195 Risk mitigation involves all but which of the following:A. developing system standards (policies, procedure, responsibility standards)B. obtaining insurance against lossC. identification of project risksD. performing contingent planningE. developing p

题目

195 Risk mitigation involves all but which of the following:

A. developing system standards (policies, procedure, responsibility standards)

B. obtaining insurance against loss

C. identification of project risks

D. performing contingent planning

E. developing planning alternatives


相似考题
更多“195 Risk mitigation involves all but which of the following:A. developing system standards (policies, procedure, responsibility standards)B. obtaining insurance against lossC. identification of project risksD. performing contingent planningE. developing p”相关问题
  • 第1题:

    Obtaining team commitment depends on:

    A clear and interesting job assignments

    B consensus on project goals

    C involvement in developing task objectives

    D All of the above.

    E B and C


    正确答案:E

  • 第2题:

    Deflection involves the transfer of risk by:

    A Contracting out to another party

    B Developing schedule alternative.

    C Establishing functions under the project manager to handle risk events.

    D Disaster planning and responses.

    E None of the above.


    正确答案:A

  • 第3题:

    Which of the following areas are addressed in risk identification:

    A environmental

    B technical

    C legal

    D All of the above.

    E A and B only


    正确答案:D

  • 第4题:

    36 Which of the following areas are addressed in risk identification:

    A. environmental

    B. technical

    C. legal

    D. All of the above.

    E. A and B only


    正确答案:D

  • 第5题:

    113 Risk mitigation involves all but which of the following:

    A. developing system standards (policies, procedure, responsibility standards)

    B. obtaining insurance against loss

    C. identification of project risks

    D. performing contingent planning

    E. developing planning alternatives


    正确答案:C

  • 第6题:

    156 Deflection involves the transfer of risk by:

    A. Contracting out to another party

    B. Developing schedule alternative.

    C. Establishing functions under the project manager to handle risk events.

    D. Disaster planning and responses.

    E. None of the above


    正确答案:A

  • 第7题:

    25 Obtaining team commitment depends on:

    A. clear and interesting job assignments

    B. consensus on project goals

    C. involvement in developing task objectives

    D. All of the above.

    E. B and C


    正确答案:E

  • 第8题:

    ● Management plans include all of the following except:

    A Organization of project.

    B Job descriptions.

    C Policies and procedures.

    D Linear responsibility charts.

    E Scope baseline.


    正确答案:E

  • 第9题:

    Performing( )involves monitoring specific project results to determine ifthey comply with relevant quality standards and identifying ways to eliminate causes ofunsatisfactory results。 A.quality planning B.quality assurance C.quality performance D.quality control


    正确答案:D
    执行质量控制(quality control)指监控具体的项目结果,确定其是否符合相关的质量标准,并判断如何杜绝造成不合格结果的根源。

  • 第10题:

    Performing(74)involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

    A.quality planning

    B.quality assurance

    C.quality performance

    D.quality control


    正确答案:D
    解析:执行质量控制指监控具体的项目结果,确定其是否符合相关的质量标准,并判断如何杜绝造成不合格结果的根源。

  • 第11题:

    Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

    • A、qualityplanning
    • B、qualityassurance
    • C、qualityperformance
    • D、quality control

    正确答案:D

  • 第12题:

    Which of the following procedure should be performed prior to delivery and generally involves running a suite of operations so as to verify that the solution is applicable for production?()

    • A、Security Check
    • B、Acceptance Testing
    • C、Project Close Out
    • D、Systems Integration

    正确答案:B

  • 第13题:

    Risk mitigation includes all but which of the following:

    A Developing system (policies, procedures, responsibilities)

    B Obtaining insurance against loss

    C performing contingent planning

    D developing planning alternatives

    E identification of project risks.


    正确答案:E

  • 第14题:

    Risk mitigation involves all but which of the following:

    A developing system standards (policies, procedure, responsibility standards)

    B obtaining insurance against loss

    C identification of project risks

    D performing contingent planning

    E developing planning alternatives


    正确答案:C

  • 第15题:

    90 Management plans include all of the following except:

    A. Organization of project.

    B. Job descriptions.

    C. Policies and procedures.

    D. Linear responsibility charts.

    E. Scope baseline.


    正确答案:E

  • 第16题:

    108 Project Risk Management is based on which of the following premises:

    A. the future is unknown.

    B. unknowns can result in risks or opportunities.

    C. we cannot control risk events.

    D. project risk impact can be measured and controlled

    E. All of the above


    正确答案:E

  • 第17题:

    193 Creation of project objectives:

    A. allows for data collection and analysis and progress reporting against which standards of performance can be measured.

    B. is accomplished by selection of measurable variables against which performance can be judged. C. is required before funding of the project by the project sponsor.

    D. all of the above.

    E. A and B only


    正确答案:E

  • 第18题:

    166 Risk mitigation includes all but which of the following:

    A. Developing system (policies, procedures, responsibilities)

    B. Obtaining insurance against loss

    C. performing contingent planning

    D. developing planning alternatives

    E. identification of project risks


    正确答案:E

  • 第19题:

    172 Management plans include all of the following except:

    A. Organization of project.

    B. Job descriptions.

    C. Policies and procedures.

    D. Linear responsibility charts.

    E. Scope baseline


    正确答案:E

  • 第20题:

    (b) Discuss the nature of the following issues in developing IFRSs for SMEs.

    (i) The purpose of the standards and the type of entity to whom they should apply. (7 marks)


    正确答案:
    (b) There are several issues which need to be addressed when developing IFRSs for SMEs:
    (i) The purpose of the standards and type of entity
    The principal aim of the development of an accounting framework for SMEs is to provide a framework which generates
    relevant, reliable and useful information. The standards should provide high quality and understandable accounting
    standards suitable for SMEs globally. Additionally they should meet the needs set out in (a) above. For example reduce
    the financial reporting burden for SMEs. It is unlikely that one of the objectives would be to provide information for
    management or meet the needs of the tax authorities as these bodies will have specific requirements which would be
    difficult to meet in an accounting standard. However, it is likely that the standards for SMEs will be a modified version
    of the full IFRSs and not an independently developed set of standards in order that they are based on the same
    conceptual framework and will allow easier transition to full IFRS if the SME grows or decides to become a publicly listed
    entity.
    It is important to define the type of entity for which the standards are intended. Companies who have issued shares to
    the public would be expected to use full IFRS. The question arises as to whether SME standards should apply to all
    unlisted entities or just those listed entities below a certain size threshold. The difficulty with size criteria is that it would
    have to apply worldwide and it would be very difficult to specify such criteria. Additionally some unlisted companies, for
    example public utilities, have a reporting obligation that is equivalent to that of a listed company and should follow full
    IFRS.
    The main characteristic which distinguishes SMEs from other entities is the degree of public accountability. Thus the
    definition of what constitutes an SME could revolve around those entities that do not have public accountability.
    Indicators of public accountability will have to be developed. For example, a listed company or companies holding assets
    in a fiduciary capacity (bank), or a public utility, or an entity with economic significance in its country. Thus all entities
    that do not have public accountability may be considered as potential users of IFRSs for SMEs.
    Size may not be the best way to determine what is an SME. SMEs could be defined by reference to ownership and themanagement of the entity. SMEs are not necessarily just smaller versions of public companies.

  • 第21题:

    Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

    A.performing organization

    B.project management team

    C.project

    D.customer


    正确答案:A

  • 第22题:

    A key activity in closing out a project is to(47).

    A.Disseminate status reports and risk assessment.

    B.Disseminate information to formalize project completion.

    C.Monitor the specific project results to determine if they comply with relevant quality standards.

    D.Transfer all the project records to the project owners.


    正确答案:B
    解析:项目收尾时的一个关键活动是发布消息以正式确认项目完工。

  • 第23题:

    Which design phase service component consists of developing a detailed, site-specific plan for implementing a new technology system or solution? Select exactly 1 answer(s) from the following:()。

    • A、Detailed Design Development
    • B、Systems Acceptance Test Plan Development
    • C、Staging Plan
    • D、Implementation Plan Development
    • E、Project Kick-off

    正确答案:D