● Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.
A Reduce.
B Eliminate.
C Double
D Increase
E Not affect
第1题:
The utility of network-based schedules:
A.Reveals interdependencies.
B.Facilitates "what if" exercises.
C.Highlights critical activities.
D.Provides information on resource requirements, time requirements and tradeoffs.
E.All of the above.
第2题:
The "buy or make" decision is usually made during the:
A acquisition cycle
B contract evaluation cycle
C requirements cycle
D pre-award cycle
E at any time that is convenient for the project manager
第3题:
90 Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.
A. Reduce.
B. Eliminate.
C. Double
D. Increase
E. Not affect
第4题:
● Resource leveling _____.
A Allocates resources to activities to find shortest schedule within fixed resource limits.
B Smoothes out resource requirements by rescheduling activities within their float time.
C Smooths out resource requirements by substituting activities with unassigned resources.
D Attempts to reduce resource requirements within a constraint on project duration
E B or D
第5题:
● The critical path in a schedule network is the path that:
A Takes the longest time to complete
B Must be done before any other tasks
C Allows some flexibility in scheduling a start time.
D Is not affected by schedule slippage
E All of the above.
第6题:
What can we conclude from Stafford’s research?
A. Marriage gives men more freedom.
B. Marriage has effects on job choices.
C. Housework sharing changes over time.
D. Having children means doubled housework.
第7题:
Those pupils who take an excessive interest in computer games ought to spend more time on ____ readings.
A. complex
B. radical
C. worthwhile
D. permanent
第8题:
The vessel ______ all ABS Rule structural requirements in effect at the time it was built.
A.had
B.made
C.did
D.met
第9题:
第10题:
哪些情形我们认为不属于紧急情况()
第11题:
Unless
Until
While
Since
第12题:
It enables her to read faster than average.
She likes to reread a sentence from time to time.
She tends to skip sentences with bright colors.
第13题:
A.expect
B.expedite
C.exercise
D.examine
第14题:
67 As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
A. Insignificant.
B. Reduced.
C. Unchanged.
D. Increased.
E. Doubled
第15题:
171 Resource leveling _____.
A. Allocates resources to activities to find shortest schedule within fixed resource limits.
B. Smoothes out resource requirements by rescheduling activities within their float time.
C. Smooths out resource requirements by substituting activities with unassigned resources.
D. Attempts to reduce resource requirements within a constraint on project duration
E. B or D
第16题:
● As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
A Insignificant.
B Reduced.
C Unchanged.
D Increased.
E Doubled.
第17题:
Which of the following qualities or abilities is related to reliability, professionalism or work ethics?
A.Time management.
B.Flexibility.
C.Commitment.
D.Team play.
第18题:
下列哪个选项是正确计算42度(角度)的余弦值()。
A.doubled=Matcos(42);
B.doubled=Matcosine(42);
C.doubled=Matcos(MattoRadians(42));
D.doubled=Matcos(MattoDegrees(42));
第19题:
A.floatf=11.1;
B.doubled=5.3E12;
C.doubled=3.14159;
D.doubled=3.14;.
第20题:
第21题:
Each time the distance from the speaker is doubled, volume decreases by().
第22题:
You are creating a view to join the Customers and Orders tables in a SQL Server 2005 database. You need to ensure that the view cannot be affected by modifications to underlying table schemas. You want to accomplish this goal by using the least possible amount of overhead. What should you do?()
第23题:
decreased clearances between rotating parts
decreased slippage to the suction side of the pump
air binding in the discharge ports
erosion and excessive wear