Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT B.Resource levelling C.Schedule compression D.Critical chain method

题目

Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.

A.PERT B.Resource levelling C.Schedule compression D.Critical chain method


相似考题
更多“Many useful tools techniques are used in developing schedule. ( )s a schedule network anal ”相关问题
  • 第1题:

    ● (73) is one of the techniques used for estimating activity durations.

    (73)

    A.Analogous Estimating

    B.Precedence Diagramming Method (PDM)

    C.Dependency Determination

    D.Schedule network Templates


    正确答案:A
    试题(73)分析
        下列用于活动历时估算的技术是答案A类比估算法。
    参考答案
        (73)A

  • 第2题:

    ● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.

    (72)

    A.PERT

    B.Resource levelling

    C.Schedule compression

    D.Critical chain method


    正确答案:D
    试题(72)分析
     在制定项目进度计划中有很多有用的方法和工具。如下:
     PERT方法能协调整个计划的各道工序,通过描绘出项目包含的各种活动的先后次序,标明每项活动的时间或相关的成本,合理安排人力、物力、时间、资金,加速计划的完成;
     Schedule compression进度压缩,是通过赶工、快速跟进等方法压缩工期,是在不改变项目范围条件下缩短项目进度的途径;
     Critical chain method关键路径法计算所有计划活动理论上的最早开始与完成时间、最迟开始与完成时间,寻找活动的关键路径,通过调整关键路径进行进度制定;
     Resource levelling资源平衡是根据有限资源调整项目进度的方法。
     所以选D。
    参考答案
    (72)D

  • 第3题:

    According to Paul Leedy (1993: 17-42), which tools thatare useful for collecting a/the data are used by researchers?()

    A.The Library

    B.The Computer

    C.Measurement

    D.Statistics and Language


    正确答案:ABCD

  • 第4题:

    Which of the following tools can be used to schedule a backup operation that is to be run every Sunday evening?()

    A.Journal

    B.Task Center

    C.Activity Monitor

    D.Command Line Processor


    参考答案:B

  • 第5题:

    ( )techniques are used to find ways to bring project activities that are alignment with the plan by fast tracking or crashing the schedule for the remaining work.

    A.Schedule forecasts
    B.Schedule compression
    C.Change requests
    D.Data analysis

    答案:B
    解析:
    翻译:( )技术用于通过快速跟踪或崩溃剩余工作的计划来找到使落后的项目活动与计划保持一致的方法。A、进度预测 B、进度压缩 C、变更请求 D、数据分析

  • 第6题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.

    A.activity duration estimating, schedule developing, activity resource estimating
    B.activity resource estimating, activity duration estimating, schedule development
    C.schedule developing, activity resource estimating, activity duration estimating
    D.activity resource estimating, schedule developing, activity duration estimating

    答案:B
    解析:
    项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制订进度计划及进度控制6个步骤。以上6个步骤具有先后顺序,因此选择“活动的资源估算”、“活动历时估算”、制订进度计划,所以选B。(71) A.活动历时估算 制订进度计划 活动的资源估算 B.活动的资源估算 活动历史估算 制订进度计划 C.制订进度计划 活动的资源估算 活动历时估算 D.活动的资源估算 制订进度计划 活动历时估算

  • 第7题:

    Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.

    A.PERT
    B.Resource levelling
    C.Schedule compression
    D.Critical chain methoD.

    答案:D
    解析:
    PERT方法能协调整个计划的各道工序,通过描绘出项目包含的各种活动的先后次序,标明每项活动的时间或相关的成本,合理安排人力、物力、时间、资金,加速计划的完成。(72) A.PERT B.资源平衡 C.进度压缩 D.关键路径法

  • 第8题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

    • A、activity duration estimating, schedule developing, activity resource estimating
    • B、activity resource estimating, activity duration estimating, schedule development
    • C、schedule developing, activity resource estimating, activity duration estimating
    • D、activity resource estimating, schedule developing, activity duration estimating

    正确答案:B

  • 第9题:

    The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()

    • A、Data flow model
    • B、The project critical path
    • C、Resource loading chart
    • D、WBS (Work Breakdown Structure)

    正确答案:B

  • 第10题:

    Which of the following tools should be used to report current network status and is often used to check the reliability of a network?()

    • A、 netpmon
    • B、 netstat
    • C、 nfsstat
    • D、 vmstat

    正确答案:B

  • 第11题:

    单选题
    Which of the following tools should be used to report current network status and is often used to check the reliability of a network?()
    A

     netpmon

    B

     netstat

    C

     nfsstat

    D

     vmstat


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    A system administrator is trying to troubleshoot company wide email problems that may be related to DNS.  Which of the following network tools would be MOST useful to determine if it is a DNS issue?()
    A

    netstat

    B

    tracert

    C

    nslookup

    D

    ping


    正确答案: B
    解析: 暂无解析

  • 第13题:

    ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

    (71)

    A.activity duration estimating, schedule developing, activity resource estimating

    B . activity resource estimating, activity duration estimating, schedule development

    C.schedule developing, activity resource estimating, activity duration estimating

    D.activity resource estimating, schedule developing, activity duration estimating


    正确答案:B
    试题(71)分析
     项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
     项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
     以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule                 development,所以选B。
    参考答案
    (71)B

  • 第14题:

    ______is one of the techniques used for estimating activity durations.

    A.Analogous Estimating

    B.Precedence Diagramming Method(PDM)

    C.Dependency Determination

    D.Schedule network Templates


    正确答案:A
    解析:下列用于活动历时估算的技术是答案A类比估算法。

  • 第15题:

    Difficult _____ the project was, I managed to finish it on schedule.

    A: no matter

    B: as

    C: despite

    D: though


    正确答案: B

  • 第16题:

    ??Many useful tools and techniques are used in developing schedule.( 73) is a schedule

    network analysis technique that modifies the project schedule to account for limited resource

    ??

    A.PERT

    B. Resource levelling

    C.Schedule compression

    D.Critical chain method


    正确答案:B
    本题考查制定项目计划时有限资源的安排技术、计划评审技术、资源平衡法、进度压缩、关键路径法。资源平衡是一种进度网络分析技术,用于已经利用关键路线法分析过的进度模型。资源平衡使用场景一般如下:处理时间安排需要满足规定交工日期的计划活动:处理只有在某些时间动用或只能动用有限数量的必要的共用或关键资源数量;处理在项目工作具体时间段内按照某种水平均匀地使用选定资源;资源平衡核心在于将稀缺资源首先用到关键路线的关键活动。此外,可以考虑加班和提高资源的生产率。所以答案选B。

  • 第17题:

    A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations.

    (74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.

    A. Duration analysis,activity-baseD.costing anD.informal bench marking
    B.Outcome analysis, technology analysis anD.activity elimination
    C.Problem analysis, root cause analysis anD.critical path analysis
    D.Cost-benefit analysis, schedule analysis anD.risk analysis

    答案:A
    解析:
    可以使用各种工具来帮助分析师发现用户的真实需求。基于在待系统中预期的变化程度可以将这些工具分为三种。在业务需求中强调采用计算机技术,因此而采用了业务流程(71)技术,该技术使用了两种通用的活动分别是(72)。业务流程(73)意味着基本业务需求针对组织运营的适度变化。(74)是该技术的三大活动。业务流程(75)是利用新思路和新技术来改变商业活动方式。(71) A.自动化 B.建模 C.实施 D.重建(72) A.过程分析和结果分析 B.问题分析和根本原因分析 C.技术分析和作业消除 D.基于活动的成本和非正式的标杆分析法(73) A.自动化 B.建模 C.改进 D.重建(74) A. 持续时间分析,基于活动的成本核算和非正式的基准测试 B.结果分析,技术分析和作业消除 C.问题分析和根本原因分析和关键路径分析 D.成本效益分析, 进度分析和风险分析 (75) A.自动化 B.建模 C.实施 D.重建

  • 第18题:

    Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.

    A.PERT
    B.Resource levelling
    C.Schedule compression
    D.Critical chain methoD.

    答案:D
    解析:
    PERT方法能协调整个计划的各道工序,通过描绘出项目包含的各种活动的先后次序,标明每项活动的时间或相关的成本,合理安排人力、物力、时间、资金,加速计划的完成。A. PERT B. 资源平衡C. 进度压缩 D. 关键链法

  • 第19题:

    You are responsible for implementing maintenance jobs on a SQL Server 2005 database server. Certain jobs run every Sunday and other jobs run at the beginning of every month.  You need to schedule the jobs in the way that uses the least amount of administrative effort.  What should you do? ()

    • A、 Create a job schedule that runs every Sunday. Assign weekly tasks to this schedule. Create a second schedule that runs on the first day of every month. Assign monthly tasks to this schedule. 
    • B、 Create a job for each task that runs once a day. Use a Transact-SQL statement to check the date and day of the week. If the day is either a Sunday or the first day of the month, execute the code. 
    • C、 Create a job schedule that runs once a day. Assign jobs to this job schedule. If the day is either a Sunday or the first day of the month, execute the jobs. 
    • D、 Create a job for each task that runs once a week on Sunday. Add a second job schedule that runs the job on the first of the month.

    正确答案:A

  • 第20题:

    Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.

    • A、PERT
    • B、Resourceleveling
    • C、Schedulecompression
    • D、Critical chain method

    正确答案:D

  • 第21题:

    Which of the following tools can be used to identify the location of a network outage?()

    • A、traceroute
    • B、netstat
    • C、nslookup
    • D、ping

    正确答案:A

  • 第22题:

    Which of the following tools can be used to schedule a backup operation that is to be run every Sunday evening?()

    • A、Journal
    • B、Task Center
    • C、Activity Monitor
    • D、Command Line Processor

    正确答案:B

  • 第23题:

    单选题
    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
    A

    activity duration estimating, schedule developing, activity resource estimating

    B

    activity resource estimating, activity duration estimating, schedule development

    C

    schedule developing, activity resource estimating, activity duration estimating

    D

    activity resource estimating, schedule developing, activity duration estimating


    正确答案: A
    解析: 暂无解析