更多“单选题()means that every project has a definite beginning and a definite end.A Project phaseB UniqueC TemporaryD Closure”相关问题
  • 第1题:

    The following reports are normally developed during the project closure phase?

    A Communications Management Plan and Lessons Learned

    B Records Archive, Closure Report, lessons learned & Formal Acceptance Report

    C Records Archive, Closure Report, & Specifications Document

    D Communications Management Plan and Closure report

    E None of the above


    正确答案:B

  • 第2题:

    For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?

    A project office memo

    B project office directive

    C project team meeting

    D formal report

    E counseling sessions


    正确答案:D

  • 第3题:

    171 Documented work authorization provide:

    A. a means of effective internal coordination of the project's activities.

    B. an audit trail of all work authorized from project initiation to completion

    C.a means for communication of work activity between the project manager and the performing activities.

    D. All of the above

    E. A and B only


    正确答案:D

  • 第4题:

    6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第5题:

    96 A negative cost variance and positive schedule variance means:

    A. The project is under budget and ahead of schedule

    B. The project is over budget and behind schedule

    C. The project is over budget and ahead of schedule

    D. The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第6题:

    ● The use of the project reports:

    A are not necessary on small projects

    B provides a means whereby various levels of authority can judge project performance

    C provides insight into project areas and the effectiveness of the control systems

    D All of the above

    E B and C


    正确答案:E

  • 第7题:

    The(67)defines the phases that connect the beginning of a project to its end.

    A.schedule

    B.project life cycle

    C.temporary

    D.milestone


    正确答案:B
    解析:项目生命周期定义了从项目开始直至结束的项目阶段。

  • 第8题:

    The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )

    A.devclopment
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    项目的生命周期是对项目各个阶段从开始到结束的描述,下列哪项不是一个阶段的传统项目的生命周期,他的概念阶段。A开发B概念C系统分析D实施

  • 第9题:

    ()means that every project has a definite beginning and a definite end.

    • A、Project phase
    • B、Unique
    • C、Temporary
    • D、Closure

    正确答案:B

  • 第10题:

    The() defines the phases that connect the beginning of a project to its end.

    • A、schedule
    • B、project life cycle
    • C、temporary
    • D、milestone

    正确答案:D

  • 第11题:

    单选题
    Who is responsible for authorizing closure of the project?()
    A

    Project Manager

    B

    Stakeholder

    C

    Customer

    D

    Executive Sponsor


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    ()means that every project has a definite beginning and a definite end.
    A

    Projectphase

    B

    Unique

    C

    Temporary

    D

    Closure


    正确答案: A
    解析: 该题的关键词为"a definite beginning and a definite end",其语句结构为" (主语)means(谓语)that",含义为"什么意味着",该题干为项目管理的一个基本概念描述,描述了项目具备临时性特点。所以选择选项C。

  • 第13题:

    A negative cost variance and positive schedule variance means:

    A The project is under budget and ahead of schedule

    B The project is over budget and behind schedule

    C The project is over budget and ahead of schedule

    D The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第14题:

    112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

    A. Project Engineer

    B. Project Manager

    C. Functional Manager

    D. Quality Assurance Manager

    E. Project Owner


    正确答案:B

  • 第15题:

    200 A program is characterized as:

    A. a grouping or related tasks lasting one year or less.

    B. a unique undertaking having a definite time period.

    C. a grouping of similar projects having no definite end that supports the product(s) from cradle to grave. D. a project with a cost over $1 million.

    E. None of the above


    正确答案:C

  • 第16题:

    88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B. Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第17题:

    97 The following reports are normally developed during the project closure phase?

    A. Communications Management Plan and Lessons Learned

    B. Records Archive, Closure Report, lessons learned & Formal Acceptance Report

    C. Records Archive, Closure Report, & Specifications Document

    D. Communications Management Plan and Closure report

    E. None of the above


    正确答案:B

  • 第18题:

    means that every project has a definite beginning and a definite end.

    A.Project phase

    B.Unique

    C.Temporary

    D.Closure


    正确答案:C
    解析:临时性是指每一个项目都有一个明确的开始时间和结束时间。

  • 第19题:

    The (71) defines the phases that connect the beginning of a project to its end.

    A.milestone

    B.schedule

    C.temporary

    D.project life cycle


    正确答案:D

  • 第20题:

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    翻译:项目的生命周期是对项目各个阶段从开始到结束的描述。下列哪项不是一个阶段的传统项目的生命周期,它是概念阶段。A.开发 B.概念 C.系统分析 D.实施

  • 第21题:

    ()means that every project has a definite beginning and a definite end.

    • A、Projectphase
    • B、Unique
    • C、Temporary
    • D、Closure

    正确答案:C

  • 第22题:

    Who is responsible for authorizing closure of the project?()

    • A、Project Manager
    • B、Stakeholder
    • C、Customer
    • D、Executive Sponsor

    正确答案:D

  • 第23题:

    单选题
    ()means that every project has a definite beginning and a definite end.
    A

    Project phase

    B

    Unique

    C

    Temporary

    D

    Closure


    正确答案: B
    解析: 暂无解析

  • 第24题:

    单选题
    The() defines the phases that connect the beginning of a project to its end.
    A

    schedule

    B

    project life cycle

    C

    temporary

    D

    milestone


    正确答案: D
    解析: 暂无解析