24 A comparison of completion status to baseline is referred to as _____.
A. Earned value measurement.
B. Percent complete.
C. ACWP.
D. BCWS
E. None of above
第1题:
A budget estimate should give the manager cost data accurate to within:
A . -5 to +10 percent of actual cost
B . -25 to +75 percent of actual cost
C . -30 to +75 percent of actual cost
D . -10 to +25 percent of actual cost
E . None of the above
第2题:
The difference between the BCWS and the BCWP is referred to as the:
A . Schedule variance
B . Cost variance.
C . Estimate of completion
D . Actual cost of the work performed
E . None of the above
第3题:
A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.
A . Trend line.
B . Trend analysis.
C . S curve.
D . Percent completion report.
E . Earned value report.
第4题:
58 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.
A. Trend line.
B. Trend analysis.
C. S curve.
D. Percent completion report.
E. Earned value report
第5题:
23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A. Baseline costs
B Budgeted costs.
C. Estimates upon completion costs
D. Scheduled costs
E. None of the above
第6题:
105 A budget estimate should give the manager cost data accurate to within:
A. -5 to +10 percent of actual cost
B. -25 to +75 percent of actual cost
C. -30 to +75 percent of actual cost
D. -10 to +25 percent of actual cost
E. None of the above
第7题:
100 The difference between the BCWS and the BCWP is referred to as the:
A. Schedule variance
B. Cost variance.
C. Estimate of completion
D. Actual cost of the work performed
E. None of the above
第8题:
24 Activities with zero time duration are referred to as:
A. Critical path activites.
B. Noncritical path activities.
C. Slack time activities.
D. Dummies
E. None of above
第9题:
48 The ability to achieve cost savings is inversely proportional to _____.
A. the earned value achieved to date
B. the estimated costs to complete
C. empowerment to the P.M.
D. productivity
E. None of the above
第10题:
● Configuration (baseline) control monitors performance against the
A scope baseline
B original schedule
C original budget
D All of the above.
E None of the above.
第11题:

A. It is loaded with the FIXED status.
B. It is loaded with the ACCEPTED status.
C. It is not loaded with the ENABLED status.
D.It is not loaded with the ACCEPTED status.
第12题:
第13题:
Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A . Baseline costs
B . Budgeted costs.
C . Estimates upon completion costs
D . Scheduled costs
E . None of the above
第14题:
Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A . Become worse, become worse
B . Become worse, improved
C . Improved, increased
D . Improved, become worse
E . None of the above are correct
第15题:
142 Activities with zero time duration are referred to as:
A. Critical path activites.
B. Noncritical path activities.
C. Slack time activities.
D. Dummies
E. None of above
第16题:
18 The difference between the BCWS and the BCWP is referred to as the:
A. Schedule variance
B Cost variance.
C. Estimate of completion
D. Actual cost of the work performed
E. None of the above
第17题:
46 Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called: A. Variance reports
B. S curves
C. Trend analysis
D. Earned value reporting
E. Baseline control
第18题:
183 Configuration (baseline) control monitors performance against the
A. scope baseline
B. original schedule
C. original budget
D. All of the above.
E. None of the above
第19题:
105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A. Baseline costs
B. Budgeted costs.
C. Estimates upon completion costs
D. Scheduled costs
E. None of the above
第20题:
106 A comparison of completion status to baseline is referred to as _____.
A. Earned value measurement.
B. Percent complete.
C. ACWP.
D. BCWS
E. None of above
第21题:
106 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A. Become worse, become worse
B. Become worse, improved
C. Improved, increased
D. Improved, become worse
E. None of the above are correct
第22题:
● Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:
A Variance reports
B S curves
C Trend analysis
D Earned value reporting
E Baseline control
第23题:
Upon completion of fueling a gasoline driven vessel it is necessary to ______.
A.keep ports,doors,windows,and hatches closed
B.start engines immediately
C.ventilate before starting engine
D.None of the above