1 Which of the following is indicative of negative float?
A. The late start date is earlier than the early start date.
B. The critical path supports the imposed end date.
C. The early finish date is equal to the late finish date.
D. When leads are employed in the schedule.
E. The project is sinking
第1题:
The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:
A.Slack
B.Free float.
C.Restricted float.
D.Level float.
E.Lag
第2题:
22 The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:
A. Slack
B. Free float.
C. Restricted float.
D. Level float.
E. Lag
第3题:
144 Free float is the amount of time that an activity may be delayed with out affecting the _____.
A. Early start of the succeeding activities.
B. Late start of the succeeding activities.
C. Project finish.
D. Cost of the project.
E. None of the above
第4题:
194 The most frequently used construct in Precedent Diagramming Method is:
A. Start to Start.
B. Finish to Finish.
C. Start to Finish.
D. Finish to Start.
E. Dummy activity
第5题:
83 Which of the following is indicative of negative float?
A. The late start date is earlier than the early start date.
B. The critical path supports the imposed end date.
C. The early finish date is equal to the late finish date.
D. When leads are employed in the schedule.
E. The project is sinking.
第6题:
● The most frequently used construct in Precedent Diagramming Method is:
A Start to Start.
B Finish to Finish.
C Start to Finish.
D Finish to Start.
E Dummy activity.
第7题:
● Which may be employed to shorten a schedule without changing the scope of the task?
A Fast tracking.
B Crashing
C Releasing resources earlier from tasks which were scheduled with a late start.
D Alter to task priorities.
E A or B
第8题:
A.活动的总时差(float)
B.只有最早开始(early start)与最晚开始时间(late Start)
C.关键路径(critical path)
D.A和C
第9题:
Based on which two conditions can master Preventive Maintenance (PM) schedules be created?()
第10题:
Examine the description of the STUDENTS table: STD_ID NUMBER(4) COURSE_ID VARCHARD2(10) START_DATE DATE END_DATE DATE Which two aggregate functions are valid on the START_DATE column?()
第11题:
Total float for the activity is 9 days.
The early finish date ofthe activity is the end ofthe day on the 14th.
The late finish date is the 25th.
The activity can be completed in 2 days ifthe resources devoted to it are doubled.
第12题:
SUM(start_date)
AVG(start_date)
COUNT(start_date)
AVG(start_date, end_date)
MIN(start_date)
MAXIMUM(start_date)
第13题:
Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.
A . 11, 13
B . 12, 14
C . 13, 15
D . 14, 16
E . 15, 17
第14题:
106 All of the following are categories of a milestone in a schedule except:
A. End date.
B. Contract dates.
C. Key events scheduled.
D. Imposed dates.
E. Task duration
第15题:
177 Which may be employed to shorten a schedule without changing the scope of the task?
A. Fast tracking.
B. Crashing
C. Releasing resources earlier from tasks which were scheduled with a late start.
D. Alter to task priorities.
E. A or B
第16题:
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
A.Total float for the activity is 9 days.
B.The early finish date ofthe activity is the end ofthe day on the 14th.
C.The late finish date is the 25th.
D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.
第17题:
● Which of the following is indicative of negative float?
A The late start date is earlier than the early start date.
B The critical path supports the imposed end date.
C The early finish date is equal to the late finish date.
D When leads are employed in the schedule.
E The project is sinking.
第18题:
● The critical path is calculated by
A subtracting the end date of task one from the start date of task two.
B determining which tasks have the least amount of total slack.
C totaling the time for all activities.
D determining the shortest path through the network.
E Determining which tasks have the most slack
第19题:
● Free float is the amount of time that an activity may be delayed with out affecting the _____.
A Early start of the succeeding activities.
B Late start of the succeeding activities.
C Project finish.
D Cost of the project.
E None of the above.
第20题:
A. SUM(start_date)
B. AVG(start_date)
C. COUNT(start_date)
D. AVG(start_date, end_date)
E. MIN(start_date)
F. MAXIMUM(start_date)
第21题:
一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()
第22题:
活动的总时差(float)
只有最早开始(early start)与最晚开始时间(late Start)
关键路径(critical path)
A和C
第23题:
elapsed time since the target start date or completion date of previous work generated by PM
difference between completion date of previous work and system date is equal to Lead Time
elapsed time since the target start date or completion date of the latest work orders for the asset
metered equipment usage since the target start date or completion date of previous work generated by PM
metered equipment usage since the target start date or completion date of the latest work order for the asset