更多“Formal written communication is mandated for which of the following?A scope changes not part of the original projectB taking exception to a specificationC procurement of raw materialsD All of the above.E A and B only”相关问题
  • 第1题:

    Which of the following would most likely increase the accuracy of estimating the project cost?

    A . Pricing out the work at lower levels in the work breakdown structure.

    B . Using historical data.

    C . Talking to people who have worked on similar projects.

    D . All of the above.

    E . A and C only.


    正确答案:D

  • 第2题:

    Which of the following areas are addressed in risk identification:

    A environmental

    B technical

    C legal

    D All of the above.

    E A and B only


    正确答案:D

  • 第3题:

    Which of the following is equivalent to a lump sum contract:

    A fixed price contract

    B price fixing contract

    C purchase order

    D All of the above.

    E B and C only


    正确答案:A

  • 第4题:

    Which of the following are part of the purchasing cycle:

    A define need

    B prepare and issue purchase order

    C inspect incoming goods

    D All of the above.

    E A and B only


    正确答案:E

  • 第5题:

    132 Which of the following is an element of procurement management:

    A. inspection

    B. purchasing

    C. estimating

    D. expediting

    E. A, B and D only


    正确答案:E

  • 第6题:

    42 In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

    A. unit price

    B. cost plus incentive fee

    C. cost plus fixed fee

    D. firm fixed price

    E.B and D only


    正确答案:D

  • 第7题:

    76 Formal written correspondence is mandated in which of the following situations:

    A. Product undergoes casual in-house testing

    B. Client requests additional work not covered under contract

    C. Project manager calls a meeting

    D. B and C only

    E. None of the above


    正确答案:B

  • 第8题:

    146 Which of the following are included as part of a scope statement?

    A. Project justification

    B. Project deliverables

    C. Project objectives

    D. All of the above

    E. B and C


    正确答案:D

  • 第9题:

    ● Configuration (baseline) control monitors performance against the

    A scope baseline

    B original schedule

    C original budget

    D All of the above.

    E None of the above.


    正确答案:A

  • 第10题:

    ● The scope baseline once established and approved, is used:

    A as the basis for making future decisions.

    B to accomplish verification measures.

    C to evaluate potential changes.

    D All of the above.

    E A and C only.


    正确答案:D

  • 第11题:

    When one connection to a host fails in a full mesh network, which of the following is true?()

    • A、All hosts can communicate.
    • B、No hosts can communicate.
    • C、Half of the hosts will lose communication.
    • D、Only the two hosts between the failed connection will lose communication.

    正确答案:A

  • 第12题:

    A system administrator has backed up the datavg volume group using the savevg command. There are several raw logical volumes and some unmounted jfs filesystems in datavg. Which of the following statements is true about this backup?()

    • A、The volume group and all logical volumes will be recreated. All raw and jfs filesystms will be backed up and restored.
    • B、This backup will be bootable and the volume group and all jfs logical volumes will be recreated.
    • C、This backup will not be bootable and the restorevg command is used to restore only the mounted and non-raw logical volumes. It will not recreate any logical volumes that are raw or unmounted.
    • D、The volume group and all logical volumes information is archived and will be recreated. The raw and unmounted filesystems will not be backed up and therefore not restored.

    正确答案:D

  • 第13题:

    Formal written correspondence is mandated in which of the following situations:

    A Product undergoes casual in-house testing

    B Client requests additional work not covered under contract

    C Project manager calls a meeting

    D B and C only

    E None of the above


    正确答案:B

  • 第14题:

    In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

    A unit price

    B cost plus incentive fee

    C cost plus fixed fee

    D firm fixed price

    E B and D only


    正确答案:D

  • 第15题:

    Which of the following is an element of procurement management:

    A inspection

    B purchasing

    C estimating

    D expediting

    E A, B and D only


    正确答案:E

  • 第16题:

    116 Which of the following are part of the purchasing cycle:

    A. define need

    B. prepare and issue purchase order

    C. inspect incoming goods

    D. All of the above.

    E. A and B only


    正确答案:E

  • 第17题:

    Which of the following is an element of procurement management:

    A. inspection

    B. purchasing

    C. estimating

    D. expediting

    E. A, B and D only


    正确答案:E

  • 第18题:

    177 Formal written communication is mandated for which of the following?

    A. scope changes not part of the original project

    B. taking exception to a specification

    C. procurement of raw materials

    D. All of the above.

    E. A and B only


    正确答案:D

  • 第19题:

    88 The scope statement provides

    A. A basis for future decisions about a project.

    B. A baseline to accomplish verification measures.

    C. A baseline to evaluate potential scope changes.

    D. All of the above

    E. B and C only


    正确答案:D

  • 第20题:

    ● Which of the following are included as part of a scope statement?

    A Project justification

    B Project deliverables

    C Project objectives

    D All of the above

    E B and C


    正确答案:D

  • 第21题:

    ● The scope management provides:

    A A basis for future decisions about the project.

    B A baseline to accomplish verification measures.

    C A baseline to evaluate potential scope changes.

    D All of the above.

    E B and C only.


    正确答案:D

  • 第22题:

    Which of following is an important input to scope verification? ()

    A.Work results
    B.Historical information
    C.Formal acceptance
    D.Change request

    答案:A
    解析:
    译文:下面哪一项是范围确认的重要输入?
    A、工作结果 B、历史信息 C、正式验收 D、变更请求

  • 第23题:

    Which of the following defines memory interleaving?()

    • A、The distribution of data written across all the memory DIMMs and the L1 cache
    • B、The distribution of data written across all the memory DIMMs in one bank
    • C、The distribution of data written across all the memory DIMMs and the processor
    • D、The distribution of data written across all the memory DIMMs and the L2 cache

    正确答案:B