert influence over the project and its results.

    A.Controls
    B.Baselines
    C.Project stakeholders
    D.Project managers

    答案:C
    解析:
    项目干系人是积极参与到项目中,或其利益可能会受到项目执行或完成结果影响的个人或组织,他们可能会对项目及其结果施加影响。

  • 第13题:

    The strong matrix versus a weak matrix.

    A . team members are more likely to be assigned to the project office in a strong matrix

    B . strong matrix is more difficult to manage.

    C . the balance of power has shifted away from the PM.

    D . functional managers no longer has control over the technical processes.

    E . All of the above.


    正确答案:A

  • 第14题:

    Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .

    A . Project managers; team members

    B . Company management philosophy in treating employees; the average worker

    C . Project sponsors; project managers

    D . The functional team; project sponsors

    E . Recruitment policy; wage and salary administration


    正确答案:B

  • 第15题:

    The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work?

    A . Matrix

    B . Classical

    C . Expediter

    D . Coordinator

    E . Pure project


    正确答案:E

  • 第16题:

    160 The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work? A. Matrix

    B. Classical

    C. Expediter

    D. Coordinator

    E. Pure project


    正确答案:E

  • 第17题:

    198 What tool have project managers come to use to identify all of the costs associated with a project. A. A bill of materials

    B. A Gantt chart

    C. An arrow diagram network.

    D. A work breakdown structure.

    E. B and C only


    正确答案:D

  • 第18题:

    125 Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?

    A. Project.

    B. Strong matrix.

    C. Weak matrix.

    D. Project coordinator.

    E. Project expeditor


    正确答案:C

  • 第19题:

    ● The scope baseline/project charter is prepared by the:

    A Project manager

    B Project manager and project office

    C Project manager, project office and functional team

    D Project manager, project office, functional team and project sponsor

    E Project manager, project sponsor and customer/user


    正确答案:E

  • 第20题:

    A An organization oriented family tree of the project.

    B A task oriented family tree of the project.

    C A cost centered structure of the project.

    D Only required on large complex projects where separately identifiable work packages are difficult to construct.

    E None of the above.


    正确答案:B

  • 第21题:

    are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

    A.Controls

    B.Baselines

    C.Project stakeholders

    D.Project managers


    正确答案:C
    解析:项目干系人是积极参与到项目中,或其利益可能会受项目执行或完成结果影响的个人或组织:他们可能会对项目及其结果施加影响。

  • 第22题:

    - Would you please let me know something more about the project -()

    A、OK, I have divided my report into three parts, the first part is an overview of the project.

    B、OK, the project is perfect.

    C、No, the project isn’t so good.


    参考答案:A

  • 第23题:

    During the implementation of the project,the user's environment(business environment,organizational structure,etc.)may change,and the demand for the project may also change.For the changing needs of the project scope,()is the person with real approval power.

    A.user
    B.project manager
    C.CCB
    D.Project investor

    答案:D
    解析:
    解析:翻译:在项目实施过程中,用户的环境(业务环境、组织架构等)可能会发生变化,对项目的需求可能也会发生变化。针对项目范围变化的需求,( )是真正具备批准权力的人。A.用户B.项目经理C.变更控制委员会(CCB)D.项目投资人
    很多时候,项目经理会面对来自客户等项目干系人一系列变化要求。由于这些人都属于客户范围,所以他们的要求通常都被认为是应当被接受的。实际上这是一种错误认识。客户通常只能提出范围变化的要求,但却没有批准的权力。即使是项目经理也没有批准的权力。真正拥有批准权力的只有一个人,那就是这个项目的投资人(除非该资助人已经授权给了他人)。