117 The project charter:A. Expresses upper management commitment to the project.B. Provides that authority by which the project will be run.C. Establishes that organizational structure with the project.D. Specifies overall objectives and timeframe. of the

题目

117 The project charter:

A. Expresses upper management commitment to the project.

B. Provides that authority by which the project will be run.

C. Establishes that organizational structure with the project.

D. Specifies overall objectives and timeframe. of the project.

E. All of the above


相似考题
更多“117 The project charter:A. Expresses upper management commitment to the project.B. Provides that authority by which the project will be run.C. Establishes that organizational structure with the project.D. Specifies overall objectives and timeframe. of the”相关问题
  • 第1题:

    130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

    A. Conceptual, charter/baseline.

    B. Conceptual, master schedule.

    C. Development, charter/baseline.

    D. Development, master schedule.

    E. Development, masterplan


    正确答案:A

  • 第2题:

    159 The project scope/charter baseline includes:

    A. Summary of background conditions defining the project.

    B. Organization, authority and responsibility relationships.

    C. Functions to be performed.

    D. Resource requirement schedule including time estimates.

    E. All of the above


    正确答案:E

  • 第3题:

    35 The project charter:

    A. Expresses upper management commitment to the project.

    B. Provides that authority by which the project will be run.

    C. Establishes that organizational structure with the project.

    D. Specifies overall objectives and timeframe. of the project.

    E. All of the above


    正确答案:E

  • 第4题:

    125 Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?

    A. Project.

    B. Strong matrix.

    C. Weak matrix.

    D. Project coordinator.

    E. Project expeditor


    正确答案:C

  • 第5题:

    ● The project charter:

    A Expresses upper management commitment to the project.

    B Provides that authority by which the project will be run.

    C Establishes that organizational structure with the project.

    D Specifies overall objectives and timeframe. of the project.

    E All of the above.


    正确答案:E

  • 第6题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第7题:

    A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

    A.Structure Chart

    B.Organizational Structure

    C.Work Breakdown Structure

    D.Functional decomposition diagram


    正确答案:C

  • 第8题:

    The (73) provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B

  • 第9题:

    ( )is a process developing a document that formally authorizes the existence of a project and provides the
    project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor and Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第10题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、project charter

    正确答案:D

  • 第11题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、projectcharter

    正确答案:D

  • 第12题:

    单选题
    The()provides the project manager with the authority to apply organizational resources to project activities.
    A

    project management plan

    B

    contract

    C

    project human resource plan

    D

    project charter


    正确答案: A
    解析: 项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第13题:

    156 Expectancy theory as applied to project management implies that:

    A. The team will work the hardest on those goals that are clearly explained by the project manager

    B. The more rewards that the project manager provides, the better the performance of the team

    C. Team members will work hardest for those project goals that also bring satisfaction to personal goals

    D. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members E. None of the above


    正确答案:C

  • 第14题:

    29 The WBS is:

    A. An organization oriented family tree of the project.

    B. A task oriented family tree of the project.

    C. A cost centered structure of the project.

    D. Only required on large complex projects where separately identifiable work packages are difficult to construct.

    E. None of the above


    正确答案:B

  • 第15题:

    43 Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?

    A. Project.

    B. Strong matrix.

    C. Weak matrix.

    D. Project coordinator.

    E. Project expeditor.


    正确答案:C

  • 第16题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    A.Project

    B.project management team

    C.performingorganization

    D.customer


    参考答案:C

    该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • 第17题:

    The(70)provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.contract

    C.project human resource plan

    D.project charter


    正确答案:D
    解析:项目章程为项目经理使用组织资源进行项目活动提供了授权。

  • 第18题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第19题:

    Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

    A.performing organization

    B.project management team

    C.project

    D.customer


    正确答案:A

  • 第20题:

    A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

    A.Functional decomposition diagram
    B.Work Breakdown Structure
    C.Structure Chart
    D.Organizational Structure

    答案:B
    解析:

  • 第21题:

    ( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

    A.Develop Project Charter
    B.Manage Project Knowledge
    C.Monitor anD.Control Project work
    D.Close project

    答案:A
    解析:
    制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

  • 第22题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    • A、Project
    • B、project management team
    • C、performingorganization
    • D、customer

    正确答案:C

  • 第23题:

    单选题
    The()provides the project manager with the authority to apply organizational resources to project activities.
    A

    project management plan

    B

    contract

    C

    project human resource plan

    D

    projectcharter


    正确答案: D
    解析: 该题的关键词为"authority to apply organizational resources",其语句结构为"The____(主语)provides(谓语)the project manager with the authority to apply organizationalresources",含义为"什么为项目经理提供了使用组织资源的权力",根据项目管理知识,为项目经理授权的文件为项目章程,所以应该选择选项D,其他选项容易排除。