● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(73)A. work performance informationB. s

题目

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

(73)

A. work performance information

B. scope statement

C. change requests

D. process analysis


相似考题
更多“● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(73)A. work performance informationB. s”相关问题
  • 第1题:

    ● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .

    (73) A. change the scope baseline

    B. contact the customer to determine if the change adds value

    C. call a meeting of the change control board

    D. change the project' s objectives


    正确答案:B

  • 第2题:

    ● (72)describes, in detail, the project’s deliverables and the work required to create those deliverables.

    (72)

    A. Product scope description

    B. Project objectives

    C. Stakeholder Analysis

    D. The project scope statement


    正确答案:D

  • 第3题:

    ( ) describes, in detail, the project’ s deliverables and the work required to create those deliverables.

    A.Product scope description B.Project objectives C.Product specification D.The project scope statement


    正确答案:D

  • 第4题:

    A project management technique that is currently in widespread use is the(71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called(72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide(73), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management.(74) was developed to make clear the interdependence between project tasks before those tasks are scheduled.(75) offers the advantage of clearly showing overlapping tasks.

    A.Structure Chart

    B.Organizational Structure

    C.Work Breakdown Structure

    D.Functional decomposition diagram


    正确答案:C

  • 第5题:

    ●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).

    (73)A. project management plan

    B. project baseline

    C. risk response plan

    D. risk baseline


    正确答案:A

  • 第6题:

    The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A、project scope statement

    B、work package

    C、WBS

    D、project scope plan


    参考答案:C

  • 第7题:

    The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . ……

    A.Monitoring

    B.Managing

    C.Gathering

    D.Reducing


    正确答案:B
    解析:在项目的生命周期里,项目通过如下措施维持一个最新的、经批准的需求集合:
      . 管理对需求的变更。
      . 维持需求、项目计划和工作产品之间的关联。
      . ……

  • 第8题:

    Managing risk and documenting them is very important in project planning process.You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the(73) .

    A.project management plan
    B.project baseline
    C.riskresponse plan
    D.risk baseline

    答案:A
    解析:
    风险管理和记录它们是非常重要的在项目规划过程。在过程定义关键风险中,包括约束和假设,应对计划和对突发事件的处理。这些细节将被包含在项目管理计划中。

  • 第9题:

    ( )in not inc1uded in Control Quality input documents.

    A.Project management plan
    B.Project documents
    C.Quality problems report
    D.Work performance data

    答案:C
    解析:
    质量控制的输入文件不包括:质量问题报告

  • 第10题:

    The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A.Project scope statement
    B.Work package
    C.WBS
    D.Project scope plan

    答案:C
    解析:
    ()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
    A.项目范围说明书B.工作包C.WBS?D.项目范围计划

  • 第11题:

    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    • A、Product scope description
    • B、Project objectives
    • C、Stakeholder Analysis
    • D、The project scope statement

    正确答案:D

  • 第12题:

    单选题
    The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
    A

    work performance information

    B

    scope statement

    C

    changerequests

    D

    process analysis


    正确答案: C
    解析: 该题的关键词为"major project deliverables、the project objectives",其语句结构为"The project (主语)is(谓语)akey input to quality planning(表语)since it documentsmaj or proj ect deliverables,the project objectives(原因状语从句)",含义为"项目的什么是质量计划的一个关键输入,因为它记录了主要的项目交付物和项目目标",容易判断出应该为项目范围说明书的作用,应该选择选项B。

  • 第13题:

    ●To ensure the project team provides the functionality the customerexpects in a new piece of software, the project manager ask the customer forsign-off on the design criteria. These documents are(75).

    (75) A. technical specifications

    B. performance specifications

    C. product descriptions

    D. quality assurance


    正确答案:A

  • 第14题:

    ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

    (73)

    A.executive IT manager

    B.project manger

    C.change control board

    D.project sponsor


    正确答案:C
    试题(73)分析
     项目变更可以由IT经理executive IT manager、项目管理者project manager、项目发起人project sponsor等任意项目干系人发起,但只有变更控制委员会change control board授权通过,所以选C。
    参考答案
    (73)C

  • 第15题:

    The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B

  • 第16题:

    ______describes,in detail,the project's deliverables and the work required to create those deliverables.

    A.Product scope description

    B.Project objectives

    C.Stakeholder Analysis

    D.The project scope statement


    正确答案:D
    解析:项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。
    选项A是产品范围说明书,选项B是项目目标,选项C是干系人分析,选项D是项目范围说明书。故D是正确的。

  • 第17题:

    The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B
    解析:项目范围说明书是制订质量计划的—项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

  • 第18题:

    A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements list

    A.Essences

    B.Elements

    C.Purposes

    D. Issues


    正确答案:B
    本题目翻译:进度表是常用的项目规划和项目组合管理。按计划元素可能是密切相关的工作分解结构(WBS)的终端元素,工作的陈述,或合同数据要求清单。考察的是进度计划。

  • 第19题:

    The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    A.project scope statement
    B.project requirement
    C.project charter
    D.product specification

    答案:A
    解析:
    项目范围说明书详细描述了项目的可交付物以及为创建这些可交付物所需的工作。
    A.项目范围说明书B.项目需求C.项目章程 D.产品规范

  • 第20题:

    ( )is not included in Control Quality input documents.

    A.Project management plan
    B.Project documents
    C.Quality problems report
    D.Work performance data

    答案:C
    解析:
    质量控制的输入文件不包括:质量问题报告。

  • 第21题:

    ( ) describes,in detail,the project’s deliverables and the work required to create those deliverables.

    A.Product scope description
    B.Project objectives
    C.Stakeholder Analysis
    D.The project scope statement

    答案:D
    解析:
    项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。(72) A.产品范围说明书 B.项目目标 C.干系人分析 D.项目范围说明说

  • 第22题:

    The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

    • A、work performance information
    • B、scope statement
    • C、changerequests
    • D、process analysis

    正确答案:B

  • 第23题:

    The () describes, in detail, the project's deliverables and the work required to create those deliverables.

    • A、project scope statement
    • B、project requirement
    • C、project charter
    • D、product specification

    正确答案:A