Double the number of processors.
Double the number of memory DIMMs.
Double the number of network adapters.
Double the number of SCSI buses and disks.
第1题:
Due to slow response times, a customer purchased additional memory. After the memory was installed,response time was not improved. They complained to the pSeries technical specialist. Which of the following questions should be asked of this customer?()
第2题:
The system administrator has been getting complaints about slow performance from the server. After running vmstat the administrator notices average readings that show the free list (fre) approaching zero, as well as page-in (pi) and page-out (po) values to be high. Furthermore, the applications running are essential to daily business operations. Which of the following recommendations would provide the best overall improvement?()
第3题:
A company needs additional storage for a block I/O based database application. The application has low I/O bandwidth requirements across the campus. The customer has a TCP/IP infrastructure and is interested in low-cost products that are compatible with its environment. Which technology is most appropriate for this customer?()
第4题:
A customer has been working with your company to purchase an iDataPlex cluster. They have a configuration from IBM and are getting ready to place an order. Which should be done of the following?()
第5题:
A customer has a new p5-550 running AIX 5.2 that is SAN-attached to a FAStT900. They have encountered hangs lasting over a minute on their new system during application load testing. They called the pSeries technical specialist for advice. Which of the following would be the most appropriate questions to determine their next step in resolving the problem?()
第6题:
Increase the undo return
Create more undo segments
Create another undotablespace
Increase the size of the undotablespace
第7题:
increase the undo retention
create more undo segments
create another undo tablespace
increase the size of the undo tablespace
第8题:
Sales Manual
Announcement Letter
POWER4+ p650 Specification Sheet
Site and Hardware Planning Information Manual
第9题:
Voltage
Frequency
Power Source Loading (max)
Power Source Loading (typical)
第10题:
SAN
FCoE
FCIP
iSCSI
第11题:
/smit.log
/smit.script
/var/log/smit.log
/.history
第12题:
Enable SMT
Reduce the weight
Renice the process
Increase the weight
第13题:
A System p administrator needs to document system changes that have occurred recently. The company has a policy of making all possible changes via the smit interface. Which of the following files would show the commands that have been performed from within smit and their resulting output()
第14题:
An SNMP alert has been generated by a server in the main data center.The alert stated that the internal temperature of the server has exceeded the threshold.No other servers in the rack have experienced problems,and no other alerts have come from that server about any other events.Which of the following is the cause of this issue?()
第15题:
An IBM Business Partner has sold a DS5020 and new IBM SAN switches to replace a customer EMC storage infrastructure. The customer dissatisfaction has arisen during the installation because according to the DS5020 interoperability matrix, two HP Proliant servers running Exchange have FC HBAs that are not supported. Which of the following is the most probable cause of the customer dissatisfaction()
第16题:
Companycom has just installed a p5 595 with four uncapped LPARs in a shared processor pool. The system and profile settings are still in their default states. One of the LPARs has an application that is consuming all of the available shared processor resources. Users of this application are complaining about response time. Which of the following changes to the slow LPAR would improve response time?()
第17题:
A customer has a large amount of data stored on three database servers and is concerned that at present there is no disaster recovery plan in place. They have an existing tape backup solution that meets their backup window. In order to analyze potential disaster recovery plans, which of the following questions is the most important?()
第18题:
Who recommended the memory purchase?
Have more users been added since the memory purchase?
Why were additional CPUs not ordered at the same time as the memory?
Did a performance analysis of peak periods show a memory bottleneck?
第19题:
Disk Magic
TPC for Data
CLARiiON Procedure Generator
System Storage Interoperability Center
第20题:
Double the number of processors.
Double the number of memory DIMMs.
Double the number of network adapters.
Double the number of SCSI buses and disks.
第21题:
Increase physical disk
Increase number of CPU’s
Increase physical memory
Increase number of servers
第22题:
netstat
ping
nslookup
grep
第23题:
A solution sizing questionnaire
Verify the customer has the proper racks
A Technical Delivery Assessment
Verify the customer has enough cooling in the computer room
第24题:
Rack cooling equipment failure
Dust collection in the server
Server processor failure
Server power supply failure