参考答案和解析
正确答案:A
更多“131 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:A. Code of accounts.B. Overhead rates.C. Budgeting system.D. Capital budgeting process.E. All of the above”相关问题
  • 第1题:

    The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

    A.Work packages.

    B.Subtasks.

    C.Tasks.

    D.Code of accounts.

    E.Integration points.


    正确答案:C

    C

  • 第2题:

    Company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the:

    A . Capital budgeting process.

    B . Overhead rates.

    C . Contracts and administration costing system.

    D . Fringe benefits packages.

    E . None of the above.


    正确答案:B

  • 第3题:

    Which of the following would most likely increase the accuracy of estimating the project cost?

    A . Pricing out the work at lower levels in the work breakdown structure.

    B . Using historical data.

    C . Talking to people who have worked on similar projects.

    D . All of the above.

    E . A and C only.


    正确答案:D

  • 第4题:

    96 A task-oriented family tree of activities is a:

    A. Detailed plan.

    B. Linear responsibility chart.

    C. Work breakdown structure.

    D. Cost account coding system.

    E. Work package description.


    正确答案:C

  • 第5题:

    146 The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

    A. Time, schedule and cost.

    B. Management coordination and organization structuring.

    C. Work methods and accountability.

    D. Quality of work.

    E. Risk and impact decision-making


    正确答案:D

  • 第6题:

    154 A Work Breakdown Structure:

    A. assures all work is identified

    B. subdivides the project into manageable segments

    C. provides the project sponsor with a time-phase task summary

    D. both A and B

    E. All of the above


    正确答案:D

  • 第7题:

    13 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:

    A. Code of accounts.

    B. Overhead rates.

    C. Budgeting system.

    D. Capital budgeting process.

    E. All of the above.


    正确答案:A

  • 第8题:

    148 Work packages are used to:

    A. Represent units of work at a level where work is performed.

    B. Clearly distinguish one work package from all others assigned to a single functional group.

    C. Limit the work to be performed to relatively short periods of time.

    D. All of the above.

    E. A and B only


    正确答案:D

  • 第9题:

    168 A work breakdown structure:

    A. assures all work is identified.

    B. subdivides the project into manageable segments.

    C. provides the project sponsor with a time-phase task summary.

    D. both A and B.

    E. All of the above.


    正确答案:D

  • 第10题:

    ● A Work Breakdown Structure:

    A assures all work is identified

    B subdivides the project into manageable segments

    C provides the project sponsor with a time-phase task summary

    D both A and B

    E All of the above.


    正确答案:D

  • 第11题:

    ● The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

    A Work packages.

    B Subtasks.

    C Tasks.

    D Code of accounts.

    E Integration points.


    正确答案:C

  • 第12题:

    The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.

    A.Schedule and cost

    B.Organization structuring

    C.Management coordination

    D.Quality of work


    正确答案:D

  • 第13题:

    A task-oriented family tree of activities is a:

    A.Detailed plan.

    B.Linear responsibility chart.

    C.Work breakdown structure.

    D.Cost account coding system.

    E.Work package description.


    正确答案:C
    C

  • 第14题:

    The work breakdown structure, the work packages, and the company's accounting system are tied together through the:

    A . Code of accounts.

    B . Overhead rates.

    C . Budgeting system.

    D . Capital budgeting process.

    E . All of the above.


    正确答案:A

  • 第15题:

    87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.

    B. Using historical data.

    C. Talking to people who have worked on similar projects.

    D. All of the above.

    E. A and C only.


    正确答案:D

  • 第16题:

    106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

    A. Work packages.

    B. Subtasks.

    C. Tasks.

    D. Code of accounts.

    E. Integration points


    正确答案:C

  • 第17题:

    10 Company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the:

    A. Capital budgeting process.

    B. Overhead rates.

    C. Contracts and administration costing system.

    D. Fringe benefits packages.

    E. None of the above


    正确答案:B

  • 第18题:

    51 Going from Level 2 to Level 4 in the work breakdown structure will result in

    A. Less estimating accuracy

    B. Better control of the project

    C. Lower status reporting costs

    D. A greater likelihood that something will fall through the cracks

    E. None of the above


    正确答案:E

  • 第19题:

    86 A work breakdown structure:

    A. assures all work is identified.

    B. subdivides the project into manageable segments.

    C. provides the project sponsor with a time-phase task summary.

    D. both A and B.

    E. All of the above


    正确答案:D

  • 第20题:

    178 A task-oriented family tree of activities is a:

    A. Detailed plan.

    B. Linear responsibility chart.

    C. Work breakdown structure.

    D. Cost account coding system.

    E. Work package description


    正确答案:C

  • 第21题:

    ● Going from Level 2 to Level 4 in the work breakdown structure will result in

    A Less estimating accuracy

    B Better control of the project

    C Lower status reporting costs

    D A greater likelihood that something will fall through the cracks

    E None of the above


    正确答案:E

  • 第22题:

    ● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

    A Time, schedule and cost.

    B Management coordination and organization structuring.

    C Work methods and accountability.

    D Quality of work.

    E Risk and impact decision-making.


    正确答案:D

  • 第23题:

    ● A task-oriented family tree of activities is a:

    A Detailed plan.

    B Linear responsibility chart.

    C Work breakdown structure.

    D Cost account coding system.

    E Work package description.


    正确答案:C