● Which of the following can be tracked using the WBS?
A time
B cost
C performance
D scope
E None of the above.
第1题:
Which of the following is referred to as payback period:
A . the number of periods required to recover the initial investment
B . the rate of return on the investment
C . the number of periods required to bring project cost back to the original budget, based on current performance
D . loan payment schedule
E . None of the above
第2题:
Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?
A . Element P
B . Element Q
C . Element R
D . Element S
E . None of the above.
第3题:
A project manager can exchange information with the project team using which media?
A tactile
B audio
C olfactory
D visual
E All of the above.
第4题:
The _____ specification delineates specific measurable capabilities or parameters for which a product can be tested as part of the acceptance procedure.
A Performance
B Functional
C Technical
D Base Line
E None of the above.
第5题:
115 In which of the following contract types is it easier to change the scope of the contract:
A. firm fixed price
B. fixed price plus incentive fee
C. cost plus percentage of cost
D. letter contract
E. None of the above.
第6题:
57 Which of the following are types of status reports?
A. document, variance, trend and exception
B. cost, trend, schedule and acquisition
C. cost, schedule, technical performance
D. analysis, cost, performance and schedule
E. All of the above.
第7题:
101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
A. Element P
B. Element Q
C. Element R
D. Element S
E. None of the above
第8题:
● Which of the following are types of status reports?
A document, variance, trend and exception
B cost, trend, schedule and acquisition
C cost, schedule, technical performance
D analysis, cost, performance and schedule
E All of the above.
第9题:
● Using the WBS shown in the Special window, a typical work package would be:
A Software development
B Systems design
C Coding
D A, B, and C
E None of the above.
第10题:
A. Broadcasts are not forwarded across the router.
B. All broadcasts are completely eliminated.
C. Adding a router to the network decreases latency.
D. Filtering can occur based on Layer 3 information.
E. Routers are more efficient than switches and will process the data more quickly.
F. None of the above.
第11题:
Which of the following options enables a user to get authenticated though a single password instead of using multiple passwords?()
第12题:
GLBP
HSRP
RPR
VRRP
SLB
RPR+
None of the other alternatives apply
第13题:
Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.
A . Over, 16.66
B . Under, 16.66
C . Over, 10.0
D . Under, 10.0
E . None of the above.
第14题:
Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
A . Element P
B . Element Q
C . Element R
D . Element S
E None of the above.
第15题:
By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:
A Significantly reduce project risks
B eliminate project risks
C provide a rational basis for better decision making
D identify risks, their impact(s), and any appropriate responses
E None of the above.
第16题:
72 Which of the following is referred to as payback period:
A. the number of periods required to recover the initial investment
B. the rate of return on the investment
C. the number of periods required to bring project cost back to the original budget, based on current performance
D. loan payment schedule
E. None of the above
第17题:
45 The most common definition of project success is:
A. Within time
B. Within time and cost
C. Within time, cost and technical performance requirements
D. Within time, cost, performance and accepted by the customer/user
E. None of the above
第18题:
60 Which of the following can be tracked using the WBS?
A. time
B. cost
C. performance
D. scope
E. None of the above
第19题:
102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?
A. Element P
B. Element Q
C. Element R
D. Element S
E. None of the above
第20题:
● The most common definition of project success is:
A Within time
B Within time and cost
C Within time, cost and technical performance requirements
D Within time, cost, performance and accepted by the customer/user
E None of the above
第21题:
● Which of the following impacts the critical path?
A Changing the task duration.
B Reduce the free float of an activity.
C Executing a backward pass
D A or B
E None of the above.
第22题:
You want to implement a high availability network using two Cisco routers. You also want to ensure that the stat of the WAN interfaces can be tracked in doing so. Which router redundancy protocol cannot be configured for interface tracking? ()
第23题:
For which of the following can you use Segment Shrink?()