Until security has been provided the Contractor shall have a maritime lien on ______ for his remuneration.A.the property lostB.the property salvedC.the property involved in the accident which gave rise to the salvage operationsD.any other property in dang

题目

Until security has been provided the Contractor shall have a maritime lien on ______ for his remuneration.

A.the property lost

B.the property salved

C.the property involved in the accident which gave rise to the salvage operations

D.any other property in danger which is not and has not been on board the vessel


相似考题
参考答案和解析
正确答案:B
更多“Until security has been provided the Contractor shall have a maritime lien on ______ for h ”相关问题
  • 第1题:

    I ( ) by the teacher at the meeting next week.

    A、am praised

    B、have been praised

    C、shall praised

    D、shall be praised


    参考答案:D

  • 第2题:

    All samples shall be supplied by the Contractor at his own cost if the supply ()is clearly intended by or provided for in the Contract.

    A、at

    B、 thereof

    C、 by

    D、 for


    参考答案:B

  • 第3题:

    The master of a ship must collect general average contributions for the benefit of those entitled to them,whether they are cargo owners or ship owner,and ______ the Shipowner's lien on the cargo,where necessary,until they are paid.

    A.exercise

    B.take

    C.make

    D.have


    正确答案:A

  • 第4题:

    In accordance with GENCON,Owners shall have a lien on ______ for detention.

    A.the cargo for freight,dead-freight,demurrage and damages

    B.dispatch money

    C.premium if paid

    D.total and/or partial loss of and/or damage to the vessel


    正确答案:A

  • 第5题:

    材料:

    The Salvor shall immediately after the termination of the services or sooner notify the Council and where practicable the Owners of the amount for which he demands security(inclusive of costs expenses and interest)from each of the respective Owners.Where the exception to the principle of no cure-no pay under Convention Article 14 becomes likely to be applicable the owners of the vessel shall on the demand of the Salvor provide security for the Salvor&39;s special compensation.The amount of any such security shall be reasonable in the light of the knowledge available to the Salvor at the time when the demand is made.

    Unless otherwise agreed such security shall be provided(i)to the Council(ii)in a form. approved by the Council and(iii)by persons firms or corporations either acceptable to the Salvor or resident in China and acceptable to the Council.The Council shall not be responsible for the sufficiency(whether in amount or otherwise)of any security which shall be provided nor for the default or insolvency of any person firm or corporation providing the same.The owners of the vessel their Servants and Agents shall use their best endeavours to ensure that the cargo owners provide their proportion of security before the cargo is released.

    Until security has been provided as aforesaid the Salvor shall have a maritime lien on the property salved for his remuneration.

    问题:

    The amount of security provided by owners shall be _______.

    A.as small as practicable to ensure not to affect the normal business of the owners

    B.sufficient to cover all costs expenses and interest the salvor had sustained in the process of or in connection with the savage operations

    C.actual costs expenses and interest incurred to the salvor calculable immediately after the termination of the services

    D.reasonable in the light of the knowledge available to the Salvor at the time when the demand is made

    Where the principle of no cure-no pay is likely not to be applicable the owners of the vessel _______.A.is exempted from providing any security for the Salvor's special compensation

    B.shall not provide any security for the Salvor's special compensation unless otherwise provided in the salvage contract

    C.shall not provide any security for the Salvor's special compensation even the Salvor so demands

    D.shall on the demand of the Salvor provide security for the Salvor's special compensation

    The Council to which the security has been provided shall _______.A.be responsible for its sufficiency(whether in amount or otherwise)

    B.be responsible for the default or insolvency of any person firm or corporation providing the same

    C.be responsible for its sufficiency(whether in amount or otherwise)but not for the default or insolvency of any person firm or corporation providing the same

    D.be responsible neither for its sufficiency(whether in amount or otherwise)nor for the default or insolvency of any person firm or corporation providing the same

    请帮忙给出每个问题的正确答案和分析,谢谢!


    问题 1 答案解析:D


    问题 2 答案解析:D


    问题 3 答案解析:D

  • 第6题:

    All that can be done.

    A.have been done
    B.have done
    C.has been done
    D.has done

    答案:C
    解析:

  • 第7题:

    翻译:If the freight, contribution in general average demurrage to be paid to the carrier and other necessary charges paid by the carrier on behalf of the owner of the goods as well as other charges to be paid to the carrie have not been paid in full nor has appropriate security been given the carrier may have a lien to a reasonable extent on the goods.


    正确答案: 应当向承运人支付的运费、共同海损分摊、滞期费和承运人为货物垫付的必要费用以及应当向承运人支付的其他费用没有付清,又没有提供适当担保的,承运人可以在合理的限度内留置其货物。

  • 第8题:

    So far the construction of the two new bridges over the river ().

    • A、have  been  completed
    • B、has  been  completed
    • C、has  completed
    • D、have  completed

    正确答案:B

  • 第9题:

    单选题
    What is indicated about delivery in the Scarborough area?
    A

    Only local residents are eligible for it.

    B

    It will be provided at no cost.

    C

    The company has never charged for it.

    D

    Rates have been cut by half.


    正确答案: A
    解析:
    广告倒数第三句“…we're waiving delivery costs on all orders in the Scarborough area”提到免费外送,所以B正确。

  • 第10题:

    单选题
    Owner shall have a lien on the cargo for freight,dead-freight,demurrage and damages for detention.It means that().
    A

    Owner will not deliver the cargo if freight not paid

    B

    Owner will keep the dead-freight until the cargo has been delivered

    C

    Owner will keep the demurrage as soon as the cargo be delivered

    D

    Owner shall have no right of detention for the damaged cargo to be delivered


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    PLEASE BE ADVISED THE CAPTIONED VESSEL PROVISIONS SUPPLY HAS BEEN DULY ARRANGED AND SHIP CHANDLER WILL GO ON BOARD YR GOOD SHIP TO ATTEND TO THIS AFTER BERTHING. This telex says that ().
    A

    the provisions have been provided on board

    B

    the provisions will be delivered to you

    C

    the shipchandler will go on board your vessel for details

    D

    the provisions have not yet been arranged


    正确答案: C
    解析: 暂无解析

  • 第12题:

    单选题
    Good title to the Goods delivered to the ship shall not pass to the()until full payment for same has been made.
    A

    Vendor

    B

    Purchaser

    C

    Master

    D

    Shipper


    正确答案: B
    解析: 暂无解析

  • 第13题:

    Even though there has been a () with child prodigies for centuries, there has been little serious study of them until recently.

    A.facility

    B.fascination

    C.faculty

    D.assassination


    正确答案:B
    解析:句子的意思是:尽管几百年来人们一直对神童们很________,认真的研究他们只是近来的事情。Facility, 容易,便捷;(facilities)设施,装备,机构;fascination, 迷恋,神魂颠倒;faculty, (大学)教职员;assassination, 暗杀。

  • 第14题:

    The sharp hearing of a fish _______ by two scientists.

    A.have been proved

    B.have proved

    C.has proved

    D.has been proved


    正确答案:D

  • 第15题:

    Owner shall have a lien on the cargo for freight,dead-freight,demurrage and damages for detention.It means that ______.

    A.Owner will not deliver the cargo if freight not paid

    B.Owner will keep the dead-freight until the cargo has been delivered

    C.Owner will keep the demurrage as soon as the cargo be delivered

    D.Owner shall have no right of detention for the damaged cargo to be delivered


    正确答案:A

  • 第16题:

    If at any time the officer in charge of the navigational watch is to be relieved when a manoeuvre or other action to avoid any hazard is taking place,______.

    A.the relief of that officer shall be made prior to such action has been completed

    B.the relief of that officer shall never be made

    C.the relief of that officer shall be deferred until such action has been completed

    D.the relief of that officer shall be made by the captain


    正确答案:C

  • 第17题:

    The conference will not begin until every one of students' parents____.

    A. have been on
    B. got here
    C. has showed up
    D. come

    答案:C
    解析:
    考查主谓一致和时态。根据后面的every one of…可以判断谓语动词要用第三人称单数,排除A 和D。根据句意,这里是说家长到了会议才开始,强调动作的完成,要用完成时,故选C。

  • 第18题:

    The discussion has been()until Monday.

    A put up with

    B put off

    C put out

    D put of


    A

  • 第19题:

    Your database is in the NOARCHIVELOG mode. Since last night’s offline backup, the logs in group 1 have been written to twice. This morning, the SYSTEM data file has become corrupted. Up to what point can it be recovered?()

    • A、until the last commit
    • B、cannot be recovered
    • C、until the last offline backup
    • D、until the beginning of the last transaction

    正确答案:C

  • 第20题:

    A work order has been created to perform corrective maintenance on a defective generator. All required information has been provided in the work order, but required materials are not in stock and  have to be ordered.  What is the status of the work order, after a maintenance manager has approved the work order? ()

    • A、 Approved (APPR)
    • B、 Waiting on Materials (WMATL)
    • C、 Waiting to be Scheduled (WSCH)
    • D、 Waiting on Plant Condition (WPCOND)

    正确答案:B

  • 第21题:

    单选题
    A work order has been created to perform corrective maintenance on a defective generator. All required information has been provided in the work order, but required materials are not in stock and  have to be ordered.  What is the status of the work order, after a maintenance manager has approved the work order? ()
    A

     Approved (APPR)

    B

     Waiting on Materials (WMATL)

    C

     Waiting to be Scheduled (WSCH)

    D

     Waiting on Plant Condition (WPCOND)


    正确答案: C
    解析: 暂无解析

  • 第22题:

    问答题
    翻译:If the freight, contribution in general average demurrage to be paid to the carrier and other necessary charges paid by the carrier on behalf of the owner of the goods as well as other charges to be paid to the carrie have not been paid in full nor has appropriate security been given the carrier may have a lien to a reasonable extent on the goods.

    正确答案: 应当向承运人支付的运费、共同海损分摊、滞期费和承运人为货物垫付的必要费用以及应当向承运人支付的其他费用没有付清,又没有提供适当担保的,承运人可以在合理的限度内留置其货物。
    解析: 暂无解析

  • 第23题:

    单选题
    If there is a strike or lock-out affecting the cargo on or after vessel’s arrival at port of discharge and the same has not been settled within 48 hours,Receivers shall have the option of keeping vessel waiting until such strike or lock-out is at an end against paying half demurrage after expiration of the time prescribed for discharging or ordering the vessel to a substituting port.The “same” refers to().
    A

    the cargo

    B

    the port

    C

    the arrival

    D

    the strike or lock-out


    正确答案: D
    解析: 暂无解析