Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:
A.Variance reports
B.S curves
C.Trend analysis
D.Earned value reporting
E.Baseline control
第1题:
A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.
A . Trend line.
B . Trend analysis.
C . S curve.
D . Percent completion report.
E . Earned value report.
第2题:
Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:
A . Overhead rates, labor rates and material costs.
B . Overhead rates, schedule slippages, and rework.
C . Rework, cost-of-living adjustments, and overtime.
D . Material costs, shipping cost, and scope changes.
E . Labor rates, material costs, and cost reporting.
第3题:
Which of the following control types has the highest risk to the owner:
A Firm fixed price (FFP)
B Time and material (T&M)
C Cost plus fixed fee (CPFF)
D Cost plus incentive fee (CPIF)
E A and B only
第4题:
95 Which type of contract requires that the buyer keep the tightest labor/material cost control?
A. Cost Plus Incentive Fee
B. Cost Plus Percentage of Costs
C. Cost Plus Fixed Fee
D. Firm Fixed Price
E. Firm Fixed Price Plus Incentive
第5题:
19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?
A. Direct labor dollars
B. Direct labor hours.
C. Overhead rates.
D. Procurement costs.
E. None of the above
第6题:
89 An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:
A. Higher salaried employees were assigned.
B. Overtime was required.
C. The overhead rate increased.
D. Employee salaries had increased.
E. Any of the above
第7题:
159 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
A. Multiplying the actual hours worked on the project by the budgeted labor rate.
B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C. Dividing the actual hours required to complete the task by the budgeted labor rate.
D. Cannot be determined.
E. None of the above
第8题:
● Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:
A Variance reports
B S curves
C Trend analysis
D Earned value reporting
E Baseline control
第9题:
在当前表单的LABELl控件中显示系统时间的语句是______。
A.THISFORM.LABELl.TEXT=TIME()
B.THISFORM.LABELI.VALUE=TIME()
C.THISFORM.LABELl.CAPTION=TIME()
D.THISFORM.LABELl.CONTROL=TIME()
第10题:
( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.
A.The control accounts
B.Funding requirement
C.The cost estimates
D.The cost baseline
第11题:
TestKing.com has a SQL Server 2005 computer. You have been assigned the task of retrieving information about a user who is currently logged in. You need to create a function that returns scalar information about the activity time for a particular user. What are two possible ways to achieve this goal?()
第12题:
第13题:
It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?
A . Direct labor dollars
B . Direct labor hours.
C . Overhead rates.
D . Procurement costs.
E . None of the above.
第14题:
Amount at Stake is the _____ .
A function of planned time/real time project costs.
B risk identified in successful project completions.
C (Standard Project Deviation + Expected Costs)/6
D cost of investment loss + least cost to restore status quo.
E inherent risk at conception altered by standard project deviations.
第15题:
Which type of contract requires that the buyer keep the tightest labor/material cost control?
A Cost Plus Incentive Fee
B Cost Plus Percentage of Costs
C Cost Plus Fixed Fee
D Firm Fixed Price
E Firm Fixed Price Plus Incentive
第16题:
144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:
A. Overhead rates, labor rates and material costs.
B. Overhead rates, schedule slippages, and rework.
C. Rework, cost-of-living adjustments, and overtime.
D. Material costs, shipping cost, and scope changes.
E. Labor rates, material costs, and cost reporting
第17题:
58 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.
A. Trend line.
B. Trend analysis.
C. S curve.
D. Percent completion report.
E. Earned value report
第18题:
146 The planned cost for the total project at its inception is called the _____.
A. Cost of goods sold.
B. Depreciable value.
C. Budgeted cost.
D. All of the above.
E. B and C only
第19题:
46 Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called: A. Variance reports
B. S curves
C. Trend analysis
D. Earned value reporting
E. Baseline control
第20题:
● Scope management is:
A a project control function.
B employs change control.
C a work authorization process.
D considers Cost, Quality and Schedule.
E All of the above.
第21题:

A. The cached result becomes invalid when any structural change is done to the EMPLOYEES table.
B. If the function execution results in an unhandled exception, the exception result is also stored in the cache.
C. Each time the function is invoked in a different session, the current result in the result cache gets overwritten.
D. If the function is invoked with a different parameter value, the existing result in the result cache gets overwritten by the latest value.
第22题:
Which factor has the greatest impact on the estimated per unit labor cost for a project?()
第23题:
the stated value
the sound valve of the vessel at the time of occurrence
the lost value
the insured value