A situation in which one of two or more risk events will follow an act, but the precise nature of these events maynot be known and the probabilities of their occurring cannot be objectively assigned, is the definition of:a. Certaintyb. Uncertaintyc. Riskd

题目

A situation in which one of two or more risk events will follow an act, but the precise nature of these events may

not be known and the probabilities of their occurring cannot be objectively assigned, is the definition of:

a. Certainty

b. Uncertainty

c. Risk

d. Risk adversity

e. None of the above


相似考题
更多“A situation in which one of two or more risk events will follow an act, but the precise nature of these events maynot be known and the probabilities of their occurring cannot be objectively assigned, is the definition of:a. Certaintyb. Uncertaintyc. Riskd”相关问题
  • 第1题:

    Total project risk can be defined as:

    A the sum of the probabilities of project risks events times the sum of consequences of those risks

    B the sum of the products of each project risk event times its consequences

    C the sum of the consequences of all project risk events

    D the sum of the probabilities of all project risk events

    E 1 - the sum of the probabilities of all project risk events.


    正确答案:B

  • 第2题:

    109 Uncertainty refers to a situation where:

    A. the outcomes are known but their probabilities are high

    B. the outcomes and their probabilities are known

    C. neither the outcomes nor their probabilities are known

    D. states of nature can change at any time

    E. probabilities of various states of nature can change at any time


    正确答案:C

  • 第3题:

    108 Project Risk Management is based on which of the following premises:

    A. the future is unknown.

    B. unknowns can result in risks or opportunities.

    C. we cannot control risk events.

    D. project risk impact can be measured and controlled

    E. All of the above


    正确答案:E

  • 第4题:

    144 Risk event probability is defined as:

    A. the total number of possible events divided into the expectations or frequency of the risk event

    B. the number of times the risk event may occur

    C. the fraction of the total project tasks which may be affected by the risk event

    D. the total number of possible events divided into the consequences of the risk event.

    E. A and B


    正确答案:A

  • 第5题:

    170 Project Risk _____ .

    A. should not be calculated for small projects.

    B. is the probability of each risk event minus the sum of the consequences of potential risk events.

    C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.

    D. cannot be quantified for first time projects.

    E. B or D


    正确答案:C

  • 第6题:

    Which two statements are true about a job chain? ()(Choose two.)

    A. A job chain can contain a nested chain of jobs.

    B. The jobs in a job chain cannot have more than one dependency.

    C. A job of the CHAIN type can be run using event-based or time-based schedules.

    D. The jobs in a job chain can be executed only by using the events generated by the Scheduler


    参考答案:A, C

  • 第7题:

    Consider the events_% tables in performance Schema. Which two methods will clear or reset the collected events in the tables?()

    • A、Using DELETE statements, for example, DELETE FROM performance_schema.events_watis_current
    • B、Using the statement RESET PERFORMANCE CACHE
    • C、Using the statement FLUSH PERFORMANCE CACHE
    • D、Using TRUNCATE statements, for example, TRUNATE TABLE performance_schema.events_waits_current
    • E、Disabling and re-enabling all instruments
    • F、Restarting Mysql

    正确答案:D,F

  • 第8题:

    Which two statements are true about a job chain? ()(Choose two.)

    • A、A job chain can contain a nested chain of jobs.
    • B、The jobs in a job chain cannot have more than one dependency.
    • C、A job of the CHAIN type can be run using event-based or time-based schedules.
    • D、The jobs in a job chain can be executed only by using the events generated by the Scheduler

    正确答案:A,C

  • 第9题:

    Which two statements are true about a job chain?()

    • A、 A job chain can contain a nested chain of jobs
    • B、 The jobs in a job chain cannot have more than one dependency
    • C、 A job of the CHAIN type can be run using event-based or time-based schedules
    • D、 The jobs in a job chain can be executed only by using the events generated by the Scheduler

    正确答案:A,C

  • 第10题:

    多选题
    Which two statements are true about a job chain?()
    A

    A job chain can contain a nested chain of jobs.

    B

    The jobs in a job chain cannot have more than one dependency.

    C

    A job of the CHAIN type can be run using event-based or time-based schedules.

    D

    The jobs in a job chain can be executed only by using the events generated by the Scheduler


    正确答案: D,B
    解析: 暂无解析

  • 第11题:

    多选题
    Which two statements are true about a job chain?()
    A

    A job chain can contain a nested chain of jobs

    B

    The jobs in a job chain cannot have more than one dependency

    C

    A job of the CHAIN type can be run using event-based or time-based schedules

    D

    The jobs in a job chain can be executed only by using the events generated by the Scheduler


    正确答案: A,D
    解析: 暂无解析

  • 第12题:

    多选题
    Consider the events_% tables in performance Schema. Which two methods will clear or reset the collected events in the tables?()
    A

    Using DELETE statements, for example, DELETE FROM performance_schema.events_watis_current

    B

    Using the statement RESET PERFORMANCE CACHE

    C

    Using the statement FLUSH PERFORMANCE CACHE

    D

    Using TRUNCATE statements, for example, TRUNATE TABLE performance_schema.events_waits_current

    E

    Disabling and re-enabling all instruments

    F

    Restarting Mysql


    正确答案: D,E
    解析: 暂无解析

  • 第13题:

    Uncertainty refers to a situation where:

    A the outcomes are known but their probabilities are high

    B the outcomes and their probabilities are known

    C neither the outcomes nor their probabilities are known

    D states of nature can change at any time

    E probabilities of various states of nature can change at any time


    正确答案:C

  • 第14题:

    15 Total project risk can be defined as:

    A. the sum of the probabilities of project risks events times the sum of consequences of those risks

    B. the sum of the products of each project risk event times its consequences

    C. the sum of the consequences of all project risk events

    D. the sum of the probabilities of all project risk events

    E. 1 - the sum of the probabilities of all project risk events


    正确答案:B

  • 第15题:

    122 Total Project Risk:

    A. should not be calculated for small projects

    B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

    C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

    D. A and B

    E. A and C


    正确答案:C

  • 第16题:

    113 Screening of risk events for potential risk is known as _____ .

    A. problem structuring.

    B. risk identification

    C. risk quantification

    D. risk modeling

    E. risk mitigation


    正确答案:B

  • 第17题:

    Which two statements are true about a job chain?()

    A. A job chain can contain a nested chain of jobs.

    B. The jobs in a job chain cannot have more than one dependency.

    C. A job of the CHAIN type can be run using event-based or time-based schedules.

    D. The jobs in a job chain can be executed only by using the events generated by the Scheduler


    参考答案:A, C

  • 第18题:

    You have been tasked with creating Business Events for an E-Business Suite workflow project. Whatwould you use to create your Business Events?()

    A. Oracle Workflow Builder

    B. Oracle Workflow Definition Loader

    C. Oracle Business Event Definition Loader

    D. Workflow Administrator Web page in E-Business Suite


    参考答案:D

  • 第19题:

    Which two statements are true about a job chain?()

    • A、A job chain can contain a nested chain of jobs.
    • B、The jobs in a job chain cannot have more than one dependency.
    • C、A job of the CHAIN type can be run using event-based or time-based schedules.
    • D、The jobs in a job chain can be executed only by using the events generated by the Scheduler

    正确答案:A,C

  • 第20题:

    Which two statements are true regarding transactions in an Oracle database()

    • A、Multiple transactions can use the same undo segment.
    • B、A transaction is assigned an undo segment when it is started.
    • C、More than one transaction cannot share the same extent in the undo tablespace.
    • D、The transactions use system undo segment to store undo data if all the segments in the undo tablespaceare used.

    正确答案:A,B

  • 第21题:

    You are developing an application that receives events asynchronously.You create a WqlEventQuery instance to specify the events and event conditions to which the application must respond.You also create a ManagementEventWatcher instance to subscribe to events matching the query.You need to identify the other actions you must perform before the application can receive events asynchronously.Which two actions should you perform?()

    • A、Start listening for events by calling the Start method of the ManagementEventWatcher.
    • B、Set up a listener for events by using the EventArrived event of the ManagementEventWatcher.
    • C、Use the WaitForNextEvent method of the ManagementEventWatcher to wait for the events.
    • D、Create an event handler class that has a method that receives an ObjectReadyEventArgs parameter.
    • E、Set up a listener for events by using the Stopped event of the ManagementEventWatcher.

    正确答案:A,B

  • 第22题:

    多选题
    Which two statements are true about a job chain? ()(Choose two.)
    A

    A job chain can contain a nested chain of jobs.

    B

    The jobs in a job chain cannot have more than one dependency.

    C

    A job of the CHAIN type can be run using event-based or time-based schedules.

    D

    The jobs in a job chain can be executed only by using the events generated by the Scheduler


    正确答案: B,A
    解析: 暂无解析

  • 第23题:

    单选题
    Which of the two events listed occurs simultaneously in a two-stroke/cycle diesel engine?()
    A

    Exhaust and scavenging

    B

    Scavenging and compression

    C

    Ignition and expansion

    D

    Exhaust and compression


    正确答案: A
    解析: 暂无解析