In project time management processes,( )involves identifying and documenting the relationships between project activities.A.activity definitionB.activity sequencingC.schedule controlD.Schedule development

题目

In project time management processes,( )involves identifying and documenting the relationships between project activities.

A.activity definition

B.activity sequencing

C.schedule control

D.Schedule development


相似考题
更多“In project time management processes,( )involves identifying and documenting the relati ”相关问题
  • 第1题:

    ● The inputs of developing project management plan do not include (72).

    (72)

    A. project charter

    B. stakeholder management strategy

    C. project scope statement

    D. outputs from planning processes


    正确答案:B

  • 第2题:

    The inputs of developing project management plan do not include (72) .

    A.project charter

    B.stakeholder management strategy

    C.project scope statement

    D.outputs from planning processes


    正确答案:B

  • 第3题:

    Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning D.Communication


    正确答案:D
    项目沟通管理是使用所需过程以确保及时、恰当地产生、收集、分发、存储、收回和最终处置项目信息的知识域。

  • 第4题:

    Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

    A.performing organization

    B.project management team

    C.project

    D.customer


    正确答案:A

  • 第5题:

    ● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)

    (74)

    A. Scope Planning

    B. Scope Verification

    C. Scope Change Control

    D. Scope Definition


    正确答案:D

  • 第6题:

    In project time management,activity definition is the process of identifying and documenting the specification to be performed to produce the project deliverables.( )are not output of activity definition.

    A.Activity list
    B.Work Break down Structures
    C.Activity Attributes
    D.Mile stone Lists

    答案:B
    解析:
    翻译:在项目管理中,活动定义是识别和记录项目可交付物而采取的具体行动的过程。( )不是活动定义的输出。A.活动清单 B.工作分解结构 C.活动属性 D.里程碑清单

  • 第7题:

    ()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.

    A.identify risks
    B.monitor risks
    C.implement risks responses
    D.plan risk management

    答案:A
    解析:
    翻译:()是识别单个项目风险以及整个项目风险的来源,并记录其特征的过程。
    A.识别风险
    B.监控风险
    C.实施风险应对措施
    D.计划风险管理
    识别风险是识别单个项目风险以及整个项目风险的来源,并记录其特征的过程。

  • 第8题:

    Configuration management is focused on the specification of both the deliverables and the processes;while( )is focused on identifying,documenting,and approving or rejecting changes to the project documents,deliverables,or baselines.

    A.cost management
    B.change management
    C.configuration management
    D.capacity management

    答案:B
    解析:

  • 第9题:

    ( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.

    A.Integrated management
    B.Configuration management
    C.Scope management
    D.Requirements management

    答案:D
    解析:
    需求管理是一个记录的过程。对需求进行分析、描绘、划分优先顺序,达成需求并控制其变化、并传达给利益相关者,它在项目中是一个持续的过程。

  • 第10题:

    The inputs of developing project management plan do not include()

    • A、project charter
    • B、stakeholder management strategy
    • C、project scope statement
    • D、outputs from planning processes

    正确答案:B

  • 第11题:

    单选题
    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
    A

    Project

    B

    project management team

    C

    performingorganization

    D

    customer


    正确答案: B
    解析: 该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • 第12题:

    单选题
    The inputs of developing project management plan do not include()
    A

    project charter

    B

    stakeholder management strategy

    C

    project scope statement

    D

    outputs from planning processes


    正确答案: B
    解析: 中文解释:制定项目管理计划的输入不包括 A.项目章程 B.干系人管理策略 C.项目范围说明书 D.计划过程输出

  • 第13题:

    Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

  • 第14题:

    The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes


    正确答案:B
    制定项目管理计划的输入不包括干系人管理策略(stakeholder management strategy)。

  • 第15题:

    Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.

    A.Developing project charter

    B.Developing project management plan

    C.Analyzing project risks

    D.Monitoring and controlling project


    正确答案:C

  • 第16题:

    Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    A.Integration

    B.Scope

    C.Configuration

    D.Requirement


    正确答案:B
    解析:项目范围管理包括为确保项目包含且仅包含成功完成项目必需工作的所需过程。

  • 第17题:

    In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.

    A.Activity list

    B.Work Breakdown Structures

    C.Activity Attributes

    D.Milestone Lists


    正确答案:B

  • 第18题:

    The inputs of developing project management plan do not include()

    A.project charter
    B.stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括:A.项目章程 B.利益相关者管理策略 C.项目范围描述 D.计划过程输出

  • 第19题:

    Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()

    A.Scope Planning
    B.Scope Verification
    C.Scope Change Control
    D.Scope Definition

    答案:D
    解析:
    在以下项目范围管理几个过程中,(74)涉及将主要项目可交付成果细分成更小、更容易管理的组件单元。A.范围规划B.范围确认C.范围变更控制D.范围定义

  • 第20题:

    The inputs of developing project management plan do not include ().

    A.project charter
    B.stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括 () 。
    A.项目章程 B.干系人管理策略
    C.项目范围说明书 D.计划过程输出

  • 第21题:

    ( ) is primarily concerned with defining and controlling what is and is not included in the project.

    A.Project Time Management
    B.Project Cost Management
    C.Project Scope Management
    D.Project Communications Management

    答案:C
    解析:
    项目范围管理是项目管理(包括时间、成本、沟通)的基础。

    项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。

    选项A是项目时间管理,选项B是项目成本管理,选项C是项目范围管理,选项D是项目沟通管理。因此应选择C。

  • 第22题:

    Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:D

  • 第23题:

    单选题
    Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.
    A

    qualityplanning

    B

    qualityassurance

    C

    qualityperformance

    D

    quality control


    正确答案: A
    解析: 该题的关键词为"monitoring specific project results. comply with relevant qualitystandards. eliminate causes ofunsatisfactory results",其语句结构为"Performing______(主语)involves(谓语)monitoring specific project results",含义为"执行什么包括监督特定的项目结果",再结合关键词分析,正是质量控制的特征,应该选择选项D。