An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
第1题:
An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
第2题:
Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()
第3题:
Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()
第4题:
A system administrator is installing a p5 590 server with an HMC. After pulling the websm client down, it is not possible to connect to the HMC. The HMC can be pinged from the client. Which of the following settings should be verified next?()
第5题:
The IP address of POWER6 595 is showing up in the HMC instead of the server name. Next to the IP address is the status, which shows ailedThe IP address of POWER6 595 is showing up in the HMC instead of the server name. Next to the IP address is the status, which shows ailed Authentication The system administrator needs to enter a password. Which password is needed to restore connection for the POWER6 595 to the HMC?()
第6题:
An administrator is applying a corrective service to their HMC. The corrective service has been shipped on 3 DVDs. Which action will ensure the corrective service is correctly installed?()
第7题:
A customer needs to create a number of LPARs on a new POWER6 server with some LPARs requiring a dedicated network and other LPARs utilizing Virtual Ethernet via a VIO server. Which limitation must be considered when planning the system configuration?()
第8题:
Order a POWER5 HMC
Connect to the existing HMC
Install an 8-port asynchronous card in the managed server to connect to the existing HMC
Install an additional network card to the existing HMC and connect to the POWER5 service processor
第9题:
An 8-port adapter to the HMC
A hub for the private network
An additional Ethernet card to the HMC
An additional Ethernet card for each partition
第10题:
Free up one HMC and update the software for use with the p5 570
Connect the new p5 570 server to an existing HMC and manage the p690s and p5 570 from that HMC
Order a new HMC to support the new p5 570 server since the CR3 HMC is not supported for a p5 570
Backup the HMC to DVD-RAM and select HMC migrate to move all the profile data to the new HMC software
第11题:
An 8-port adapter to the HMC
A hub for the private network
An additional Ethernet card to the HMC
An additional Ethernet card for each partition
第12题:
An additional switch for the new HMc
Asynchronous adapters on the new HMc
The two 570 servers are directly connected to the new HMc
One 570 is directly connected to the new HMC and the other is directly connected to the existing HMc
第13题:
A network administrator needs to add an additional connection to a room. The administrator adds a new Ethernet switch and must connect it to an existing switch. Which cable type should be used to connect the two switches?()
第14题:
The IP address of POWER6 595 is showing up in the HMC instead of the server name.Next to the IP address is the status,which shows Failed Authentication.The system administrator needs to enter a password. Which password is needed to restore connection for the POWER6 595 to the HMC?()
第15题:
A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()
第16题:
A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()
第17题:
A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()
第18题:
A customer currently has five partitioned POWER4 systems and is adding new systems. When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()
第19题:
A system administrator wants to control the HMC from their workstation. Microsoft Windows 2000 is running and the HMC graphical user interface is being used remotely. Which of the following actions will accomplish this task?()
第20题:
An additional switch for the new HMC
Asynchronous adapters on the new HMC
The two 570 servers are directly connected to the new HMC
One 570 is directly connected to the new HMC and the other is directly connected to the existing HMC
第21题:
The hscroot user password.
The CE password.
The HMC password.
The ASM admin password.
第22题:
Select the option to automatically reboot the HMC
Select the option to automatically reboot the HMC after each disk
Shutdown all managed LPARs prior to beginning the install process
Copy all disks into the SERVICE directory and select concurrent install
第23题:
The hscroot user password.
The CE password.
The HMC password.
The ASM admin password.