On a voyage charter party when the vessel is in port the charter will specify a definite period of time for loading or discharging of cargo by the Charterer.This time is called ________ .A.DemurrageB.DispatchC.Days of readinessD.Laydays

题目

On a voyage charter party when the vessel is in port the charter will specify a definite period of time for loading or discharging of cargo by the Charterer.This time is called ________ .

A.Demurrage

B.Dispatch

C.Days of readiness

D.Laydays


相似考题
更多“On a voyage charter party when the vessel is in port the charter will specify a definite p ”相关问题
  • 第1题:

    As in the case of a voyage charter-party,it is implied in the bill of lading that the voyage must be prosecuted with ______.

    A.operational custom

    B.rational practice

    C.due diligence

    D.reasonable despatch


    正确答案:D

  • 第2题:

    ______ is not a type of charter-party.

    A.A voyage charter-party

    B.A time charter-party

    C.A charter-party by demise

    D.The charter of the United Nations


    正确答案:D

  • 第3题:

    A vessel has a charter party for one voyage to carry a full load of manganese from Durban,South Africa,to Baltimore,Maryland,at a stipulated rate per ton. Which type of contract is involved? ______.

    A.Bareboat charter party

    B.Voyage charter party

    C.Demise charter party

    D.Time charter party


    正确答案:B

  • 第4题:

    The owners of the S.S. Short Haul agree to a charter with the Longsplice Steamship Company. The owners stipulate in the charter party that the regular Master must be employed as the vessel's Master for the entire life of the contract. Which charter has be

    A.Bareboat

    B.Lease

    C.Time

    D.Voyage


    正确答案:C

  • 第5题:

    翻译:bareboat charter or demise charter party


    正确答案:光船租赁

  • 第6题:

    单选题
    A Contract of Affreightment covering the movement of a particular cargo from one designated port to another at a specified rate for each ton of goods loaded is called a().
    A

    bareboat charter party

    B

    demise charter party

    C

    time charter party

    D

    voyage charter party


    正确答案: B
    解析: 暂无解析

  • 第7题:

    单选题
    As in the case of a voyage charter-party,it is implied in all bills of lading that()will be made from the contractual route unless such deviation is justified.
    A

    deviation

    B

    no deviation

    C

    navigation

    D

    no navigation


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    On a voyage charter,when a vessel is ready to load cargo,the Master should render to the charterer a().
    A

    Notice of Readiness

    B

    Master Certificate of Service

    C

    Shipmasters Declaration

    D

    Vessel Utilization and Performance Report


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    Sometimes the charter-party()that the vessel must only use safe ports within a certain area.
    A

    improves

    B

    installs

    C

    contains

    D

    requests


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    Where a charter-party specifies the estimated time of arrival of a vessel at the port of loading,there is()obligation on the shipowners to sail to there on the date on which when proceeding with all convenient speed it would normally reach the port on or about the estimated date of arrival.
    A

    an optional

    B

    a reasonable

    C

    an absolute

    D

    rational


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    The owners of the S.S. Short Haul agree to a charter with the Longsplice Steamship Company. The owners stipulate in the charter party that the regular Master must be employed as the vessel’s Master for the entire life of the contract. Which charter has be ().
    A

    Bareboat

    B

    Lease

    C

    Time

    D

    Voyage


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    ()is not a type of charter-party.
    A

    A voyage charter-party

    B

    A time charter-party

    C

    A charter-party by demise

    D

    The charter of the United Nations


    正确答案: A
    解析: 暂无解析

  • 第13题:

    ______ is a charter form,in which the bare ship is chartered without crew and Charterer takes over the vessel with a minimum of restrictions.

    A.Time Charter

    B.Trip Charter

    C.Demise Charter

    D.Voyage Charter


    正确答案:C

  • 第14题:

    A Contract of Affreightment covering the movement of a particular cargo from one designated port to another at a specified rate for each ton of goods loaded is called a ______.

    A.bareboat charter party

    B.demise charter party

    C.time charter party

    D.voyage charter party


    正确答案:D

  • 第15题:

    As in the case of a voyage charter-party,it is implied in all bills of lading that ______ will be made from the contractual route unless such deviation is justified.

    A.deviation

    B.no deviation

    C.navigation

    D.no navigation


    正确答案:B

  • 第16题:

    The S.S. Microwave has been chartered to the Longline Steamship Company. The Longline Steamship Company agrees to pay all expenses and employ and pay the crew. Which type of contract is involved? ______.

    A.Bareboat Charter Party

    B.Lease Charter Party

    C.Time Charter Party

    D.Voyage Charter Party


    正确答案:A

  • 第17题:

    In marine voyage chartering, the following()terms are normally appeared in the voyage charter party.

    • A、freight payment
    • B、hire payment
    • C、lay-time
    • D、demurrage

    正确答案:A,D

  • 第18题:

    单选题
    It is an()condition precedent in every voyage charter-party that the ship shall proceed on the voyage without departure from her proper course.
    A

    implemented

    B

    implied

    C

    impossible

    D

    improper


    正确答案: B
    解析: 暂无解析

  • 第19题:

    单选题
    A vessel has a charter party for one voyage to carry a full load of manganese from Durban,South Africa,to Baltimore,Maryland,at a stipulated rate per ton. Which type of contract is involved? ()
    A

    Bareboat charter party

    B

    Voyage charter party

    C

    Demise charter party

    D

    Time charter party


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    Where a time charter-party is wrongfully(),the Charterer is entitled to claim damages amounting the difference between the contract rate for the balance of the period of the charter-party and the market rate for the chartering a substitute vessel.
    A

    reproduced

    B

    repatriated

    C

    repudiated

    D

    recovered


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A charterer is unable to complete the loading of a vessel during the lay days specified in the charter party. Under these circumstances,the().
    A

    vessel operator can collect demurrage

    B

    ship is authorized extra time to discharge the cargo

    C

    charterer must pay dispatch money

    D

    effective period of the charter is extended


    正确答案: A
    解析: 暂无解析

  • 第22题:

    单选题
    The S.S. Hollowpoint has a charter party in which the charterer assumes no responsibility for the operation of the vessel but pays stevedoring expenses. What is the name of the charter party? ().
    A

    Bareboat

    B

    Dispatch

    C

    Voyage

    D

    Demise


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    A clause in the charter party requires a vessel’s owner to pay dispatch money when the vessel ().
    A

    changes berths to expedite loading or discharging

    B

    does not load and discharge its cargo in the time specified

    C

    is not ready to load or discharge cargo

    D

    loads and discharges its cargo in less time than specified


    正确答案: C