The best way to insure quality conformance is to _____.A . distribute the responsibility to subordinates.B . maintain total control.C . train each worker to implement the work.D . inspect quality into the project.E . None of the above.

题目

The best way to insure quality conformance is to _____.

A . distribute the responsibility to subordinates.

B . maintain total control.

C . train each worker to implement the work.

D . inspect quality into the project.

E . None of the above.


相似考题
更多“The best way to insure quality conformance is to _____.A . distribute the responsibility to subordinates.B . maintain total control.C . train each worker to implement the work.D . inspect quality into the project.E . None of the above.”相关问题
  • 第1题:

    Quality control is normally performed by the _____ .

    A . QA personnel

    B . project team

    C . operating personnel

    D . project management

    E . None of the above.


    正确答案:C

  • 第2题:

    Inspection of a complex project according to specifications is accomplished by _____.

    A . inspection by attributes.

    B . cyclical inspection

    C . quality conformance inspection

    D . original inspection

    E . None of the above.


    正确答案:C

  • 第3题:

    In the project environment, the individual ultimately responsible for quality control is:

    A . The line workers who must strive "to do things right the first time" to avoid quality problems.

    B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.

    C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.

    D . The project manager who has ultimate responsibility for the entire project.

    E . the customer who must ensure that he is receiving a quality product from the vendor.


    正确答案:D

  • 第4题:

    Japanese quality control has improved dramatically in the last 30 years for all of the following reasons except:

    A . the use of quality circles.

    B . small, continuous improvements in quality control.

    C . the use of worker suggestion systems.

    D . the use of quality control charts.

    E . focusing quality control efforts on production outputs.


    正确答案:E

  • 第5题:

    Which of the following is closet to Deming's definition of Quality:

    A . conformance to requirements.

    B . fitness for use.

    C . continuous improvement of products and services.

    D . customer focus.

    E . All of the above.


    正确答案:C

  • 第6题:

    132 A proven effective means to insure quality conformance is to:

    A. delegate accountability to subordinates

    B. revise quality specifications to match quality measurements

    C. train workers in proper quality methods

    D. inspect quality into the product

    E. make quality a higher priority than cost or schedule


    正确答案:C

  • 第7题:

    9 The best way to insure quality conformance is to _____.

    A. distribute the responsibility to subordinates.

    B maintain total control.

    C. train each worker to implement the work.

    D. inspect quality into the project.

    E. None of the above


    正确答案:C

  • 第8题:

    39 Quality and _____ are directly related.

    A. productivity

    B. cost overruns

    C. scope control

    D. Pareto diagram

    E. None of the above.


    正确答案:A

  • 第9题:

    91 The best way to insure quality conformance is to _____.

    A. distribute the responsibility to subordinates.

    B. maintain total control.

    C. train each worker to implement the work.

    D. inspect quality into the project.

    E. None of the above


    正确答案:C

  • 第10题:

    ● Proper implementation of project management will guarantee that:

    A Budgets will be met.

    B Schedules will be adhered to.

    C Quality/performance will be met.

    D The project will be a success.

    E None of the above.


    正确答案:E

  • 第11题:

    “Cost of quality”is a project management concept that includes cost of( 73)

    A.exceedings requirements

    B.Changes to the requirements

    C.Ensuring conformance to requirements

    D.The quality control requirements


    正确答案:C

  • 第12题:

    单选题
    下列组合正确的是(  )。
    A

    质量管理—quality control

    B

    质量管理—quality management

    C

    质量管理—quality assurance

    D

    质量管理—quality circle

    E

    质量管理—total quality management


    正确答案: A
    解析:
    质量管理(quanlity management,QM)是指导和控制影像质量的一切活动,它包括质量保证(quality assurance,QA)和质量控制(quality control,QC)活动的全部过程。

  • 第13题:

    Quality and _____ are directly related.

    A . productivity

    B . cost overruns

    C . scope control

    D . Pareto diagram

    E . None of the above.


    正确答案:A

  • 第14题:

    In order to achieve long-term quality improvements, management must do the following:

    A . Motivate the employees with seminars, contests, and institute programs such as "Quality Improvement' day.

    B . Create a quality control department and give the head of the department ultimate responsibility for quality improvement.

    C . Implement of a formal quality control program with worker and management involvement.

    D . Establish financial incentive packages for worker.

    E . A and D


    正确答案:C

  • 第15题:

    A proven effective means to insure quality conformance is to:

    A . delegate accountability to subordinates

    B . revise quality specifications to match quality measurements

    C . train workers in proper quality methods

    D . inspect quality into the product

    E . make quality a higher priority than cost or schedule


    正确答案:C

  • 第16题:

    Which of the following is closest to Juran's definition of Quality:

    A . conformance to requirements.

    B . fitness for use.

    C . continuous improvement.

    D . customer focus.

    E . All of the above.


    正确答案:B

  • 第17题:

    The auditing function that provides feedback about the quality of output is referred to as:

    A . quality control.

    B . quality planning.

    C . quality assurance.

    D . quality improvement

    E . All of the above.


    正确答案:C

  • 第18题:

    3 In order to achieve long-term quality improvements, management must do the following:

    A. Motivate the employees with seminars, contests, and institute programs such as "Quality Improvement' day.

    B Create a quality control department and give the head of the department ultimate responsibility for quality improvement.

    C. Implement of a formal quality control program with worker and management involvement.

    D. Establish financial incentive packages for worker.

    E. A and D


    正确答案:C

  • 第19题:

    16 Inspection of a complex project according to specifications is accomplished by _____.

    A. inspection by attributes.

    B cyclical inspection

    C. quality conformance inspection

    D. original inspection

    E. None of the above


    正确答案:C

  • 第20题:

    69 Non-conformance penalties are a form. of _____.

    A. quality incentive

    B. risk sharing

    C. contract negotiations

    D. quality assurance programs

    E. None of the above


    正确答案:C

  • 第21题:

    ● Scope management is:

    A a project control function.

    B employs change control.

    C a work authorization process.

    D considers Cost, Quality and Schedule.

    E All of the above.


    正确答案:E

  • 第22题:

    (c) Discuss the ethical responsibility of the company accountant in ensuring that manipulation of the statement

    of cash flows, such as that suggested by the directors, does not occur. (5 marks)

    Note: requirements (b) and (c) include 2 professional marks in total for the quality of the discussion.


    正确答案:
    (c) Companies can give the impression that they are generating more cash than they are, by manipulating cash flow. The way
    in which acquisitions, loans and, as in this case, the sale of assets, is shown in the statement of cash flows, can change the
    nature of operating cash flow and hence the impression given by the financial statements. The classification of cash flows
    can give useful information to users and operating cash flow is a key figure. The role of ethics in the training and professional
    lives of accountants is extremely important. Decision-makers expect the financial statements to be true and fair and fairly
    represent the underlying transactions.
    There is a fine line between deliberate misrepresentation and acceptable presentation of information. Pressures on
    management can result in the misrepresentation of information. Financial statements must comply with International
    Financial Reporting Standards (IFRS), the Framework and local legislation. Transparency, and full and accurate disclosure is
    important if the financial statements are not to be misleading. Accountants must possess a high degree of professional
    integrity and the profession’s reputation depends upon it. Ethics describe a set of moral principles taken as a reference point.
    These principles are outside the technical and practical application of accounting and require judgement in their application.
    Professional accountancy bodies set out ethical guidelines within which their members operate covering standards of
    behaviour, and acceptable practice. These regulations are supported by a number of codes, for example, on corporate
    governance which assist accountants in making ethical decisions. The accountant in Warrburt has a responsibility not to mask
    the true nature of the statement of cash flow. Showing the sale of assets as an operating cash flow would be misleading if
    the nature of the transaction was masked. Users of financial statements would not expect its inclusion in this heading and
    could be misled. The potential misrepresentation is unacceptable. The accountant should try and persuade the directors to
    follow acceptable accounting principles and comply with accounting standards. There are implications for the truth and
    fairness of the financial statements and the accountant should consider his position if the directors insist on the adjustments
    by pointing the inaccuracies out to the auditors.

  • 第23题:

    下列组合正确的是

    A.质量管理——quality control

    B.质量管理——quality management

    C.质量管理——quality assurance

    D.质量管理——quality circle

    E.质量管理——total quality management


    正确答案:B
    B。质量管理——quality management,就是制定质量计划,并为实现该计划所开展的一切活动的总和。