更多“Which of the following impacts the critical path?A.Changing the task duration.B.Reduce the free float of an activity.C.Executing a backward passD.A or BE.None of the above.”相关问题
  • 第1题:

    The critical path in a schedule network is the path that:

    A.Takes the longest time to complete

    B.Must be done before any other tasks

    C.Allows some flexibility in scheduling a start time.

    D.Is not affected by schedule slippage

    E.All of the above.


    正确答案:A
    A

  • 第2题:

    A non-critical path activity is completed in half the time. Then,

    A.The critical path is also reduced.

    B.The slack in the path containing this activity will increase.

    C.The total cost for this activity has decreased.

    D.Manpower from this activity can be assigned to other activities.

    E.All of the above.


    正确答案:B

  • 第3题:

    On a precedence diagram, the arrow between two boxes is called:

    A.An activity.

    B.A constraint.

    C.An event.

    D.The critical path.

    E.None of above.


    正确答案:B
    B

  • 第4题:

    Standard deviation of project completion is _____ .

    A a relationship of the uncertainty of critical path activities.

    B an indicator of project end date target confidence

    C a function of critical path, leveling and project costs.

    D A and B

    E All of the above.


    正确答案:D

  • 第5题:

    112 The schedule risk is the _____ .

    A. the accumulated "expected' durations which maintain project completion.

    B. Critical Path adjusted by "high-risk" activity float.

    C. highest risk path that maintains quality.

    D. Critical Path when calculated with "most likely" duration.

    E. highest risk path that contributes the most risk toward the project completion


    正确答案:B

  • 第6题:

    163 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

    A. The project will be completed late.

    B. The critical path has been lengthened.

    C. the costs are being overrun.

    D. Overtime will be required to maintain the original critical path.

    E. None of the above.


    正确答案:E

  • 第7题:

    ● The critical path is calculated by

    A subtracting the end date of task one from the start date of task two.

    B determining which tasks have the least amount of total slack.

    C totaling the time for all activities.

    D determining the shortest path through the network.

    E Determining which tasks have the most slack


    正确答案:B

  • 第8题:

    ● Free float is the amount of time that an activity may be delayed with out affecting the _____.

    A Early start of the succeeding activities.

    B Late start of the succeeding activities.

    C Project finish.

    D Cost of the project.

    E None of the above.


    正确答案:A

  • 第9题:

    ● The first step in building a PERT/CPM network is to:

    A Create a flow chart

    B Determine the critical path

    C Show task relationships

    D Create a work breakdown structure

    E None of the above.


    正确答案:D

  • 第10题:

    ● Bar charts are most appropriate for:

    A Comparing actual to planned performance to each activity.

    B Showing slack time.

    C Showing critical path dependencies.

    D Showing which activities can be rearranged in parallel.

    E All of the above.


    正确答案:A

  • 第11题:

    In the following statements about graph operations,which one is NOT correct?

    A.Finding critical path is an operation on directed graph

    B.Finding critical path is an operation on undirected graph

    C.Spanning tree of a graph may not be unique

    D.Minimum spanning tree of a graph may not be unique


    正确答案:B

  • 第12题:

    单选题
    An administrator needs to add the /usr/vac/bin directory to their PATH environment variable for the current session.  Which of the following will accomplish this task()
    A

    path=$path:/usr/vac/bin; export path

    B

    path.=/usr/vac/bin; export $path

    C

    Modify the path environment variable in /etc/profile

    D

    Modify the path environment variable in /.profile


    正确答案: A
    解析: 暂无解析

  • 第13题:

    Bar charts are most appropriate for:

    A.Comparing actual to planned performance to each activity.

    B.Showing slack time.

    C.Showing critical path dependencies.

    D.Showing which activities can be rearranged in parallel.

    E.All of the above.


    正确答案:A
    A

  • 第14题:

    Activities with zero time duration are referred to as:

    A.Critical path activites.

    B.Noncritical path activities.

    C.Slack time activities.

    D.Dummies

    E.None of above.


    正确答案:D
    D

  • 第15题:

    During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

    A . The project will be completed late.

    B . The critical path has been lengthened.

    C . the costs are being overrun.

    D . Overtime will be required to maintain the original critical path.

    E . None of the above.


    正确答案:E

  • 第16题:

    The schedule risk is the _____ .

    A the accumulated "expected' durations which maintain project completion.

    B Critical Path adjusted by "high-risk" activity float.

    C highest risk path that maintains quality.

    D Critical Path when calculated with "most likely" duration.

    E highest risk path that contributes the most risk toward the project completion.


    正确答案:B

  • 第17题:

    160 Which of the following impacts the critical path?

    A. Changing the task duration.

    B. Reduce the free float of an activity.

    C. Executing a backward pass

    D. A or B

    E. None of the above


    正确答案:A

  • 第18题:

    ● Which of the following is indicative of negative float?

    A The late start date is earlier than the early start date.

    B The critical path supports the imposed end date.

    C The early finish date is equal to the late finish date.

    D When leads are employed in the schedule.

    E The project is sinking.


    正确答案:A

  • 第19题:

    ● Which of the following impacts the critical path?

    A Changing the task duration.

    B Reduce the free float of an activity.

    C Executing a backward pass

    D A or B

    E None of the above.


    正确答案:A

  • 第20题:

    ● In crashing a task, you would focus on:

    A As many tasks as possible.

    B Non critical tasks.

    C Accelerating performance of tasks on critical path.

    D Accelerate performance by minimizing cost.

    E A and D.


    正确答案:C

  • 第21题:

    ● The critical path in a schedule network is the path that:

    A Takes the longest time to complete

    B Must be done before any other tasks

    C Allows some flexibility in scheduling a start time.

    D Is not affected by schedule slippage

    E All of the above.


    正确答案:A

  • 第22题:

    ● A non-critical path activity is completed in half the time. Then,

    A The critical path is also reduced.

    B The slack in the path containing this activity will increase.

    C The total cost for this activity has decreased.

    D Manpower from this activity can be assigned to other activities.

    E All of the above.


    正确答案:B

  • 第23题:

    A critical path for a project is the series of activities that determine( )by which the project can be completed.

    A.the earliest time
    B.the latest time
    C.the total time
    D.the free time

    答案:A
    解析:
    翻译:关键路径通常由一系列决定项目工期的活动组成,它们决定了整个项目的( )。A.最早完成时间 B.最迟完成时间 C.总时间 D.自由时间