47 The major difference between PERT and CPM networks is:
A. PERT requires three time estimates whereas CPM requires one time estimate.
B. PERT is used for construction projects whereas CPM is used for R & D.
C. PERT addresses only time whereas CPM also includes cost and resource availability.
D. PERT requires computer solutions whereas CPM is a manual technique.
E. PERT is measured in days whereas CPM uses weeks or months
第1题:
A.时间估计与分析
B.画法不同
C.组成不同
D.时间参数不同
第2题:
101 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A. Increases.
B. Is not affected by
C. Does not require
D. Is heavily dependent upon
E. Is the only means of determining
第3题:
有哪三种主要的图示法:( )
A.AOA、PERT、CPM
B.PERT、CPM、GERT
C.先导、箭线、条件
D.AON、AOA、PDM
第4题:
● The first step in building a PERT/CPM network is to:
A Create a flow chart
B Determine the critical path
C Show task relationships
D Create a work breakdown structure
E None of the above.
第5题:
PERT和CPM的最根本区别是( )。
A.CPM的工作逻辑关系肯定,PERT的工作逻辑关系不确定
B.CPM使用最大可能工作时间估计,PERT使用加权平均时间估计
C.CPM的工作必须进行,PERT的某些工作可以不进行
D.CPM不允许存在回路,PERT中可以存在回路
第6题:
第7题:
第8题:
目前,软件项目的进度安排的两种比较常用的方法是程序评估与审查技术(PERT)和关键路径法(CPM)。
第9题:
下列哪个关于估算的说法是正确的()
第10题:
三种主要的用于项目管理的图示法是:()
第11题:
CPM和PERT在时间的估计和分析上是相同的。
第12题:
AOA、PERT、CPM
PERT、CPM、GERT
先导、箭线、条件
D、AON、AOPDM
第13题:
190 The first step in building a PERT/CPM network is to:
A. Create a flow chart
B. Determine the critical path
C. Show task relationships
D. Create a work breakdown structure
E. None of the above
第14题:
129 The major difference between PERT and CPM networks is:
A. PERT requires three time estimates whereas CPM requires one time estimate.
B. PERT is used for construction projects whereas CPM is used for R & D.
C. PERT addresses only time whereas CPM also includes cost and resource availability.
D. PERT requires computer solutions whereas CPM is a manual technique.
E. PERT is measured in days whereas CPM uses weeks or months
第15题:
● The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A Increases.
B Is not affected by
C Does not require
D Is heavily dependent upon
E Is the only means of determining
第16题:
● 在软件开发中, (29) 不能用来描述项目开发的进度安排。在其他三种图中可用 (30) 动态地反映项目开发进展情况。
(29)A. 甘特图 B. PERT 图 C. PERT/CPM 图 D. 鱼骨图
(30)A. 甘特图 B. PERT 图 C. PERT/CPM 图 D. 鱼骨图

第17题:
在信息系统项目建设开发中,( )不能用来描述项目的进度安排;( )可采用来动态的放映建设的进展状况。
A.甘特图B.pert 图C.pert/cpm 图D.鱼骨图A.甘特图B.pert 图C.pert/cpm 图D.鱼骨图
第18题:
第19题:
分析CPM和PERT的主要的特点及区别。
第20题:
三种主要的图示法(diagramming methods)是()
第21题:
有哪三种主要的图示法()
第22题:
下列有关PERT和CPM的说法错误的是()
第23题:
制定项目计划常用的方法有()